SASE1 Status and SASE3 Readiness
|
Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther |
Not logged in |
|
|
Message ID: 91
Entry time: 11 Dec 2019, 09:54
|
Author: |
Adriano Violante |
Location: |
General |
Severity: |
Information |
Subject: |
Report after Tech. Int. meeting 09.30 |
|
|
FXE:
- New optical table will be installed today. Access to the hutch could be limited.
- The new Airbox installed by D3 is colliding with the sliding door. It might be problematic to bring the new laser table in. SRP informed. It is being followed up.
- uTCA update will be done on Thursday.
SCS
- The interlock system for the big sliding door has to be fixed. JTD is following up the issue with TS and SRP. It is not so clear who are the main players so far.
MID:
- SDL will be completed at the beginning of next week (inc. cables measurement).
- SDL tests ongoing
- Hexapod controllers will be moved to the rackroom. KS is waiting for the controller allocation in the racks in relation to the cables length from MFobian.
EEE:
- uTCA puppet migration: in MID it has been done yesterday. Today SQS and SCS will undergo the update. Tomorrow HED and FXE. Next week tunnels.
- 1 day has been requested to ITDM to clean up and re arrange uTCA related cablin in the balconies. ITDM has to come back to BF to define a date.
- Update of loops in the tunnels are scheduled for next week
|