Technical integration and coordination SASE1 Status and SASE3 Readiness
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 172     Entry time: 26 Oct 2020, 11:18
Author: Frederik Wolff-Fabris 
Location: General 
Severity: Information 
Subject: Notes XO Integration Meeting 26.10.2020 
General Announcement:
-	 

CTRL:
- SA3 vacuum loops problems: seems to compromise some experiments. Beckhoff loops are changing states very quickly and compromises the whole system. 
CTRL ask for the instruments to give info on the type of command given that makes motors change states. CTRL investigates together with EEE as more data has been produced 
as compared to the past. 
This problem does not happen in SA1/SA2 and may be related to the PES which will be checked this afternoon.
- Please call the new OCD numbers: 6541 and 6542. Specially on weekends it is the fast way to contact. This number is valid since last spring.

DA:
- Nothing to report.

EEE:
- Nothing to report.

VAC:
- Nothing to report except of SA3 vacuum loops.

XPD:
- Not present.

DET:
- XO asks on the train-ID progress of Agipd. Monica T. says that the plan is to correct in the DAQ level during the next shutdown. 
K. Wrona adds that the fixing takes long and the current investigation focus on doing in the DAQ level during January.

ITDM: 
- Maxwell nodes used to login in the Maxwell will be rebooted today, causing access limitations.

XRO:
- Nothing to report.

LAS:
- Bunch pattern in demand: LAS assume XO will take care of this topic. Andreas G. says XO will take care but need to be informed on what is needed. 
Tomasz J. mentions it needs some coordination between instruments and machine.

UNSYS:
- Couple of issues in SA3 undulator cell: it got stuck, mostly during machine development times by running out of range. This was corrected during the weekend.

SPB:
- Moving on with WP8. Continuing today.

FXE:
- Nothing to add.

MID:
- MID makes a general reminder on the train-ID development with AGIPD: MID expects to have a meeting to discuss a long term solution plus the test procedure for 
implementation after the quick fix. 
This has to be planned in advance.

HED:
- Nothing to report.

SCS:
- Nothing to report.

SQS:
- SQS has suffered during the weekend with the VAC issue.