Minutes of the Technical integration meeting 10.07.19 , posted by Adriano Violante on 10 Jul 2019, 16:16
|
XO
In SASE3 the apertures of the GATT have to be realigned. The upstream apertures have been alreadz realigned. The downstream ones will
be probablz realigned tomorrow. If not succesfull some restrictions of the operation have to be evaluated. ==> Done.
Turnstile issue: 2 days |
Minutes of the Technical integration meeting 10.04.19 , posted by Adriano Violante on 10 Apr 2019, 10:54
|
SPB/SFX
CRL implementation in the hutch. Tests can start today.
CSS Test have been started. One elmo devide has to be implemented
today. Interlocks have to be tested (later).
AGIPD motion. Middle layer final tests will be done during next reconfiguration od the detector.
Julabo |
Minutes of the Technical integration meeting 08.05.19 , posted by Adriano Violante on 08 May 2019, 10:10
|
SPB/SFX
IRDa commissioning ongoing.
CSS. Limit switches re cabling is ongoing. For the next run the old configuration will
still be used. RB and MS will meet to make sure the system can be safely (from the component point of view) operated. ==> Solved.
Comment |
Minutes of the Technical integration meeting 07.08.2019, posted by Adriano Violante on 07 Aug 2019, 11:55
|
XO
The accelerator is now working at 2.25 MHz. Kicker can be used. DET informs that for repetition rates different to the ones been used so
far the calibration can be significatively different. |
Minutes of the Technical integration meeting 06.03.19 , posted by Adriano Violante on 06 Mar 2019, 10:31
|
SPB/SFX
CSS component commissioning. Concept and implementation finalized. EPLAN has been modified. PLC modification has to follow.
Issues
concerning the simultaneous operation of more Jungfrau detector modules has been solved. Additional tests ongoing.
CRL implementation |
Minutes of the Technical integration meeting 06.02.19 , posted by Adriano Violante on 06 Feb 2019, 11:13
|
SPB/SFX
AGIPD commissioning and tests. ==> intervention on the wings is ongoing.
CSS component commissioning. RBean is discussing
with AE. By the end of the week the changes could be implemented.
Loop 14 (Jungfrau) is needed for next week to start the commissioning. AE |
Minutes of the Technical integration meeting 05.06.2019, posted by Gerd Wellenreuther on 05 Jun 2019, 09:59
|
FXE
SPB/SFX
few days of beamtime remaining, no particular issues
preparing for emergency power off
preparing |
Minutes of the Technical integration meeting 03.07.19 , posted by Adriano Violante on 03 Jul 2019, 10:18
|
XO
In SASE3 the apertures of the GATT have to be realigned. The upstream apertures have been alreadz realigned. The downstream ones will
be probablz realigned tomorrow. If not succesfull some restrictions of the operation have to be evaluated.
FXE |
Minutes of the Technical integration meeting 03.04.19 , posted by Adriano Violante on 03 Apr 2019, 10:44
|
SPB/SFX
CRL implementation in the hutch. Cables at the back of the crate have been re-shuffled by EETf. VAC vessel had a leak and is being re-sealed
and pumped. If everything is fine and the vessel can be brought to the hutch the motors test can in principle start already this week. Interaction |
Minutes after dispatch meeting 09.00, posted by Adriano Violante on 15 Mar 2019, 11:27
|
SPB/SFX
No major issues reported
Motors in Loop 14 have been tested and problems with the motion sign and encoder were found. AE/EET
on it.
FXE |
MInutes of the dispatch meeting 09.30, posted by Adriano Violante on 11 Feb 2019, 09:59
|
SPB/SFX
Beam is back on Wed. night.
IT cables in D.23 were re-measured on friday. Probemessung was OK. Waiting for the complete set
of measurements. PSPO pushes the company.
Updates+testing of the AGIPD with the CFEL experts is ongoing.
interlock definitions |
MInutes of the dispatch meeting 09.00, posted by Adriano Violante on 22 Feb 2019, 12:36
|
SPB/SFX
Pulse picker commissiong - Issues concerning motors position and triggers ==> To be worked out with AE, but beam is needed. Has to
be done.
DET group is helping setting up the Jungfrau detector (w/o PLC).
DAQ performance test performed yesterday.
Trigger |
Info on dispatch meeting 09.00, posted by Adriano Violante on 02 Aug 2019, 09:10
|
| The meeting did not take place since only EEE was attending. |
, posted by Andreas Galler on 30 Mar 2020, 08:57
|
CTRL:
Broker Pile Up in 4 topics over the weekend
LAS affected in all topics, LA2 even twice
SPB affected once
mitigation
startegy worked
EEE: |