Technical integration and coordination SASE1 Status and SASE3 Readiness
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther, Page 31 of 31  Not logged in ELOG logo
ID Date Author Location Severity Subjectdown
  75   02 Aug 2019, 09:10 Adriano ViolanteGeneralInformationInfo on dispatch meeting 09.00

The meeting did not take place since only EEE was attending.

  Draft   30 Mar 2020, 08:57 Andreas Galler   

CTRL:

  • Broker Pile Up in 4 topics over the weekend
    • LAS affected in all topics, LA2 even twice
    • SPB affected once
  • mitigation startegy worked

EEE:

  • nothing to report

VAC:

nothing to report

 

XPD

  • vac systems in the lab had been secured --> secuvac valves installed plus webcams

DET:

  • nothing to report

ITDM:

  • exflgateway hardware problem on Saturday --> fixed

XRO:

  • nothing to report

SPB:

  • rough pump turned off, possibly lack of cooling water
    • interlock tripped --> pressures raised
  • were able to set remotely

FXE:

  • nothing to report

MID:

  • everything is fine

HED:

  • VAC is fine, ion pumps are on, no roughing pumps running

DA:

  •  

 