General Announcement:
- XO thank the effort made by preparing the activity lists for the maintenance period. In few cases XO is contacting groups back with questions and/or comments.
- The Winter maintenance period was adjusted yesterday. The ending period is now on January 13th, 2021, instead of January 4th.
CTRL:
- CTRL is reaching conclusions on recent Beckhoff problems:
1. CTRL would like to upgrade most of installations in instruments next week (upgrade of motors software). This upgrade is in general a step forward for the PLC
connections when it is dropped (re-starting).
2. For SASE installations, CTRL will make next week during machine days.
3. The GATT will not be upgraded now – this will start during Winter maintenance period. Upgrade of GATT is a priority for CTRL (has been added to the maintenance list
submitted to XO).
DA:
- Nothing to report.
EEE:
- Intervention in SA3 PP-laser was done.
VAC:
- No new issues to report.
- Maintenance on SA3 vacuum loop: in case of problems, one has to restart in PLC level with EEE staff and may result a bit longer recovery.
Steffen H. comments it has been worked on and may be solved in the next day or so. The restart procedure is easy but lengthy. CTRL/OCD knows what to do.
XPD:
- One of vacuum pumps lost Beckhoff connection.
DET:
- Nothing to report.
ITDM:
- Nothing to report.
XRO:
- Nothing to report.
LAS:
- Nothing to report.
UNSYS:
- Nothing to report.
SPB:
- Not present.
FXE:
- Nothing to report.
MID:
- All is super at MID.
HED:
- All sounds great at the moment.
SCS:
- Nothing to report.
SQS:
- Nothing to report. |