ID |
Date |
Author |
Location |
Severity |
Subject |
Text |
|
296
|
21 Jun 2017, 10:21 |
Tobias Haas | General | Information | Status and Plans after 09:30 meeting | XTDs:
DESY requests the KMONO
to be commissioned since the K Values of |
|
298
|
22 Jun 2017, 15:15 |
Tobias Haas | XTD2 | Information | Schedule for first beam SASE1 hutches | It was just decided to put a very low intensity
beam into the SASE1 hutches starting tomorrow
morning at 8 AM. Both instruments declared |
|
299
|
23 Jun 2017, 11:11 |
Tobias Haas | General | Information | Status and plans after SASE1 Readiness Meeting |
General
A low intensity beam |
|
300
|
26 Jun 2017, 10:57 |
Tobias Haas | General | Information | Status and Plans after 09:30 meeting | General:
Beam was brought
to all SASE1 hutches on Friday. Beam was |
|
303
|
30 Jun 2017, 11:33 |
Tobias Haas | General | Information | Status and plans after SASE1 Readiness Meeting | Data Acquisition and Data Archiving
K. Wrona summarised the
basic ingredients of the system.
All |
|
306
|
03 Jul 2017, 10:26 |
Tobias Haas | General | Information | Status and Plans after 09:30 meeting | General
Accelerator was down all
weekend due to cold compressors that were |
|
Draft
|
10 Jul 2017, 10:26 |
Tobias Haas | General | Information | Status and Plans after 09:30 meeting | |
|
323
|
10 Jul 2017, 10:31 |
Tobias Haas | General | Information | Status and Plans after 09:30 meeting | General
Interlock was set in the
injector last Friday
All shifts |
|
326
|
12 Jul 2017, 10:45 |
Tobias Haas | General | Information | Status and Plans after 09:30 meeting | XTDs
Mechanical operation of
KMONO is prepared. Work is now ongoing on |
|
335
|
14 Jul 2017, 13:17 |
Tobias Haas | General | Information | Status and plans after SASE1/3 Readiness Meeting | General
From now on progress with
the SASE3 tunnel will be monitored in this |
|
338
|
19 Jul 2017, 10:11 |
Tobias Haas | General | Information | Status and Schedule after 09:30 meeting | General
The latency observed by
SPB in the GUI client could be reproduced |
|
360
|
09 Aug 2017, 10:23 |
Tobias Haas | General | Information | Status and Plans after 09:30 meeting | General
Main focus for Vacuum
Group and AE next week will be to get |
|
361
|
11 Aug 2017, 10:07 |
Tobias Haas | General | Information | Status and plans after SASE1/3 Readiness Meeting | General
The focus of activities
next week for the AE and vacuum groups is |
|
363
|
18 Aug 2017, 11:23 |
Tobias Haas | General | Information | Status and plans after SASE1/3 Readiness Meeting | Software:
CAS meets with SPB and
FXE on a daily basis to fine tune progression |
|
365
|
21 Aug 2017, 16:26 |
Tobias Haas | General | Information | Status and Schedule after 09:30 meeting | General
Access to tunnel XTD10
ends today around midday and beam is expected |
|
369
|
23 Aug 2017, 10:20 |
Tobias Haas | General | Information | Status and Schedule after 09:30 meeting | CAS
Finishing tests for KARABO
2.1.15. Deployment should start today during |
|
370
|
25 Aug 2017, 13:42 |
Tobias Haas | General | Information | Status and plans after SASE1/3 Readiness Meeting | General
T. Haas conveys the congratulations
of the management
for the achievements |
|
373
|
01 Sep 2017, 10:34 |
Tobias Haas | General | Information | Status and plans after SASE1/3 Readiness Meeting | General:
The length of the shut
down in October is still under discussion. |
|
375
|
04 Sep 2017, 10:39 |
Tobias Haas | General | Information | Status after 0930 meeting | SPB
Demo experiment done last
week
Flat fields taken with AGIPD |
|
376
|
04 Sep 2017, 12:03 |
Tobias Haas | General | Information | Status after 0930 meeting | Just to clarify:
Tunnel and SPB are in different
Karabo Topics. It should not be a problem |
|