ID Date Author Location Severitydown Subject Text Attachments
  332   14 Jul 2017, 09:31 Jan GrünertGeneralInformationWP74 SASE1/3 readiness status and outlookSASE1 / SASE3 readiness --- WP74

2017-07-14

SASE1: 
  
  333   14 Jul 2017, 10:50 Gerd WellenreutherGeneralInformationTAS updatedDear all,

the Tunnel Access Schedule has
been update - potential access has been shifted
  
  335   14 Jul 2017, 13:17 Tobias HaasGeneralInformationStatus and plans after SASE1/3 Readiness MeetingGeneral


From now on progress with
the SASE3 tunnel will be monitored in this
  
  336   14 Jul 2017, 18:46 Nicola CoppolaGeneralInformationInformation AE OCD July 14--17 (till Monday 8:00)AE on call service:

    Contact person:

       
  
  337   18 Jul 2017, 10:57 Gerd WellenreutherGeneralInformationTunnel access schedule updatedDear all,

an updated TAS is provided: https://docs.xfel.eu/share/page/site/PSC/wiki-page?title=Tunnel_access_schedules

There is potential access to the
  
  338   19 Jul 2017, 10:11 Tobias HaasGeneralInformationStatus and Schedule after 09:30 meetingGeneral


The latency observed by
SPB in the GUI client could be reproduced
  
  339   20 Jul 2017, 15:19 Gerd WellenreutherGeneralInformationTunnel access schedule updatedDear all,

according to the current planning
on next Tuesday (25.7.) both XTD9 and XTD10
  
  340   24 Jul 2017, 10:03 Gerd WellenreutherGeneralInformationTunnel access schedule updatedDear all,

access to XTD9 and XTD10 will be
available from tomorrow Tuesday the 25.7.
  
  341   24 Jul 2017, 10:07 Frederike WittmaackGeneralInformationStatus and plans after SASE 1/3 Readiness MeetingGeneral (T. Tschentscher/G. Wellenreuther)


Further tuning of the machine
might require some time which was initially
  
  342   24 Jul 2017, 10:38 Adriano ViolanteGeneralInformationStatus after 9.30 MeetingGeneral


The latency observed by
SPB in the GUI client has been almost completely
  
  343   25 Jul 2017, 13:26 Gerd WellenreutherGeneralInformationTunnel access schedule updatedDear all,

I had some minor updates of the
TAS during the last days, please check again.
  
  344   26 Jul 2017, 10:35 Adriano ViolanteXHEXPInformationStatus after 9.30 MeetingGeneral


Today the machine is being
prepared to lase with 30 bunches in order
  
  345   26 Jul 2017, 14:10 Bernard BaranasicXHEXPInformationSPB - Loop 5 is back onlineSPB Loop 5 is back online:

- but without crate BKF00095-SPB_IRU_CHL
(there is missmatch of hardware and documentation
  
  346   26 Jul 2017, 18:04 Martin DommachXTD9InformationFast valves in XTD9Dear all,

the problem with the fast valves
  
  347   27 Jul 2017, 15:42 Eric BoydXHEXPInformationRestricted areas Durring Radiation Measurements of SASE 1, Friday 28.07No radiation measurements have taken place
today (27.07) due to insufficent energy of
the machine. We think we can achive the desired
 Restricted_areas_for_measurments.pptx 
  348   28 Jul 2017, 11:10 Eric BoydXHEXPInformationNo Restricted Areas for Radiation CommissioningDesired parameters where reached for radiation
measurments of the SPB OPT and SPB EXP hutches.
Radiaiton could not be detected inside the
  
  349   28 Jul 2017, 11:50 Frederike WittmaackGeneralInformationStatus and plans after SASE 1/3 Readiness MeetingGeneral



The radiation test
in SASE1 could not take place yesterday since
  
  350   30 Jul 2017, 23:04 Gerd WellenreutherGeneralInformationTunnel access schedule updatedDear all,

on Tuesday, XTD9 will be accessible
from 7:00 - 14:00, due to requests by Naresh
  
  351   31 Jul 2017, 11:58 Adriano ViolanteGeneralInformationStatus after 9.30 dispatch MeetingGeneral



SRP was not able
to measure any radiation even inside D.09
  
  352   02 Aug 2017, 10:17 Monica ArestéGeneralInformationStatus after 9:30 dispatch MeetingGeneral



This Thursday the
radiation test in D.05 (FXE) will be performed
  