Technical integration and coordination SASE1 Status and SASE3 Readiness
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 351     Entry time: 22 Aug 2022, 09:50
Author: Frederik Wolff-Fabris 
Location: General 
Severity: Information 
Subject: Notes XO Integration Meeting 21.03.2022 
General Announcement:
- Power glitch on Saturday morning took two cryo streets down and beam was recovered more than 24:00 later.
- Naresh K. as PRC reminds instruments to retract CRLs and place beamlines in safe state after ending the beamtime on Mondays.
- P. Schmidt as DRC reports that minor issues were addressed on Sunday after beam was back.

CTRL:
- Nothing to report.

DA:
- Nothing to report.

EEE:
- PLC team busy today for testing the tunnel PNACT remotely.
- SA3 PLC master upgrade also happening today from 10:00.

VAC:
- Saturday's power glitch did not affect any vacuum devices this time.

XPD:
- Nothing to report.
- Naresh K., as PRC, reports MID got 30mins more beam as agreed with operators.

DET:
- Nothing to report.

ITDM: 
- Nothing to report.

XRO:
- Nothing to report.

LAS:
- Ask SCS for confirmation if it is needed to change PP-laser rep rate this week. SCS will confirm later.

UNSYS:
- Nothing to report.

SPB:
- Intervention last night was advertised 20 mins but took 1 hour.

FXE:
- Issue with digitizers for detector was solved.

MID:
- User experiment on THU/FRI went good.
- Second user experiment on SAT/SUN received about 12hs of beam delivery; no outcome.

HED:
- Nothing to report.

SCS:
- Suffered from downtime.

SQS:
- Nothing to report.