Technical integration and coordination SASE1 Status and SASE3 Readiness
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 173     Entry time: 29 Oct 2020, 08:11
Author: Frederik Wolff-Fabris 
Location: General 
Severity: Information 
Subject: Notes XO Integration Meeting 28.10.2020 
General Announcement:
-	 

CTRL:
- SA3 VAC loop - 2 approaches to find out the root cause (discussed also with EEE):
1. Thursday 8-11:00AM to test the whole loop by partitioning batches of devices. This may pinpoint the single device that cause the problem.
2. Reproduce the problem at lab level. Based on the reproducibility this approach will be continued in parallel. 

DA:
- Nothing to report.

EEE:
- PLC colleagues are troubleshooting SA3 VAC loop.
- DET reported that measurements are carrying on wrong train-IDs. Tests are being made in the lab (not reproducible) but EEE is working on it.

VAC:
- SA3 VAC loop is main activity - interaction with Michaela P.

XPD:
- Group mainly busy with Photon Diag Conference this week.
- Supporting STAB and not heard any major issues in this effort.

DET:
- Report on the train-ID. This affects all the AGIPDs including the mini-half.

ITDM: 
- Nothing to report.

XRO:
- Nothing to report.

LAS:
- Preparing for next week operation.

UNSYS:
- Nothing to report.

SPB:
- Collected lot of data last few days: SPB/SFX thanks LAS and accelerator teams for support.

FXE:
- Nothing to report.

MID:
- All fine.

HED:
- All fine.

SCS:
- Issue with door interlock: Eric B. has investigated this morning. Problem seems to be with the maglocks and has been solved for now but a long term has to be worked on.

SQS:
- Nothing to report.