Technical integration and coordination SASE1 Status and SASE3 Readiness
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 342     Entry time: 18 Jul 2022, 09:31
Author: Andreas Galler 
Location: General 
Severity: Information 
Subject: Notes XO integration meeting 18.07.2022 

General Announcement:

  • none

CTRL:

  • fastADC karabo Version updated
    • everything looks fine
  •  

DA:

  • nothing

EEE:

  • PLC and cabling as scheduled
  • fastADC update
    • MID and SPB issues being solved by lunch time

VAC:

  • HED Mono
  • SXP tunnel interface

XPD:

  • ZZ on Tuesday for XTD1 SR imager camera reset

DET:

  • DSSC update
    • test not yet conclusive on whether operation is safe or not.
    • current suggestion: postpone experiments until repair is done
  • AGIPD firmware update went well

ITDM:

  • nothing

XRO:

  • not present

LAS:

  • Timing issues solved, solved by Lars Froehlich
  • LAS may suffer from limited available resources

UNSYS: 

  • all fine

SPB/SFX:

  • issue with Elmo motors

FXE:

  • nothing

MID:

  • nothing
    •  

HED:

  • nothing

SCS:

  • mobile compressor will be used this week

SQS:

  • nothing

DRC

  •  

PRC

  •  