Technical integration and coordination SASE1 Status and SASE3 Readiness
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 288     Entry time: 20 Dec 2021, 09:25
Author: Andreas Galler 
Location: General 
Severity: Information 
Subject: Notes XO integration meeting 20.12.2021 

General Announcement:

  •  

CTRL:

  • no update

DA:

  • nothing

EEE:

  • nothing

VAC:

  • nothing to report

XPD:

  • nothing special, shtudown tasks are in schedule, HXPES / XTED2 cable work ongoing

DET:

  • nothing special

ITDM:

  •  

XRO:

  •  

LAS:

  • lasers ramped down

UNSYS: 

  • APPLEXv inv place, VAC to be closed next year

SPB/SFX:

  • working on mirrors
    • checking vacuum today
  • not clear what is the status with the movement of racks wrt SXP (SPB/SFX optics hutch racks currently powered down)
    • electrical installation?
    • PG comments: Brad won't allow operation until 230 V power distribution is calrified, once Brad gives the OK, the racks can be switched on
      racks are being finalized by EEE, but some checks need electrical power
    • RB: SPB/SFX were promised that the move of the racks were finished before X-Mas, but it seems the electrical work is not up to satandards

FXE:

  • shutdown task in schedule

MID:

  • all fine
    • some loop updates planned for Today

HED:

  •  

SCS:

  •  

SQS:

  • nothing

AOB:

  • light OCD over X-Mas for XPD in case of floowings, power outages.lists will be