Technical integration and coordination SASE1 Status and SASE3 Readiness
  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther, Page 2 of 30  Not logged in ELOG logo
ID Date Authordown Location Severity Subject Text Attachments
  34   02 Feb 2017, 17:46 Tobias HaasGeneralInformationStatus of component list as of 17:45   Componets-XTD2-9.xlsx 
  39   09 Feb 2017, 13:57 Tobias HaasGeneralInformationUpdate of installation list for tomorrow's S1R Meeting Please check if correct. I mark all
newly done things in yellow!
 Componets-XTD2-9.xlsx 
  40   09 Feb 2017, 17:16 Tobias HaasGeneralInformationStatus of Differential PumpingPost on behalf of R. Villanueva
  
  41   10 Feb 2017, 08:31 Tobias HaasGeneralInformationProgress Beam TransportPost on behalf of Harald Sinn
Fortschritte,
die ich letzte Woche beobachten konnte, sind: 
  
  42   10 Feb 2017, 15:07 Tobias HaasGeneralInformationUpdated Components List Added Diagnostic Screen for SPB and
changed PRIO for DPS - XGM - DPS in XTD9
to high as discussed during the S1R meeting
 Componets-XTD2-9-new.xlsx 
  44   10 Feb 2017, 16:34 Tobias HaasGeneralInformationUpdated Components List   Components-XTD2-9.xlsx 
  54   24 Feb 2017, 16:33 Tobias HaasGeneralInformationUpdate of component list after weekly meeting   240217_Components-XTD2-9.xlsx 
  55   28 Feb 2017, 11:38 Tobias HaasGeneralInformationReminder: Stable operation and development periodsOne word of clarification:
The discussion last Friday left some
people uncertain over how to define stable
  
  58   03 Mar 2017, 16:40 Tobias HaasGeneralInformationUpdate of Component Priority list after weekly meeting   170303_Components-Priority-list.xlsx 
  59   03 Mar 2017, 16:46 Tobias HaasGeneralInformationMinutes of weekly SASE1 Readiness Meeting Here is the link to the minutes Minutes   
  67   10 Mar 2017, 11:15 Tobias HaasGeneralInformationUpdate of Tunnel Component Priority List after SASE1 Readiness Meeting   Components-Priority-list.xlsx 
  68   10 Mar 2017, 11:18 Tobias HaasXHEXPInformationInstrument Component Priority List update after SASE1 Readiness Meeting   170310_Instrument_Components-Priority-list.xlsx 
  70   10 Mar 2017, 12:53 Tobias HaasGeneralInformationUpdate of Tunnel Component Priority List after SASE1 Readiness MeetingNote that due to a bug in the elog the
name appeared wrongly in my previous message.
In general: Avoid underscores in the file
 170310-Tunnel-Components-Priority-list.xlsx 
  72   10 Mar 2017, 16:56 Tobias HaasGeneralInformationTunnel Commissioning Schedule for Week 11
    
        

           Day
  
  87   24 Mar 2017, 13:21 Tobias HaasGeneralInformationSchedule for PLC and Karabo Week 13 

  
  88   24 Mar 2017, 15:24 Tobias HaasGeneralInformationUpdate of component priority list after weekly meeting   170324-Tunnel-Components-Priority-list.xlsx 
  90   31 Mar 2017, 15:00 Tobias HaasGeneralInformationUpdate of component list after weekly meeting   170331-Tunnel-Components-Priority-list.xlsx 
  93   03 Apr 2017, 10:03 Tobias HaasGeneralInformationSchedule for PLC and Karabo 3 April after 09:30 MeetingTunnels closed today and tomorrow
- AE updates Vacuum and motion loop
in the morning
  
  94   04 Apr 2017, 11:21 Tobias HaasGeneralInformationSchedule after 09:30 Meeting Tunnel
closed today. Might re-open around 14:00
Note that that we re-convene briefly
  
  97   04 Apr 2017, 15:11 Tobias HaasGeneralInformationAccess to XTD2MPS informed me that they hit some problems
and that they still need 30 mins to 1 h until
we can go to XTD.  
  