Technical integration and coordination
|
| Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther |
Not logged in |
 |
|
|
Message ID: 351
Entry time: 22 Aug 2022, 09:50
|
| Author: |
Frederik Wolff-Fabris |
| Location: |
General |
| Severity: |
Information |
| Subject: |
Notes XO Integration Meeting 21.03.2022 |
|
|
General Announcement:
- Power glitch on Saturday morning took two cryo streets down and beam was recovered more than 24:00 later.
- Naresh K. as PRC reminds instruments to retract CRLs and place beamlines in safe state after ending the beamtime on Mondays.
- P. Schmidt as DRC reports that minor issues were addressed on Sunday after beam was back.
CTRL:
- Nothing to report.
DA:
- Nothing to report.
EEE:
- PLC team busy today for testing the tunnel PNACT remotely.
- SA3 PLC master upgrade also happening today from 10:00.
VAC:
- Saturday's power glitch did not affect any vacuum devices this time.
XPD:
- Nothing to report.
- Naresh K., as PRC, reports MID got 30mins more beam as agreed with operators.
DET:
- Nothing to report.
ITDM:
- Nothing to report.
XRO:
- Nothing to report.
LAS:
- Ask SCS for confirmation if it is needed to change PP-laser rep rate this week. SCS will confirm later.
UNSYS:
- Nothing to report.
SPB:
- Intervention last night was advertised 20 mins but took 1 hour.
FXE:
- Issue with digitizers for detector was solved.
MID:
- User experiment on THU/FRI went good.
- Second user experiment on SAT/SUN received about 12hs of beam delivery; no outcome.
HED:
- Nothing to report.
SCS:
- Suffered from downtime.
SQS:
- Nothing to report. |