  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther, Page 4 of 33  Not logged in ELOG logo
Entry   Report after dispatch meeting 09.00, posted by Adriano Violante on 01 Mar 2019, 14:18 
SPB/SFX


Today Loop 8 could be ready (AE)
Agipd - visualization of data shows variable rep rate... correlations to be investigated.


FXE

​SQS
Entry   Report after dispatch meeting 09.00, posted by Adriano Violante on 05 Apr 2019, 10:07 
SPB/SFX


5Hz mode tests started (SPB/SQS) and partially successful. A detailed report will be sent around. 2 cameras in SPB and digitizers in
SQS were tested. Cameras OK. Digitizers data recordin has some issues being fixed (train id related). Next week on Thursday a test with beam is foreseen.
Entry   Report after dispatch meeting 09.00, posted by Adriano Violante on 26 Apr 2019, 12:28 
SPB/SFX


IRD commissioning ongoing.
CRL motors being tested. --> Mechanical issue with a CRL motor is being addressed.
CSS
interlock tests with AE still ongoing.
AE needs to know when Loop 9 and 10 are expected to run. SPB to check.
Jungfrau detector:
Entry   Report after dispatch meeting 09.00, posted by Adriano Violante on 10 May 2019, 10:52 
SPB/SFX


IRDa commissioning successful. A. Mancuso thanked all the people involved in the project. 
The gear ratio of the
CSS is unclear but this was already known and discussed with SPB/SFX
Mirrors motors had some issues (ELMO motors), they are already been fixed.
Adam
Entry   Report after dispatch meeting 09.00, posted by Adriano Violante on 07 Jun 2019, 11:53 
FXE

SPB/SFX


few days of beamtime remaining, no particular issues
preparing for emergency power off
preparing shutdown activities
Entry   Report after dispatch meeting 09.00, posted by Adriano Violante on 09 Dec 2019, 09:22 
FXE:


No major issues.
Karabo will be updated to the version 2.7.0. on Friday.
uTCA update will be done on Thursday.


SCS:


it was forgotten to involve EEE in the PLC update of the train picker in the tunnel. Now the issue is solved.


MID:
Entry   Report after dispatch meeting 09.00, posted by Adriano Violante on 16 Dec 2019, 09:28 
FXE:


uTCA update has been completed by EEE on Friday evening. Information will be passed to controls for the finalization.


SCS


The interlock system for the big sliding door has to be fixed. JTD is following up the issue with TS and SRP.
MT will talk
Entry   Report after Tech. Int. meeting 09.30 , posted by Adriano Violante on 11 Dec 2019, 09:54 
FXE:


New optical table will be installed today. Access to the hutch could be limited.
The new Airbox installed by D3 is colliding
with the sliding door. It might be problematic to bring the new laser table in. SRP informed. It is being followed up. 
uTCA update will
    Reply   Re: running jdd panels in control rooms, posted by ITDM Admin on 19 Jun 2019, 16:33 
Regarding the recent announcements from doocs/jddd people about running jddd application I post here a short summary:
- running jddd with oracle java 8 via java webstart will be no longer possible as of 10.07.19
- on all control PCs in the instruments control rooms, BKR and exflgateway the new jddd was already in use since March, as described in the previous
Entry   Notes XO integration meeting 20.12.2021, posted by Andreas Galler on 20 Dec 2021, 09:25 
General Announcement:


 


CTRL:


no update


DA:
Entry   Notes XO integration meeting 18.07.2022, posted by Andreas Galler on 18 Jul 2022, 09:31 


General Announcement:


none


CTRL:
Entry   Notes XO integration meeting 12.10.2022, posted by Andreas Galler on 12 Oct 2022, 09:16 
General Announcement:


 


CTRL:


nothing major


DA:
Entry   Notes XO integration meeting 11.04.2022, posted by Andreas Galler on 11 Apr 2022, 09:10 


General Announcement:


 


CTRL:
Entry   Notes XO integration meeting 06.04.2022, posted by Andreas Galler on 06 Apr 2022, 09:15 


General Announcement:


 


CTRL:
Entry   Notes XO integration meeting 04.04.2022, posted by Andreas Galler on 04 Apr 2022, 09:26 
General Announcement:


 


CTRL:


PP LAS restarting device servers for upgrading the device tag --> autoinstantiate some servers all topics


DA:
Entry   Notes XO Integration meeting 27.04.2020, posted by Frederik Wolff-Fabris on 28 Apr 2020, 16:19 
General Announcement:
- The CTRL group has received 3 Control Network tasks that can be carried out this week;
- Requests from the groups to Tunnel activities from May 4th are being treated and an answer will come in the next couple of days. 
Entry   Notes XO Integration meeting 26.07.2023, posted by Andreas Galler on 26 Jul 2023, 09:21 
General Announcement:


The injector Laser Window had been exchanged yesterday and currently leak search is ongoing. Tuning is expected to start around lunch
time. 


CTRL:
Entry   Notes XO Integration meeting 18.04.2023, posted by Andreas Galler on 19 Apr 2023, 09:27 
General Announcement:


 


CTRL:


nothing major


DA:
Entry   Notes XO Integration meeting 17.04.2023, posted by Andreas Galler on 17 Apr 2023, 09:26 
General Announcement:


 


CTRL:


nothing major


DA:
Entry   Notes XO Integration meeting 12.04.2023, posted by Andreas Galler on 12 Apr 2023, 09:23 
General Announcement:


 


CTRL:


not much to report


DA: