Technical integration and coordination SASE1 Status and SASE3 Readiness
  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther, Page 24 of 30  Not logged in ELOG logo
New entries since:Thu Jan 1 01:00:00 1970
ID Date Author Locationdown Severity Subject Text Attachments
  447   11 Jan 2018, 15:17 Bruno FernandesGeneralInformationFXE/SPB/PPL Timing UpdateHi everyone,

after talking with the responsabile
people, here's the timetable for the
  
  448   12 Jan 2018, 11:10 Gerd WellenreutherGeneralInformationStatus and plans after Readiness Meeting

  
  449   12 Jan 2018, 14:34 Bruno FernandesGeneralInformationUpdate Timing Firmware/Doocs ServerDear all,

with the exception of one board,
all boards in SASE1, SASE3, FXE, SPB and
  
  450   15 Jan 2018, 13:56 Adriano ViolanteGeneralInformationStatus report after dispatch meeting 13:00
SPB:
- The exchange
of the mc and mfpga boards has been done
and some problems were found. The boards
  
  451   17 Jan 2018, 13:54 Adriano ViolanteGeneralInformationStatus report after dispatch meeting 13:00
SPB:
- one mfpga
board was found malfunctioning and was replaced
with the old one. Concerning the mc the new
  
  453   17 Jan 2018, 16:53 Bruno FernandesGeneralInformationEvent #16 back to 1Hz Dear all,

I communicated today on the 13h
meeting that the Trigger #16 was back to
  
  454   19 Jan 2018, 16:06 Bruno FernandesGeneralInformationEvent #16 back (for good) to 10Hz Event trigger #16 is now back to 10Hz and
it will still that way.
  
  455   22 Jan 2018, 10:36 Gerd WellenreutherGeneralInformationStatus and plans after Readiness MeetingSPB/SFX:


2nd AGIPD intervention
will be finished today.
SE worked
  
  456   22 Jan 2018, 13:28 Adriano ViolanteGeneralInformationStatus report after dispatch meeting 13:00General remarks:


Stable beam only to be
expected starting from 1.03. for SASE1 instruments
  
  457   22 Jan 2018, 15:12 Bruno FernandesGeneralInformationRe: Status report after dispatch meeting 13:00Hi everyone,

there was some miscommunication
between us and DESY: only the Timing firmware
  
  458   24 Jan 2018, 14:48 Adriano ViolanteGeneralInformationStatus report after dispatch meeting 13:00SPB/SFX:


Preparing D.02 for mirrors
installation (next 2 weeks no access to D.02)
Karabo
  
  459   24 Jan 2018, 16:15 Bruno FernandesGeneralInformationSASE1 Timing System UpdateDear all,

the update to the SASE1 Timing
system has been perform with no problems.
  
  460   29 Jan 2018, 09:29 Gerd WellenreutherGeneralInformationStatus and plans after SASE1 Status/SASE3 Readiness Meeting 26.1.SPB/SFX:



Preparation
for the mirror installation were ongoing
  
  461   29 Jan 2018, 10:02 Gerd WellenreutherGeneralInformationLink to "Access Request" gathering for tunnels after the shutdownDear all,

please enter your access requests
to the tunnels into the list provided by
  
  463   29 Jan 2018, 14:51 Adriano ViolanteGeneralInformationStatus report after dispatch meeting 13:00SPB/SFX:


Problems with data loggers
==> no statements about the past.
Loop
  
  464   31 Jan 2018, 10:06 ITDM AdminGeneralInformationexflgateway migrationToday late in the evening (~22:00), the
exflgateway will be migrated to a new hardware.
All users will be logged out before migration
  
  465   31 Jan 2018, 14:56 Adriano ViolanteGeneralInformationStatus report after dispatch meeting 13:00SPB/SFX:


Fixing of Karabo scenes
ongoing
Loop 5 need to be updated
  
  466   31 Jan 2018, 22:34 ITDM AdminGeneralInformationRe: exflgateway migrationThe migration has finished, to avoid temporary
problem with ssh you can use

ssh exflgateway -o StrictHostKeyChecking=no
  
  467   05 Feb 2018, 09:11 Adriano ViolanteGeneralInformationStatus and plans after SASE1 Status/SASE3 Readiness Meeting 02.02.SPB

- Loops update OK

- Issue with SmarACT controllers.
  
  468   05 Feb 2018, 13:18 Adriano ViolanteGeneralInformationStatus report after dispatch meeting 09.30SPB

- MIrrors installation (2 horizontal
mirrors) in D.02 has started 
  