94
|
08 Jan 2020, 12:36 |
Adriano Violante | General | Information | Report of the Technical integration meeting |
SPB:
- Coordinatd motion for MC2 motors is going to be rolled out by EEE soon.
FXE:
MID:
- SDL tests ongoing.
- All SDL cables have been installed and tested apart from 6 cables (still waiting for pins to be delivered).
- Various loops update and hexapod integration ongoing.
- CRLs - EPS loop will be update probably this week. (involves position sensors in the y direction for CRLs in SASE2 and 1. To be done in the framework of the full beam operation project)
EEE:
- SA1 VAC loop update. Issues with the eplan export. Discussion ongoing with VAC and XPD.
- SA2 MOV loop update for imagers MC2 motors. This week a meeting with all the stakeholder will be held (MID, HED, EEE, Controls) and a suitable date (during next week) for the update will be found. PMO will ask MDommach to provide some feedback on the Tunnel closing schedule. As soon as the feedback is available, it will be distrubuted through the readiness mailing list.
|
93
|
18 Dec 2019, 10:06 |
Adriano Violante | General | Information | Report after tech. Int. meeting 09.30 |
MID:
- SDL tests ongoing. Important motors have been tested. Alignment of the mechanics with the alignment laser ongoing. Will be pumped over Christmas.
EEE:
- uTCA puppet migration: Instr. done. Tunnels and balconies probably will be updated at the beginning of next year.
- SASE2 EPS loop will be updated probably today.
- SPB/SFX is getting a new CPU.
- Migration to MC2 motors has been agreed with controls, XRO, XPD. in XTD 6 XPD the upgrade will be done in KW2. For the rest a plan has to be made.
ITDM
- Meeting this week ITDM/EEE/TS to discuss how to mitigate issues caused by accidents (e.g. cooling water interruption caused by power cut).
Controls:
- CY sent a mail several weeks ago to XO and the DH. The topic is emergency procedures during Christmas. No reply. CY announces that in the period 23.12-07.01 the Controls OCDs would not be available.
AoB
- No dispatch meeting on 06.01. Next meeting will be the Technical Integration one on 08.01.
|
92
|
16 Dec 2019, 09:28 |
Adriano Violante | General | Information | Report after dispatch meeting 09.00 |
FXE:
- uTCA update has been completed by EEE on Friday evening. Information will be passed to controls for the finalization.
SCS
- The interlock system for the big sliding door has to be fixed. JTD is following up the issue with TS and SRP.
- MT will talk to VAC to clarify how to go on with the train picker integration in the tunnel.
SQS
- uTCA has been updated.
- A channel in a digitizer is bisbehaving. The issue is being fixed.
- Steinmeyer stages will be commissioned today with MS.
MID:
- SDL tests ongoing
- Hexapod controllers will be moved to the rackroom. Cables have to be pulled and only after the position of the controllers can be chosen.
- Loop12 will be updated today by EEE
EEE:
- uTCA puppet migration: Instr. done. Tunnels and balconies probably will be updated at the beginning of next year.
- SASE1 and 3 EPS loop will be updated probably today.
- PLC in SPB with issues is being worked on.
- Migration to MC2 motors has been agreed with controls, XRO, XPD. in XTD 6 XPD the upgrade will be done in KW2. For the rest a plan has to be made.
XPD:
- Some issue with the font size in the new Karabo GUI. Controls will have a look.
Controls:
- Karabo updates ongoing. SASE3 today until 13:00. SA1, 2 on Wed.
- MC2 motors updates has been started also in FXE.
- SASE3: meeting with Lasermet for the integration of interlock signals in Karabo. Controls has handed over the scenes to the instruments that will optimize them.
- firmware of the power supply for the AGIPD has to be updated urgently (by Wed.). CY sent a mail to AM. If no reply the power supplies will be switched off for the update.
|
91
|
11 Dec 2019, 09:54 |
Adriano Violante | General | Information | Report after Tech. Int. meeting 09.30 |
FXE:
- New optical table will be installed today. Access to the hutch could be limited.
- The new Airbox installed by D3 is colliding with the sliding door. It might be problematic to bring the new laser table in. SRP informed. It is being followed up.
- uTCA update will be done on Thursday.
SCS
- The interlock system for the big sliding door has to be fixed. JTD is following up the issue with TS and SRP. It is not so clear who are the main players so far.
MID:
- SDL will be completed at the beginning of next week (inc. cables measurement).
- SDL tests ongoing
- Hexapod controllers will be moved to the rackroom. KS is waiting for the controller allocation in the racks in relation to the cables length from MFobian.
EEE:
- uTCA puppet migration: in MID it has been done yesterday. Today SQS and SCS will undergo the update. Tomorrow HED and FXE. Next week tunnels.
- 1 day has been requested to ITDM to clean up and re arrange uTCA related cablin in the balconies. ITDM has to come back to BF to define a date.
- Update of loops in the tunnels are scheduled for next week
|
90
|
09 Dec 2019, 09:22 |
Adriano Violante | General | Information | Report after dispatch meeting 09.00 |
FXE:
- No major issues.
- Karabo will be updated to the version 2.7.0. on Friday.
- uTCA update will be done on Thursday.
SCS:
- it was forgotten to involve EEE in the PLC update of the train picker in the tunnel. Now the issue is solved.
MID:
- SDL cabling ongoing.
- SDL preliminary tests ongoing
- Hexapod controllers will be moved to the rackroom. KS is waiting for the cables length from MFobian.
HED:
- IC1: cheking of the encoder is going on with the help of EEE (Hazem Ali)
- New interlock definitions for Loop 6 are giong to be delivered with some delay. NJ is informed.
- Hexapod controllers will be moved to the rackroom. KS is waiting for the cables length from MFobian.
- XPD installed the diamond screens in the pop in monitors in the tunnel.
EEE:
- uTCA puippet migration will start today in the optical laser systems. Next weeks it is planned to do it in the tunnel (XPD is informed). Info mail will follow.
- 1 day has been requested to ITDM to clean up and re arrange uTCA related cablin in the balconies. Info mail will follow.
- SCS: new set of cables (microscope and others) will be ready for installation tomorrow.
Controls:
- 13.12. Karabo 2.7.0 deployment will begin.
- Normal motors will be upgraded to MC2. First tests are foreseen in MID tunnels. XPD and XRO are affected. XPD has been informed in this dispatch meeting. KS will inform MV (XRO). MS (EEE).
|
89
|
04 Dec 2019, 14:18 |
Adriano Violante | General | Information | Summary of the technical integration meeting |
FXE
- No major issues - PLCs update has been started by EEE (BB)
SCS
- Hrixs and related components will be delivered on 13 and 14.01.2020. SCS is coordinating the works with TS in order to crane the chambers into the hall (collision with the scaffolding required for HED dipole laser)
- Puls picker update in XTD10. Requires update of loops. EEE is not informed. JTD follows the issue up.
EEE
- General work is ongoing.
- Next week the EPS loops will be updated in the framework of the full beam operation project.
- Issue with a PLC in SPB crashing after update to Win10. Beckhoff is working to a solution. If this does no work the PLC will be replaced.
Controls
- A mail will be sent out early next week to announce th deployment schedule of the new Karabo release.
|
88
|
28 Nov 2019, 15:42 |
Andreas Galler | General | Problem | affected ITDM Systems after power cut tonight |
XHQ.E1.092
SW-HH-AL-271 was available
SW-HH-AL-272 came back after the DL switch was back (see below, ca 09:33)
SW-HH-AL-273 had to be power cycled and rebooted by NOC through console to come back fully (ca. 10:52).
SASE1 balcony room 38
restarted at 4am:
DELL servers:
exflprx03n0
exflprx04n0
exflprx112
exflpcl01n0 to 08n0
exflpcl18n0
SuperMicro servers:
exflonc09 to 12 (4-in-1 chassis)
exflong06
IBM ESS systems stayed off, as well as storage jbods
exfl-ons-gs111 and 112
exfl-ons-gl111 and 112
exfl-ons-gl113 and 114
IBM server (hosting ems servers for OS installations) was off as well
exflkvm01
SuperMicro servers stayed off:
exflong03 to 05
juniper (management network) switch stuck at booting, power cycled, after long time finally came back, but we were lacking management network over whole site
SW-HH-AL-DL-07 (office network distribution layer) switch was stuck at booting, came back after power cycling. Some (not all) office switches were not available because of this, seemingly the failover between AL and DL didn't work. Both this switch and the (permanently available) ...DL-08 were correctly cabled to separate PDUs.
Second fuse in BR38 rack 7 was out and had to be pushed back in manually (made power redundant again).
SA1 tunnel:
exflcon08n0 restarted at 4am, but apparently switch in the tunnel was off till 10:30 and since that time the server was accessible
E0.604
All systems were affected. We need the clear statement from YS why the second line did not work.
DELL servers rebooted at 4am:
exflprx01n0
exflprx02n0
exflpcl51n0
exflpcl52n0
exflpcl53n0
exflcon03n0
exflcon04n0
exflcon05n0
exflcon150
exflcon153
exflcon156
exflcon157
exflons01 and 02
exfldaq01 and 02 (gitlab CIs)
exflst105 (karabo project db - development and labs)
IBM servers stayed off:
exflpcl54n0
exflpcl55n0
exflpcl56n0
exflpcl57n0
exflonc41
exflonc41
IBM ESS system stayed off:
exfl-ons-gs901 and 902
There are also several servers (proxmox, serving VM OnlyOffice) all rebooted at 4am
List of h/w failures:
exflpcl05 PSU dead
exflong04 and 05 PSU dead (in exflong04 was actually since yesterday after reboot for OS updates)
may not be related to power glitch
exflprx106 RAM DIMM error
Intel server:
exflonc21 to 24 (4-in-1 chassis) PSU dead
|
87
|
27 Nov 2019, 09:25 |
Andreas Galler | General | Information | dispatch meeting Mon Nov 25 2019 |
FXE: no issues
SPB: no issues
MID: Split & Delay line arriving on Friday, MID aims for a quick integration into instrument / beamline
EEE informed to switch Hexapod motors from loop3 to loop 7
HED: changing loop1 (JJ X-ray motors) from open to closed loop operation
SQS: KB works, see sometimes spontaneous switching of end switch logics
EEE: MID, SPB, VAC loop updates running this week;
no triggers for experiments available until end of power off work
Jörn: cabling for MID is in full swing, for future installations first check phase 1 cabling, for non blocking
HED: cabling
SCS company Witte 30 ccables
FXE: two CRDs not approved yet, no cabling during this shutdown
Controls:
|
86
|
20 Nov 2019, 10:12 |
Adriano Violante | General | Information | Minutes of the Technical integration meeting 20.11.19 |
FXE
- Wille was asked by D3 to pull new cables for the Pandora in FXE on 19.11.. This was not known by FXE. Will be discussed with Safety/DNölle.
- Mono was fixed and is now ready for commissioning with beam
SPB/SFX
- uTCA update planned for tomorrow#
- Chris Blöm will leave the company next week. His tasks need to be re assigned.
- Order of loops upgrade will be discussed with M.Stupar as soon as he is back.
- The drag chain will be opened for cables re organization. HV cables will be also replaced by Wille . SPB/SFX will get the new HV cables from Sonay Sayar.
SCS
SQS
MID
- Loop11 (AGIPD) needed. The task was not envisaged in the shutdown task list and is required by the detector group. Will be discussed with MS.
- It has to be checked whether the delivery of the SDL is confirmed and the patch panels infrastructure is ready for cables installation.
HED
Optical lasers
VAC
XRO
XPD
DET
EEE
- Power supplies - firmware update will be performed in the next days. Mail will be sent around.
- Tming system update. No triggers will be available. Will be announced by mail.
- uTCA CPUs migration. The CPUs stored valued will be lost. Karabo devices will need to be re installed. Karabo stored values will not be lost. Will be announced by mail.
Controls
- The overnight and weekend OCD service will stop during the shutdown. OCD only available in the time 6:00 - 18:00
- Karabo 2.7.0 deployment date for the tunnels is the 13.12.- Instruments to follow.
ITDM
SRP
TS
- The power cut works will start at 6:00 in the morning. The electronics should ne put in a safe state the day before.
- TS can provide support for temporary light and powerr during the power cut periods.
AoB |
85
|
13 Nov 2019, 10:12 |
Adriano Violante | General | Information | Status report after tech. Int. Meeting 9.30 |
FXE
- Radiation tests ongoing.
- EEE informs that the PLC drawings will be exchanged in the WS
SPB/SFX
SCS
SQS
MID
HED
- During the first week of shutdown (KW47) the loop1 devices will be put into closed loop (e.g. for backlash compensation).
- An electrical shutdown seems to be necessary to upgrade the protection against the power glitches, especially to protect the optical lasers. This is now planned for the 17/18.19 for SASE2 and similar dates for SASE1 and 3. AV will try to collect more information and come back to the instruments ans technical groups.
Optical lasers
VAC
XRO
XPD
DET
EEE
- EEE needs the updated interlock definitions from VAC
- The list of requested services during the WS is very long. NJ is trying to plan the works inside EEE and will come back to XO/PMO in case priorities have to be assigned. Also, late requests and changes are making things more difficult.
Controls
- The overnight and weekend OCD service will stop during the shutdown. OCD only available until 18:00
- Karabo 2.7.0 deployment date (now forseen for KW51) is being verified. More info to come.
ITDM
SRP
TS
AoB |
84
|
12 Nov 2019, 09:49 |
Adriano Violante | General | Information | Status report after dispatch meeting 09.00 |
FXE
- FXE – radiation tests and LPD tests planned for this week. Small issues with the scan tools are being addressed.
SPB/SFX
SCS
SQS
MID
- First measurements with the pulsed magnet have been performed last week with the power supply installed temporarily in the experiment hutch. This week only the cryostat is going to be used. Next step will be to bring the magnet power supply in the rackroom to comply with the electrical safety requirements. MID will follow it up.
HED
Pptical lasers
VAC
XRO
XPD
DET
EEE
Controls
- Many IT/controls services will be down in KW48 (shutdown)
ITDM
- Server 13 for SCS will be down today.
- General remark from Controls and ITDM: devices and functionalities (e.g. new devices in the DAQ, data aggregators…) that have not been tested during the normal working ours should not be used during shifts in the weekend or during the night. This creates a huge and evitable overhead for the people in OCD.
SRP
TS
AoB |
83
|
28 Aug 2019, 10:33 |
Adriano Violante | General | Information | Minutes of the Technical integration meeting 28.08.2019 |
XO
FXE
- Leak in the LPD cooling system has been found. DET on it. Ongoing
- Laser went out of synch several time during the last weeks. Being addressed with the synch. group.
- Mono middle layer is not working properly. Calibration parameters are not reloaded correctly after restart. CAS on it. Ongoing.
- SA1 MOV loop has been updated. Minor issues with the CRL encoders are being addressed.
SPB/SFX
- CSLITS - discrepancies between the behavior of normal motors vs MC2 motors. CAS on it. ==> will be fixed once Karabo 2.6.1. has been deployed.
SCS
SQS
MID
- During last WE big issues with the AGIPD were experienced. Probably calibration pipeline related. DET on it.
- Laser hutch A.07 is not supposed to be accessible in the next weeks because of the laser operation. SRP points out that they are not sure whether the interlocks are properly working and active. To be clarified offline between MID, HED and SRP.
HED
- Access to the experiment hutch, Optics and Rackroom will be restricted this week due to laser shots tests.
Optical lasers
VAC
XRO
- Change of middle layer devices for the attenuator in SASE2 will be discussed offline with CAS
XPD
DET
EEE
- Loops are being updated in coordination with the instruments.
CAS
- 2.6.1. ready to be deployed. Deployment schedule has been agreed with individual groups.
ITDM
- Maxwell cluster maintenance on 2-3. 09.
- Control PCs wil be deployed during the shutdown week
- Claoud service (DESY platform) will be put into operation. An official announcement will details will follow.
SRP
TS
AoB |
82
|
26 Aug 2019, 09:52 |
Adriano Violante | General | Information | Report after dispatch meeting 09.30 |
XO
- Today a test of the fire alarm system will take place. Mail has been circulated by SRP.
- From next monday the dispatch meeting time slot will change to 8.30. Chair will be with XO.
FXE
- Leak in the LPD cooling system has been found. DET on it.
- Laser went out of synch several time during the last weeks. Being addressed with CAS.
- Mono middle layer is not working properly. Calibration parameters are not reloaded correctly after restart. CAS on it.
SPB/SFX
- CSLITS - discrepancies between the behavior of normal motors vs MC2 motors. CAS on it.
SCS
SQS
MID
- During last WE big issues with the AGIPD were experienced. Probably calibration pipeline related. DET on it.
HED
- Hirex 2 commissionig ongoing.
- Mono commissioning - cameras were found not to work. CAS/EEE to check.
- Access to the experiment hutches will be restricted this week due to laser shots tests.
Optical lasers
VAC
XRO
- SASE1 FEL imager was damaged following the last power cuts and EPS/MPS issues. Will be replaced by Thursday.
XPD
DET
EEE
CAS
- 2.6.1. ready to be deployed. Deployment schedule has been agreed with individual groups.
ITDM
SRP
TS
AoB |
81
|
21 Aug 2019, 11:15 |
Adriano Violante | General | Information | Minutes of the Technical integration meeting 21.08.19 |
XO
- A review of the procedures in case of power failure is in progress. Thanks to everybody for the efforts during the last days.
FXE
- Remote control of the radiation shutter dows not work. IP of the new computer is needed. Will be solved offline between FXE, CAS and ITDM. ==> Done for FXE. Small issues being fixed for MID.
SPB/SFX
SCS
- Support from EEE is needed to make sure motors needed for the user experiments in 2 weeks are actually working (e.g. Elmo). ==> fine tuning of the support plan will be made between SCS and EEE.
SQS
MID
- DPS turbo pump issue. A software workaround exists. The problem is that the used controller has not been commissioned firmwarewise before. This is not a showstopper and wil be addressed later. ==> The cabling is done differently. EEE is testing the device + firmware. ==> Ongoing
HED
- The smaract stages with the current firmware can be either driven fast or precise. EEE will discuss with the isntruments involved how to modify the stages implementation to be able to have both options available.
Optical lasers
VAC
XRO
- There was an issue with a drift of the HED mirror. As a consequence, VAC and XRO have switched of the mirror cooling. HED and MID should report about the change of the situation. ==> still exchange of information needed. ==> Measurements from MID have been received. HED will do the same. Investigation of the problem will happen next week (shutdown)
XPD
DET
- Calibration database haes been migrated. If problems are experienced please send a ticket to DET.
EEE
- Loop updates in the tunnels and instruments being scheduled together with the involved groups.
CAS
- 2.6.1. being prepared. Deployment plan is still valid.
ITDM
SRP
TS
AoB |
80
|
19 Aug 2019, 11:11 |
Adriano Violante | General | Information | Report after dispatch meeting 09.30 |
General
- Still recovering from the power loss occured on Saturday (The primary line was affected). In the hall the power was down for about 30 minutes, while in the tunnels it seems it was only a glitch.
- It is clear that it was a major system failure. Optimization of procedures and responsibility will be discussed within the DOD.
FXE
- Issues with the acquisition of images fromt he Jungfrau detector with the last version of Karabo. DET to follow it up offline.
- There are concerns about the replacement of the simple motor with the MC2 library, in particular about whether all functionalities will still be available (e.g. step-up/down). According to EEE this should be okay. CAS has already release the new library for testing. ==> will be done in thw WS for FXE, later for th tunnels and the other instruments.
- Remote control of the radiation shutter dows not work. IP of the new computer is needed. Will be solved offline between FXE, CAS and ITDM.
SPB/SFX
- Hexapods are being integrated. ==> This was rescheduled due to the issues with hexapods at HED and MID. Currently, there is no dire need to integrate the SPB/SFX hexapod, it can be run from TwinCAT. ==> postponed.
SCS
- Support from EEE is needed to make sure motors needed for the user experiments in 2 weeks are actually working (e.g. Elmo).
- If issues with the pulse IDs occur, AS, PG and BF are to be contacted (part of the trigger board)
SQS
MID
- DPS turbo pump issue. A software workaround exists. The problem is that the used controller has not been commissioned firmwarewise before. This is not a showstopper and wil be addressed later. ==> The cabling is done differently. EEE is testing the device + firmware. ==> Ongoing
- Vacuum interlock worked fine following the power failure.
- Recovering from the power failure. Definition of check list in progress.
HED
- Recovering of Loop 9 is ongoing (motors fpor Mono1 and 2). EEE is supporting.
- Jungfrau has been fully recovered. Epix in progress.
Optical lasers
VAC
XRO
- There was an issue with a drift of the HED mirror. As a consequence, VAC and XRO have switched of the mirror cooling. HED and MID should report about the change of the situation. ==> still exchange of information needed.
XPD
DET
- In general, it seems that no major issues occured after the power loss.
- In FXE the power supply and the chiller for the LPD are connected on different power lines and this lead to the fact that, after the power came back, the power supply was back on while the chiller was off. This should be avoided anc hecked by the instruments.
EEE
CAS
- 2.6.0. being prepared. ==> Sneak peak was deployed in SPB/SFX. Actual deployment datas can be found in the Shutdown planing, will be discussed in the chapters and with the SASE responsibles. ==> tests with ITDM being planned.
ITDM
SRP
TS
AoB |
79
|
14 Aug 2019, 10:01 |
Gerd Wellenreuther | General | Information | Minutes of the Technical integration meeting 14.08.2019 |
XO
- On Monday at around 12:20 there was a power glitch at least in Hamburg, affecting the machine.
- In this cause, the startup was delayed due to a missing signal from the Vacuum EPS-MPS-interface. The signal had to be manually enabled again.
- Tuning is estimated to take until 14:00 today.
- In the wake of such events a lot of communication about the machine status is happening. In the future, XO will ensure the readiness mailing list will be updated, too. In this respect, P. Gessler suggested to rethink / rename the multitude of mailing lists inherited from the construction phase.
FXE
- There are concerns about the replacement of the simple motor with the MC2 library, in particular about whether all functionalities will still be available (e.g. step-up/down). According to EEE this should be okay. CAS has already release the new library for testing.
SPB/SFX
- Hexapods are being integrated. ==> This was rescheduled due to the issues with hexapods at HED and MID. Currently, there is no dire need to integrate the SPB/SFX hexapod, it can be run from TwinCAT.
SCS
- There is an issue with the main sample stage. SCS and SEC are working on it, will continue with commissioning the instrument.
SQS
- Loop 14 will be updated today.
MID
- DPS turbo pump issue. A software workaround exists. The problem is that the used controller has not been commissioned firmwarewise before. This is not a showstopper and wil be addressed later. ==> The cabling is done differently. EEE is testing the device + firmware.
HED
- Loop 13 has been commissioned.
Optical lasers
VAC
XRO
- There was an issue with a drift of the HED mirror. As a consequence, VAC and XRO have switched of the mirror cooling. HED and MID should report about the change of the situation.
XPD
- During an intervention in XTD1 the LED for the Self-Seeding setup was replaced.
DET
EEE
CAS
- 2.6.0. being prepared. ==> Sneak peak was deployed in SPB/SFX. Actual deployment datas can be found in the Shutdown planing, will be discussed in the chapters and with the SASE responsibles.
ITDM
SRP
- The primary door of the HED experiment is currently not guarded with a magnet against incidential opening of the door leading to a trip of the machine. KWitt has to redo some cabling, until then, users can set the laser interlock, which will engage the magnet.
TS
- Controller for the hexapod is currently in the MID control room. UBrueggmann should check the installation.
AoB
- Please check the shutdown planning
- No dispatch meeting on Friday.
|
78
|
12 Aug 2019, 09:50 |
Gerd Wellenreuther | General | Information | Status report after dispatch meeting 12.8. |
XO
FXE
- XTD1 CRLs: There is an issue regarding a limit switch, to be repaired in the shutdown by MKnoll + EEE.
SPB/SFX
- Master loop has to be updated. EEE to agree offline with SPB/SFX ==> has been fixed
- Hexapods are being integrated. ==> was supposed to be tackled today. But since both HED and MID experienced different issues with their hexapods, the commissioning at SPB/SFX has to rescheduled (Tuesday?)
- Micro KB encoders + beam are drifting away, so closed loop operation would stabilize things... has to be commissioned, foreseen for Wednesday. Users start at Thursday...
- A microscope got stuck on a limit switch. Probably the limit switches have to be rewired.
- An encoder in loop 11 seems to be missing. EEE is on it...
SCS
- Since Sunday there appears to be an issue with the in-vacuum sample stage. Is kind of urgent...
SQS
- Last week: Commisioned the laser
- This week: Users & night shift
MID
- There is an issue with the hexapod, EEE is on it.
- Chris is testing some cooling / heating using peltier elements.
HED
- Train IDs are missing in loop 5 and 10. EEE is on it, too.
Optical lasers
VAC
XRO
XPD
- There is probably an intervention in XTD1 to repair a camera for the self-seeding setup. Others might want to jump on the train. Time is not yet decided.
DET
EEE
CAS
- Test for 2.6. are ongoing.
ITDM
SRP
TS
AoB
|
77
|
07 Aug 2019, 11:55 |
Adriano Violante | General | Information | Minutes of the Technical integration meeting 07.08.2019 |
XO
The accelerator is now working at 2.25 MHz. Kicker can be used. DET informs that for repetition rates different to the ones been used so far the calibration can be significatively different.
FXE
SPB/SFX
- Hexapods are being integrated.
- Master loop has to be updated. EEE to agree offline with SPB/SFX
SCS
SQS
- Commissioning of smaract stages done. 1 encoder cable is being checked (seems a problem of definition).
MID
- DPS turbo pump issue. A software workaround exists. The problem is that the used controller has not been commissioned firmwarewise before. This is not a showstopper and wil be addressed later.
HED
Optical lasers
VAC
XRO
XPD
DET
- Offline calibration update has been performed in SCS. Tests are foreseen for today.
EEE
- A new karabo device updating the digitizers with the beam parameters in real time has been successfully tested last week.
CAS
ITDM
SRP
TS
AoB
The dispatch/tech. integration meetings will be re organized in the near future. Slides are attached. |
76
|
05 Aug 2019, 10:19 |
Adriano Violante | General | Information | Status report after dispatch meeting 09.30 |
XO
FXE
- Photon3 detector has been fully implemented.
SPB/SFX
- Some issues reading the encoders of the JJ XRay CSLIT. EEE checks whether similar issues are also present in other instruments. ==> has been fixed.
SCS
SQS
MID
- 2 Motors have to be checked: Rotation of the hexapod and the y motion of the AUX3 are needed for next week.
- DPS turbo pump 3 behaving strangely. EEE to have a look
- Loop 7 has to be updated. Offline discussion MS/JH
HED
- Grating holder motion HED OPT. Motors to be commissioned. EEE required
- Cable needed for the Jungfrau timing signal. KS BF to discuss offline.
Optical lasers
VAC
XRO
XPD
DET
EEE
CAS
ITDM
SRP
TS
AoB
|
75
|
02 Aug 2019, 09:10 |
Adriano Violante | General | Information | Info on dispatch meeting 09.00 |
The meeting did not take place since only EEE was attending. |