Message ID: 399     Entry time: 01 Mar 2023, 09:41
Author: Frederik Wolff-Fabris 
Location: General 
Severity: Information 
Subject: Notes XO Integration Meeting 01.03.2023 
General Announcement:
-	 

CTRL:
- Nothing to report.
- Problems with FXE motors were solved at the DOOCS side. It was not a Karabo issue.

DA:
- Nothing to report.
- As DRC P. Schmidt says all is running quietly this week.

EEE:
- Remind on the deploy of ADQ new digitizer to be done next Monday morning. It will be done in all instruments apart of SQS. In case of question please contact Bruno F.

VAC:
- All fine with VAC systems.

XPD:
- All fine with Diagnostics. 
- The PES issue was resolved by exchanging the low voltage module in a ZZ also together with CTRL. Under investigation why the board was damaged.

DET:
- Nothing to report.

ITDM: 
- Nothing to report.

XRO:
- Not present.

LAS:
- Nothing to report.

UNSYS:
- Nothing to report.
- Issue with FXE motors / undulators will be further investigated.

SPB:
- Nothing to report.

FXE:
- Nothing to report.

MID:
- Nothing to report.

HED:
- Setting up experiment.
- Problems with Karabo being slow which affected night progress. CTRL and DA will investigate with DOC.

SCS:
- Several problems with Karabo devices happening during the night. It seems to be solved by now. Jan-Torben D. will get further information.

SQS:
- Nothing to report.

SXP:
- Nothing to report.