ID |
Date |
Author |
Location |
Severity |
Subject |
Text |
 |
208
|
17 Mar 2021, 09:15 |
Arvid Gebhardt | General | Information | Notes XO Integration Meeting 17.03.2021 | General Announcement:
- nothing.
CTRL: |
|
224
|
12 May 2021, 09:21 |
Arvid Gebhardt | General | Information | Notes XO Integration Meeting 12.05.2021 | General Announcement:
- User Operations Meeting takes
place on next Friday 09:00. |
|
234
|
16 Jun 2021, 08:37 |
Arvid Gebhardt | General | Information | Notes XO Integration Meeting 16.06.2021 | General Announcement:
- Interlock test next 2 weeks starting
on monday - from next wednesday the photon |
|
245
|
26 Jul 2021, 09:20 |
Arvid Gebhardt | General | Information | Notes XO Integration Meeting 26.07.2021 | General Announcement:
- Power glitch 3 times at night,
what brought down the beam for 1,5 hour each |
|
246
|
28 Jul 2021, 09:29 |
Arvid Gebhardt | General | Information | Notes XO Integration Meeting 28.07.2021 | General Announcement:
- No general announcement.
CTRL: |
|
87
|
27 Nov 2019, 09:25 |
Andreas Galler | General | Information | dispatch meeting Mon Nov 25 2019 | FXE: no issues
SPB: no issues
MID: Split & Delay line arriving |
|
88
|
28 Nov 2019, 15:42 |
Andreas Galler | General | Problem | affected ITDM Systems after power cut tonight |
XHQ.E1.092
SW-HH-AL-271
was available |
|
95
|
15 Jan 2020, 09:09 |
Andreas Galler | General | Information | notes Dispatch meeting Jan 13 2020 |
SPB:
Testing coordinated movement |
|
96
|
22 Jan 2020, 09:16 |
Andreas Galler | General | Information | notes Dispatch meeting Jan 20 2020 |
SPB:
nothing to report
FXE: |
|
99
|
26 Feb 2020, 09:06 |
Andreas Galler | General | Information | notes Dispatch meeting Feb 24 2020 | SPB:
nothing to report
FXE:
not present due to group |
|
100
|
04 Mar 2020, 08:49 |
Andreas Galler | General | Information | notes Dispatch meeting Mar 2 2020 | SPB:
AGIPD improvement campaign
great success
EEE --> 2nd C&C |
|
103
|
18 Mar 2020, 09:26 |
Andreas Galler | General | Information | Technical Integration Meeting 18.03.2020 |
SPB:
interument parked
power |
|
104
|
23 Mar 2020, 08:57 |
Andreas Galler | General | Information | notes Dispatch meeting Mar 23 2020 | Currently EuXFEL
enforces a hand-off policy for instrument/tunnel
hardware. That includes remote control of |
|
105
|
25 Mar 2020, 09:32 |
Andreas Galler | General | Information | Technical Integration Meeting 25.03.2020 | Currently EuXFEL
enforces a hand-off policy for instrument/tunnel
hardware. That includes remote control of |
|
Draft
|
30 Mar 2020, 08:57 |
Andreas Galler | | | | CTRL:
Broker Pile Up in 4 topics
over the weekend
LAS affected |
|
107
|
01 Apr 2020, 09:19 |
Andreas Galler | General | Information | Technical Integration Meeting 01.04.2020 |
CTRL:
productive meeting with |
|
109
|
08 Apr 2020, 08:45 |
Andreas Galler | General | Information | Technical Integration Meeting 08.04.2020 |
CTRL:
no bigger issues
announcement: |
|
110
|
15 Apr 2020, 09:03 |
Andreas Galler | General | Information | Technical Integration Meeting 15.04.2020 |
CTRL:
notificagion service device |
|
145
|
22 Jul 2020, 09:22 |
Andreas Galler | General | Information | XO integration meeting 22.07.2020 | General Announcement:
Default beam positions
are being implemented for each SASE at the |
|
146
|
27 Jul 2020, 09:05 |
Andreas Galler | General | Information | Notes XO Integration Meeting 27.07.2020 |
General Announcement:
XO discusses the need for |
|