209
|
22 Mar 2021, 10:14 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 22.03.2021 |
General Announcement:
- The Covid-19 health task force is looking into testing schemes to be employed on-site. In the future there will be an opportunity to do the self-tests on-site for
people who does critical works.
- The UOM series will restart on next Friday 26/03 at 09:00. Communication via e-mail will be send.
CTRL:
- Follow-up for delay train-ID: progressing with discussion on using longer time data.
DA:
- Thomas Michelat reports one issue with Agipd. The Maxwell server was restarted and then issue was fixed. If something similar happens again, the advice is to contact
Maxwell team from Desy.
EEE:
- Today EEE perform the SEPS update for SA3 Interlock. For SA2 the test takes place on Thursday.
VAC:
- Not present.
XPD:
- Nothing to report.
DET:
- Nothing to report.
ITDM:
- ITDM reminds on the storage/cache maintenance taking place next week (inclusion of additional storage place). Janusz S. will send an e-mail to readiness list.
XRO:
- Nothing to report.
LAS:
- SA3 PP-laser is off today due to work on interlock system. LAS hopes to get back as soon as possible (not before Thursday/Wednesday) for SCS use.
UNSYS:
- Problem in cell36/SA1 (communication error). A ZZ will be needed to recover the cell.
SPB:
- Ongoing with preparations for back-up user experiments; A problem with Jungfrau has been communicated.
FXE:
- Problem with Mono last week: positions for the crystals were shifted by 10mm. It is not known if this is a physical or only reading issue.
MID:
- Pressurized air by a compressor was moved to another location; the topic was discussed with TS and a big compressor will be installed until May 1st to solve problems.
HED:
- Nothing to report.
SCS:
- Issued a ticket with EEE to verify possibility to averaging positions on middle layer servers.
SQS:
- Preparing for beam in April. |
208
|
17 Mar 2021, 09:15 |
Arvid Gebhardt | General | Information | Notes XO Integration Meeting 17.03.2021 |
General Announcement:
- nothing.
CTRL:
- LAS reported the pulse statistics did not work properly: re-started systems due to lost connections.
- OCD call related to HED AGIPD test system: fix ongoing.
- Update on train-ID slow data on XGM: CTRL is in touch with Desy and Theo. Question to SPB and XPD: how much effort is needed for that CTRL and ITDM to place the missing information in the run. Involved parts will discuss an agreement by the end of the week. Steffen H. will prepare a summary to inform XPD.
DA:
- no important news.
EEE:
- no important news.
VAC:
- nothing to report.
XPD:
- nothing to report.
DET:
- nothing special.
ITDM:
- all fine.
XRO:
- Not present.
LAS:
Going fine: Laser pattern issue from yesterday was solved by CTRL.
UNSYS:
- Problem on Monday with quad mover cell18/SA1 took 6 hours on ZZ. It is now fixed.
- A problem with undulator segment on cell36/SA1 needs diagnostic and eventual ZZ access. RCs are contacted.
SPB:
- The samples to be used next week are challenging to prepare.
FXE:
- Used beam yesterday. No problems to report.
MID:
- all fine.
HED:
- nothing to report.
SCS:
- nothing to report.
SQS:
- all good. |
207
|
15 Mar 2021, 11:26 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 15.03.2021 |
General Announcement:
- Following Desy e-mail to all EUXFEL staff, the emergency call system of the elevators will be offline on Thursday March 18th during the morning. Please avoid using the
elevators in this day.
- On March 23rd is scheduled the SEPS interlock tests in SA3. On March 25rd is planned for SA2, pending a confirmation with the machine on the impact in SA1 operation.
CTRL:
- Progressing with investigating the train-ID issues, currently it relates to DOOCS/Desy.
- DOC: reports one fix today at 13:00 (following a call). Please respect a sign "we are in", "we are out" at the DOC to help staff focusing on issues.
DA:
- Nothing to report.
EEE:
- Nothing to report.
VAC:
- Nothing to report.
XPD:
- All working fine in XPD.
DET:
- Detector commissioning in SPB: AGIPD was completed as planned and Jungfrau seems to run properly (data to be analyzed.
ITDM:
- ITDM will add more space to the storage system (data taking). Initial idea is to make it on March 30th to minimize impact. Acquiring data and data analysis are not
impacted.
XRO:
- Beam power increase ongoing.
LAS:
- An issue with SA1 interlock in PP-laser room: the inside doors were reported to be open on Thursday afternoon.
As SPB was not using the PP-laser, the laser was put in safe mode and Interlock was broken to access and verify the situation. The internal doors were closed.
Further discussions will follow. This door issue happened for the first time in SA1.
- LAS is providing beam to SPB and HED as requested.
UNSYS:
- Couple of e-log entries on settings of air coils and phase shifter, all addressed during the weekend.
SPB:
- Detector program is completed. One measurement (which is not critical) is missing from Jungfrau.
- Interacting with DOC worked nicely.
FXE:
- Preparing for this week.
MID:
- Fully in preparation for first April beam. All fine.
HED:
- Nothing to report.
SCS:
- SCS asks for update of missing CPU from EEE. No news from EEE. Contact will be made.
SQS:
- Preparing to have beam in April. |
206
|
10 Mar 2021, 09:20 |
Arvid Gebhardt | General | Information | Notes XO Integration Meeting 10.03.2021 |
General Announcement:
- nothing for now
CTRL:
- A few issues for DOC: Cameras IP addresses need to be reconfigured
- Continuing investigation of train-IDs on Doocs/XGM (they oscillate). CTRL will follow and close contact with Theo M. and Desy colleagues.
DA:
- nothing to report
EEE:
- nothing to report
VAC:
- nothing to report
XPD:
- Not present.
DET:
- nothing special – commissioning this week
ITDM:
- nothing to report
XRO:
- Maurizio V. reminds the SEPS interlock check in SA3 still has to happen as it is a condition prior beam operation. Zunaira A. says she sent an e-mail to xo-planning.
F. Wolff-Fabris asks if the SCS door is fixed or not, a pre-condition for the test. Zunaira A. replies the problem was with the power supply to the door and is fixed.
A date for the SEPS test can be planned by XO.
LAS:
- SASE2 interlock: LAS got unexpected calls when disconnecting AMPHOS cables (thus triggering SA2 Interlocks).
- SA3 AMPHOS no news since Monday. The ADC cards do not receive train-IDs.
- LAS suffer of lack of laser lab, missing PLC installation. LAS asks XO for a follow-up on prioritizations.
- Zunaira says that lasers are coupled to the interlocks (yesterday event happens as all lasers in room A23 and A07 are connected to the HED and MID interlocks). Thomas Preston says it triggers the warning lights for the laser lab. Zunaira A. says if shutters are closed it shall not be a problem if lasers reach this shutter signals. Tomasz J. says that ideally they must be decoupled.
UNSYS:
- nothing to report
SPB:
- going on with the plan; Detector commissioning from tomorrow.
FXE:
- the floor works are ongoing - looking good.
MID:
- not present
HED:
- nothing to report
SCS:
- A new experimental chamber (chemistry chamber) will be installed for beam commissioning on next month. A CPU in rack room is needed for recommissioning the motor an Martin T. waits for feedback.
SQS:
- Staff is getting the search training which was expiring.
- Noticed issues notice with DACHS system which show the access properties with delay. |
205
|
08 Mar 2021, 10:49 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 08.03.2021 |
General Announcement:
- SPB/SFX will continue receiving beam this week for commissioning.
- Issues with access to the Operations/21 e-log: SPB run coordinator wrote to wrote to the admin but no answer so far. Entries by Adrian M. while using VPN also did not
work.
XO will follow with IT (see below).
- Gerd W. reports that works in SCS chicane are done and the radiation interlock keys are returned.
CTRL:
- Some observations triggered by DOC regarding XGM trains coming too late (20s). An update will be made later on the day or next days.
DA:
- Not present due to DOC shift compensation day.
EEE:
- Nothing to report.
VAC:
- Nothing to report.
XPD:
- A. Koch and Theo M. say no issues to XPD were reported. All operating fine.
DET:
- Commissioning beamtime with SPB detectors. The AGIPD program for last week was completed successfully.
ITDM:
- Janusz S. says on the e-log issues that administrator of the e-log has the power to include new people.
While using VPN access one can read the e-log and post entries using the copy function from another e-log. Nothing in the procedure has changed from past time.
XRO:
- Nothing to report.
LAS:
- SA1 PP-laser recovered power for SPB and is delivering in the nominal power level.
- SA3 AMPHOS was switching off at random during the weekend; no reliable operation in SA3. LAS is in contact with external company.
UNSYS:
- Cell4 and cell6 in SA2 required intervention from expert (Suren K.) during the weekend.
SPB:
- Drift of horizontal beam position was observed on the weekend and reported to the DOC which provided a tool to diagnostic the drift. SPB/SFX would like to thank the DOC
for the availability.
Beam pointing was changing every hour and was difficult to keep into M1 and M2. Theo M. says the XGM drift happened in the horizontal by many mm. DOC can not solve and
then contacted Optics group.
The observed drift seemed to be too big to be compensated. Richard B. says the movement was seen from XTD9 XGM and was a fast drift.
Andreas G. will address communication channels between DOC/DRC and PRC (PRC was not informed).
FXE:
- Floor refurbishment starts today.
- Last Wednesday it was checked the gate valves are corrected integrated in EPS and MPS. If shutter is open this signal is sent to the MPS and triggers closing V0.
MID:
- All fine.
HED:
- Nothing to report.
SCS:
- Nothing to report.
SQS:
- All good at SQS. |
204
|
03 Mar 2021, 09:23 |
Arvid Gebhardt | General | Information | Notes XO Integration Meeting 03.03.2021 |
General Announcement:
- Hick-ups in the beam operation are happening since last night. There is no obvious indications on the origin of the problem and MXL is investigating to restore a normal beam delivery condition.
- There is an issue with “Operation-2021” e-log where some SPB staff can’t login to create entries. This will be addressed by XO/PRC and ITDM (see ITDM entry).
CTRL:
- SA1 DAQ was dropping some trains (the late ones) in the XGM. CTRL and ITDM are following up and will test the XGM late this week or next week. CTRL will contact XPD for deployment first in SA2 and SA3.
DA:
- News from the DOC: deployment of major updates ongoing/to take place.
EEE:
- nothing to report
VAC:
- not present
XPD:
- Commissioning and setting up for SA3 HIREX
DET:
- preparing for commissioning Detectors
ITDM:
- Janusz S. says the configuration for the “Operation-2021” e-log uses the same configuration as previously set for 2020. F. Wolff-Fabris likens the issue with possible new users and asks SPB to provide the name of users who can’t login into the e-log.
Janusz S. says one can use the copy function from instruments e-log to place a copy into the Operations-2021 e-log. Jan G. says that login is necessary to avoid the entry being as “Anonymous”.
XO and ITDM will address it offline.
XRO:
- not present
LAS:
- In SA3 PP-laser one had exchange of power supply for AMPHOS due to communication errors.
- In SA1 PP-laser one observes a loss of 1/4 of power in AMPHOS. LAS is not sure if there is enough power for users.
- Two problems with triggers on Monday: 1. a faulty board in SA3; 2. MCS group update timing system caused trigger loss in all hutches (due to a bug in their server).
UNSYS:
- nothing to report
SPB:
- Couple of Helps asked to DOC and SPB/SFX are thankful for that.
- Login at Operation-2021 e-log does not work for 4 people.
FXE:
- Prepared for AIBS. Few PLC problems remain but not related to AIBS.
- Next week between Tuesday/Friday there are no access to the hutch due to floor work ongoing.
MID:
- all fine
HED:
- all fine
SCS:
- sliding door will probably be repaired today with an external company.
SQS:
- nothing to report |
203
|
01 Mar 2021, 10:49 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 01.03.2021 |
General Announcement:
- An e-mail from Steve Aplin informs on how to contact the DATA operation center during beam delivery times. It changes contact phone numbers for OCDs.
Old numbers are discontinued. The 98089 is the new number.
- The lead scheduling for machine/operation can always be found at the TTFINFO link (BKR E-log). Any other schedule is not official.
- Hutch search training goes invalid for many scientists in the instruments. Please check your status at the DARF-DACHS system or with RPOs.
- If there is anything unclear with masks or Corona rules, please give feedback in this meeting series or to the corona task force.
- Gerd W. says that works on SCS chicane are taking place right now. Afterwards a check will be done until Wednesday. The SCS key is still removed.
CTRL:
- Next days CTRL would like to solve DAQ situations while restarting devices. For SPB it is under discussion when to proceed.
DA:
- Not present due to planning meeting for end-to-end DA commissioning.
EEE:
- Fast electronics: a problem with SA3 PP-Laser (timing issue) was found and a board will be replaced.
- PLC side: deploying SA3 laser interlock. EEE will get in touch with XO for agreeing on a date.
VAC:
- XTD6 is still open and will be closed tomorrow (Tuesday 02.Mar) afternoon.
XPD:
- Friday at 15:00 there was a wide spread network issue and XGMs were giving warnings. The XGMs came back rather quickly but beam was lost until Saturday.
DET:
- Preparing for the SPB detectors commissioning with beam this week. One module was exchanged and will be evaluated next Monday.
ITDM:
- Nothing to report.
XRO:
- Not present.
LAS:
- SA3 PP-laser: issue on Thursday afternoon late; Replacement boards were received. Tomasz J. informs the triggers were lost in the last 5 minutes.
- Tomasz J. question if LAS is going to receive enough support on Mondays from the DATA center as they have to prepare lasers for Tuesday.
LAS expect same level of support on Mondays from DATA department. Steffen H. says that the OCD and Data Run coordinator will support the activities.
UNSYS:
- Nothing to report.
SPB:
- Receiving beam from tomorrow on.
FXE:
- Working with EEE to get Beckhoff loops finished for the AIBS test taking place at FXE on Thursday.
MID:
- All fine at MID.
HED:
- HED asks for the status on the ADC issue. Bruno F. says it is being fixed today (crate is up and running) and objective is to finish by today.
- Question to CTRL on cameras: S. Hauf says that CTRL will ask HED to test the fix. HED will contact Dennis G.
- Pouneh S. says that for laser safety googles it is exceptionally allowed to use FFP2 masks with filters. A. Galler points that the Corona task force strictly forbids
this type of masks at XHEL as protection against Coronavirus.
This subject will be brought to the Task Force for more clarifications.
SCS:
- Sliding door issue is ongoing. Eric Boyd says that Zunaira A. is in contact with the company and they will come to XFEL on Wednesday (it is caused by the controller of
the door).
SQS:
- Nothing to report. |
202
|
24 Feb 2021, 09:03 |
Arvid Gebhardt | General | Information | Notes XO Integration Meeting 24.02.2021 |
General Announcement:
- Due to a failure alarm in the smoke extraction system in XTD6+8+9, Desy colleagues will need to reboot a crate and exchange one module. This will bring down the air conditioning for the tunnels during about two hours. The activity is scheduled for March 1st starting at 11:30AM and it appears in the EuXFEL infrastructure calendar.
- It has been found a situation with one of the elevators to the XHEXP1 Hall. Due to corona regulations a maximum of 3 people is allowed simultaneously in the elevator. This number is indicated by signs/papers fixed nearby. However, someone unauthorized has modified the number “3” to an “8”. We are investigating the situation. The shields have been corrected back to “3” but we would like to remind signs and warnings must not be modified by unauthorized persons.
- Gerd W. informs that SXP chicane modification foreseen to take place today and tomorrow is shifted to Monday or Tuesday due to delays in delivery of components. Affected people have been contacted by PMO via but in case of issues with the new plan, please contact Gerd W.
CTRL:
- Few requests for tickets on Karabo devices were received. CTRL reminds to please add device ID in the ticket.
- SA3 motors: a few changes were done due to migration of MC2 motors. If someone or a group needs more input, please directly contact Steffen Hauf.
- Regarding Data Operation Center (DOC): CTRL would like to have a functional account to the instrument e-logs to be able to access it and track problems when OCD gets called. If instruments have any concerns with this, please contact Steffen Hauf.
DA:
- Nothing today.
EEE:
- No main issue.
- EEE also asks that when submitting tickets, please include the instrument and component name, preferentiably in the header.
- PLC side: ZZ to check motors.
VAC:
- Nothing to report.
XPD:
- Continuing today with beam commissioning of XTD6 components (HIREX and MCP).
DET:
- Nothing special to report.
ITDM:
- Nothing special.
XRO:
- Issues will be addressed when tunnels are open.
LAS:
- SA1 and SA3 PP-lasers are making progress.
UNSYS:
- Nothing to report.
SPB:
- Issues with Interlock and DACHS are solved.
FXE:
- Interlock issues are solved.
MID:
- Nothing special.
HED:
- Thomas Preston asks if the Covid regulations in hutches can be sent by e-mail. Sandra Plett will send the link to the documents after the meeting.
- The mask occupancy for the hutch was changed (are the signs updated or not?). Thomas P. says it was 4-5 but someone wrote new numbers in the signs. Sandra P. says that if everybody is using FFP2 masks, then more people are allowed than the max. occupancy.
- Pouneh S. says if people use laser safety googles, one can use FFP2 with filters. Sandra P. says that rules also apply for this case.
- Issues with cameras: DAQ did not run (did not take data, probably due to lost configurations). HED will send ticket.
SCS:
- Nothing to report.
SQS:
- Yesterday a meeting to review digitizers took place. |
201
|
22 Feb 2021, 10:14 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 22.02.2021 |
General Announcement:
- In case someone has any remaining question on the use of masks in the hutches please feel free to ask in this meeting series or write XO an e-mail.
- Racks for the SXP will be delivered and moved around XHEXP1 in March. The calendar for such activities will appear in the EXFEL infrastructure calendar.
The activity is coordinated by TS and in case of conflicts, please contact us or Ulf Brueggmann.
CTRL:
- Few configurations issues with motors are being taken care with EEE.
- XPD found a bug in the middle layer device and it needs new deployment. CTRL will contact people involved.
- DOC will start going on next week. Further info will be sent around and contact to single points in the instruments will be made.
DA:
- Preparing the DA contribution to the DOC.
EEE:
- Nothing to report apart the work for the configuration of motors.
VAC:
- Vacuum interlocks triggered on Friday in SA3. VAC reminds that when someone opens the shutter, nothing behind must be left in the beam.
XPD:
- A. Koch says commissioning of SA3 components and Imagers take place. The Shimadzu camera was tested with beam in SA1 and signal was observed.
DET:
- Preparing for regular support of Detectors.
ITDM:
- A question arises if SASE3 also operating. A. Galler says there is an effort for commissioning beam transport on SASE3, but focus for operation still remains in SASE1.
XRO:
- XRO has commissioned beam transport in SA3 and in SA1. Overall beam was stable apart of few interruptions. Objectives for the weekend were successfully completed.
- Couple of issues need to be fixed; XRO will request ZZ access in XTD10 together with EEE. Tickets are sent.
LAS:
- No news from last week.
UNSYS:
- Nothing to report.
SPB:
- Issues with Laser interlock system and accessing hutches persists, as reported last Wednesday. SPB expects laser safety to be working on that.
Romain Letrun confirms the problem is related to the DACHS access system.
FXE:
- It has faced similar problems with the interlock system as the ones observed by SPB/SFX.
MID:
- Hutch cleaning is planned this week.
HED:
- All fine.
SCS:
- Nothing to report.
SQS:
- Last Friday an interlock issue (no beam to hutch) was found but solved almost immediately. |
200
|
17 Feb 2021, 09:27 |
Arvid Gebhardt | General | Information | Notes XO Integration Meeting 17.02.2021 |
General Announcement:
-
CTRL:
- update for GUI server this morning is finished.
- CTRL advices people starting systems such as cameras, in case of connecting issues please try first to reboot the devices first.
DA:
- nothing special to report.
EEE:
- will update PPL update mTCA SASE3 - affects only LAS group
VAC:
- nothing to report.
XPD:
- Recommissioning diagnostics in SA1.
- Pop-in YAG screen in FXE/SA1 was found broken. Any information on when was working last time please send to Andreas K. In this Pop-in is a second screen with diamond which is working. YAG exchange is for next maintenance period.
DET:
- The offline calibration service update is finished and is available again. Please contact DET in case of issues.
ITDM:
- nothing to report.
XRO:
- Working at BKR yesterday with commissioning SA1 alignment; SA1 is aligned until SPB and FXE.
- Today continuing with SA2 depending on beam stability.
- Idoia F. mentions that computers were not running at BKR. A check after shutdowns and prior operation is welcome.
LAS:
- The AMPHOS in SA3 needs a new power supply. Expected delivery and exchange on Friday.
- PLC update in SA3 and uTCA upgrade on Friday.
- Advancing with SA1-PPL commissioning.
- LAS will send e-mail to Zunaira A. for that MEA3 personal is contacted on the problems with sensor boxes.
UNSYS:
- Ambient field coil was fixed.
- New minimum gaps will be calculated and communicated to XO.
SPB:
- After interlock test last week there is an issue with the new DACHS terminal. The hutches can’t be accessed. Pouneh S. says DACHS is working but this particular new terminal might not be activated in the system. An special permission must be given. Tobias Haas will be informed to contact MEA3.
FXE:
- Martin K. will ask FXE colleagues on YAG screen information. Currently he is not aware when this happens (similar event back in 2019).
MID:
- all fine.
HED:
- all fine.
SCS:
- in contact with Eric B. to get the beam shutter back on Friday for closing hutches during the weekend.
SQS:
- Early next week review with the digitizer engineers.
- Pouneh S. asks that laser interlock in laser hutch does not work. The new parts have been shipped and arrive soon. Together with TS electrician one has to exchange the relay. Daniel Rivas is informed. |
199
|
17 Feb 2021, 08:52 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 15.02.2021 |
General Announcement:
- It had been a cooling water issue with SA1 and SA3 PPLs on Saturday. Other groups are encouraged to check their components for eventual damage. Cooling water is back
again.
- Change on definition of a critical work: everything that leads to operation is from now on considered a critical work (official communication will be send by e-mail).
- Tomasz J. says interlock tests in SA1 tripped the laser interlock due to the Seeder connection to the interlock.
Andreas G. says there are care been taken to prevent this in future. More discussion will follow.
CTRL:
- Updates were done on the time servers and data loggers.
- GUI servers will be done this week as there was no access to GITLab. Current suggestion is next Wednesday morning before 08:00AM.
Each topic will take a few minutes only. XPD is fine with the proposed day/time.
DA:
- Nothing to report.
EEE:
- Issue during weekend: signals to the absorber. EEE and PRC (Maurizio V.) will coordinate when it is the best time for applying the final fix.
EEE needs to mask it for proceeding with the work.
VAC:
- VAC OCD was involved in the absorber EPS issue.
- Today around lunchtime the XTD6 and XTD9 will be closed.
XPD:
- EPS issues: any component driven to the beam was not protected by many bunches operation. The EPS was thinking the PNACT was closing but in reality, it was opened.
PRC/EEE/VAC/XPD OCDs solved by manually telling the system it is closed.
- Wrong bunch number sent to XGM: SA3 toroid was moved to a different position and the old name was not valid anymore.
Info from this toroid was not received and the consequence XGM was receiving wrong bunch numbers. This makes impossible for the XGM to calculate correctly the number of
bunches.
Doocs servers were not updated (these programs would need to be informed of new naming).
- Andreas K. says that XTD6 is clean. In XTD9 an intervention by EEE will take place. Bruno F. says that it is a simple task and we are accessing tunnels right now.
- Operation E-log 2021 is missing and must be created.
DET:
- Offline calibration work is ongoing until tomorrow morning.
ITDM:
- GPFS offline storage maintenance to be done today.
- ITDM was notified by Desy that is necessary to reboot logins on Maxwell nodes (between 11:00-12:00).
XRO:
- Nothing to add to what was discussed on the EPS.
LAS:
- Affected by water cooling incident. SA1 came up without issues but in SA3 there is problem as AMPHOS did not restart.
- Trigger issue on last week are not the issue anymore. This was not repeated (but SA1 still on local mode).
UNSYS:
- BBA and photon BBA last week: new values to be implemented and minimum gaps will be updated accordingly.
- Frank Brinker tested the ambient field corrections. A ZZ is taking place this morning to fix SA2/cell12.
Few other coils have different polarities and will be fixed today or in another ZZ.
SPB:
- Preparing for the first two weeks with beam in March.
FXE:
- Aligned the cameras in FXE mono.
- Crates to be installed in the rack room.
MID:
- Joerg H. raises the question on the FFP2 usage recommendation. Sandra Plett says the document containing guidelines will be prepared (hopefully today);
It is mandatory to use FFP2 masks if you are not alone; it also depends on the room size and at the moment it is 3-5 people in the hutches with mandatory use.
A. Galler says these are the current regulations and maybe this will change in future.
HED:
- Nothing to report.
SCS:
- Nothing to report.
SQS:
- Trying to get a new DAQ and will talk to ITDM. |
198
|
10 Feb 2021, 09:20 |
Arvid Gebhardt | General | Information | Notes XO Integration Meeting 10.02.2021 |
General Announcement:
- Tunnel closure: it has been decided both XTD6 and XTD9 will be searched and closed on Monday 15.02.
- Temporary tunnel access requests: for ZZ access please be aware of the new Redmine ticket for access requests. The link to it appears in the BKR E-log.
- Use of FFP2 masks in experiments control hutches: Sandra Plett informs rules such as temporary stop of work after 75 minutes of mask use or a day off after two working days with masks are not mandatory - these are only a recommendation; If two people are <1.5m, one has to use masks. While Seated or alone you can remove the masks; However, if there are people running around, please use masks also if seated; The wearing time is just a recommendation - it is not mandatory to make the break.
CTRL:
- Graphical user interface update: there is a new version to install in the gateway and BKR.
- Update of data loggers and GUI servers to take place.
DA:
- all going well.
EEE:
- SA2 loop update (MOV) was done yesterday for Hirex and Shimadzu.
VAC:
- nothing to report
XPD:
- DACHS terminal in XTD9 did not allow access: database connection issue. Andreas K. has contacted M. Prollius.
DET:
- Deployment of offline calibration pipeline from today until Friday. It will be communicated when it’s finished.
ITDM:
- Two weeks ago, ITDM pre-announced an offline GPFS update. Preparations will be ready by Friday. Ideally ITDM will deploy on next Monday. Please let K. Wrona aware if this date is not suitable.
XRO:
- Not present.
LAS:
- Upgrade on uTCA crate in SA1 – ADC acquires data. A small problem with data acquisition was found and a Redmine ticket was created. In any case all is fine for switching PPL-SA1 on.
- Today between 2:00-08:00AM there was no trigger coming to PPL-SA1. It may be from Desy or from Balcony room. Bruno F. will investigate the balcony rooms.
UNSYS:
- Unsys will request access for next week to fix a SA2 ambient coil.
SPB:
- nothing
FXE:
- nothing
MID:
- All fine
HED:
- nothing
SCS:
- nothing
SQS:
- Issues with trigger are fixed.
- uTCA firmware updated; now fixed. |
197
|
08 Feb 2021, 08:30 |
Arvid Gebhardt | General | Information | Notes XO Integration Meeting 08.02.2021 |
General Announcement:
- XTD10 tunnel was closed last Friday; XTD9 to be closed by end of this week; XTD6 is undefined – mostly likely by Monday. Any schedule deviation will be communicated.
CTRL:
- Deployment of offline services from 10.2 to 12.2. Services such as offline calibrations are not reliable in this time. An e-mail was sent and another reminder will be sent again.
DA:
- no news.
EEE:
- Update of PPL uTCA in SA1 today (laser);
- SASE2 PLC loop update to take place tomorrow at 13:00 (Hirex and Shimadzu camera).
VAC:
- Nothing to report
XPD:
- No issues to report.
- Andreas K. says in SA1 hardware activities are done; testing optical alignment.
- Hirex SA2 update is missing.
DET:
- nothing to report
ITDM:
- nothing to report
XRO:
- nothing to report
LAS:
- Switching on SA1 laser – after uTCA upgrade. Small issue relates to the missing trigger from Desy (dynamic triggers). Point of contact are Tim Wilksen and Lars Froelich.
UNSYS:
- Hick-ups with controls during the weekend. BKR opened gaps to 220mm and caused troubles (usually they open o 210mm).
- One ambient field coil needs ZZ for fixing (SA2/cell12); not urgent.
- Cleaning was done in XTD4.
SPB:
- setting up for the first set of commissioning
- Gotthard trigger seems to be solved.
FXE:
- nothing to add
MID:
- all fine
HED:
- nothing to add
SCS:
- not present.
SQS:
- uTCA digitizer issue: ongoing. |
196
|
03 Feb 2021, 09:26 |
Arvid Gebhardt | General | Information | Notes XO Integration Meeting 03.02.2021 |
General Announcement:
- Automatic Power Switch Testing was done yesterday. The switches are working as expected and a protocol has been produced. Torsten Schoen informs this test is done every 4 years; from now on equipment can be connected again to the orange and green power outlets.
- Re-start of the accelerator takes place from last Monday. Currently the setup of the injector and LINAC is ongoing. There are no changes to the last plan for closing dates of the photon tunnels.
CTRL:
- CTRL works on the Doocs Undulator devices/panels that have to be changed.
DA:
- nothing to report.
EEE:
- EEE and LAS people are on-site checking the reported uTCA problems after the power switch (by LAS). Issue refers to no communication to the uTCA.
- SASE1 motion loop update yesterday was done.
VAC:
- Not present.
XPD:
- XTD6 and XTD9 Shimadzu cameras update continue.
- Next loop update for XTD6 will probably be next week together with Hirex changes.
DET:
- all fine
ITDM:
- everything is fine
XRO:
- VAC is busy in tunnel leaking check the XTD10 soft mono (pressure went down to 10-6mbar already) but it takes more time.
LAS:
- Yesterday the SA1 and SA3 PP-laser systems were lost. Tomasz J. and EEE are looking into it.
UNSYS:
- today ZZ in XTD4 for the cleaning at SASE3. PRC has informed the BKR.
SPB:
- Problems with trigger of Gotthard are reported by Marcin S. It may be also linked to a communication issue.
FXE:
- nothing to add
MID:
- all fine
HED:
- nothing to add
SCS:
- not present.
SQS:
- Wanted to run digitizer on uTCA but could not find/communicate to it. Under investigation this afternoon. |
195
|
01 Feb 2021, 09:06 |
Arvid Gebhardt | General | Information | Notes XO Integration Meeting 01.02.2021 |
General Announcement:
- The test of the emergency automatic switch of power bridge is scheduled for Tuesday, 2nd of February 2021, 09:00. This will affect orange outlets in XHQ and green and orange outlets in XHEXP1. A short interruption in the power supply lines will happen. We expect all groups have taken appropriate measures to place devices in safe mode or connected to white power outlets.
CTRL:
- not much to report, things are running
- Read the docs is operational again. A given feedback to CTRL is welcome.
DA:
- Nothing special to report.
EEE:
- Tomorrow update sase1 motion loop at 13:00: an email will be sent to readiness mailing list.
VAC:
- Nothing to report.
XPD:
- Maintenance work ongoing: Imagers in XTD6; Work with EEE in XTD6 and XTD9.
DET:
- AGIPD: new control with new gain is tested. DAQ issue with data is fixed (K. Wrona informs it was related to a wrong hidden parameter setting).
ITDM:
- Downtime on Offline calibration system / GPFS: update to be made in about two weeks from now. K. Wrona says that ITDM would like to have one day of GPFS maintenance; it is important to switch to the new scratch files before we start operation. Data taking shall not be affected by this.
- Jan G. asks when would be required by the earliest. K. Wrona says they need to copy a lot of data before the update and it is estimated in two weeks (+-2 days), to take place in the second half of February. As photon activities take place in the last two weeks of February, one needs coordination to find a suitable date.
XRO:
- everything fine.
- Today closing of soft mono chamber in XTD10.
LAS:
- Upgrade in SA1 uTCA: information will be given to LAS this afternoon.
- Two Desy colleagues needs access in SA1 hutches. Use of FFP2 masks is mandatory.
UNSYS:
- ZZ in XTD4 is planned for Wednesday (for cleaning undulator area).
- Suren K. asks if the balcony rooms are effected by test emergency power switch. This will be discussed offline.
SPB:
- Nothing special to report.
FXE:
- Nothing special to report.
MID:
- all fine
HED:
- Nothing special to report.
SCS:
- Nothing special to report.
SQS:
- Nothing to report. |
194
|
27 Jan 2021, 09:08 |
Arvid Gebhardt | General | Information | Notes XO Integration Meeting 27.01.2021 |
General Announcement:
- FFP2-Masks needs to be used in the experiment control hutches from now on regardless the number of people working in this areas. Regulations concerning the maximum number of staff in this areas remain the same.
- SASE1 Laser interlock upgrade originally scheduled for this week was postponed to next week. As soon as we receive the information on the new date, this will be communicated.
CTRL:
- Intervention for the new scenes for the size of the labels was originally scheduled for yesterday. This was postponed as additional tests will be conducted in CTRL lab. A new date will be announced.
- Panel topics: some old types doocs undulator devices were replaced for a single device. CTRL would like to remove the old ones in 2-3 weeks and kindly ask groups to inform if they are still in use. CTRL will send an e-mail on this subject.
DA:
- Nothing special to report.
EEE:
- Nothing special to report.
VAC:
- Still working in XTD10 and XTD6.
XPD:
- Tunnel works ongoing in XTD6 and XTD9, e.g. Shimadzu cameras / Imagers.
- EEE will need to have access at the end of the Imager intervention of XTD6.
DET:
- SPB Agipd: issues with new data acquisition system. It has been under work.
- This week DET plans to test the new Control fix medium gain to be used in user experiments.
ITDM:
- Nothing special to report.
XRO:
- Not present.
LAS:
- After SASE2 AMPHOS update: there are issues with the interlock
UNSYS:
- Unfortunately neither Desy or EuXFEL could grant access to the external company for the XTD4 tunnel cleaning. UNSYS is trying to organize themselves. PKG shall not be switched on before the clean is done.
SPB:
- Tests with DAQ of the AGIPD: new version has issues with data assignment of aggregated version. Currently AGIPD is back in the old version.
- Work of EEE with some crates of rack room.
FXE:
- Nothing special to report.
MID:
- all fine
HED:
- Nothing special to report.
SCS:
- Nothing special to report.
SQS:
- nothing to say |
193
|
25 Jan 2021, 09:28 |
Arvid Gebhardt | General | Information | Notes XO Integration Meeting 25.01.2021 |
General Announcement:
- Test of automatic switch of power bridge is shifted to Feb.2: this affects all devices connected to orange or green power sockets (no power for few seconds/minute). General e-mail will be sent. Instruments will need to care for equipment which is connected to these sockets. This also affects the E0 level as well as office space in XHQ. Pease plug devices out or re-plug in other sockets.
- The Covid-19 regulations continue valid. Only critical work in the XHEXP1 or tunnel activities shall take place.
- Work on the Soft Mono in XTD10 (SA3) takes place this week. XRO and ME asks everybody to do not move any motors in this device during the whole week.
CTRL:
- New Script to fix label issues in Karabo is ready and will be run today. An e-mail will be sent.
- ITDM and CTRL managed to get updated the “Read the docs”. It runs properly.
DA:
- Not present due to Satellite Workshop.
EEE:
- nothing to report
VAC:
- continuing with tunnel works
XPD:
- Ongoning with few tasks in the tunnel
DET:
- Not present
ITDM:
- nothing to report. Offline GPFS under work today: no Maxwell access during this time.
XRO:
- Not present. Please see general announcements on the Soft Mono.
LAS:
- Error with remote operation on mirrors for SA3/SQS PP-laser is found. A discussion after the meeting will take place between LAS and XO.
UNSYS:
- Nothing to report
SPB:
- Nothing to report
FXE:
- Nothing to add
MID:
- all fine
HED:
- Nothing to report
SCS:
- Nothing to report
SQS:
- Nothing to report |
192
|
20 Jan 2021, 10:32 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 20.01.2021 |
General Announcement:
- A. Galler encourages attendants to pose questions on the authorities decision of lockdown prolongation:
Zunaira A. asks on travel restrictions between different cities: The commuting continues to be allowed, but not business travels;
Adriano V. asks on business/meetings that were postponed (MID/AGIPD intervention) to February in order to plan work that will happen during the summer shutdown: Andreas
G. says that if meeting can't be decided by Zoom, please send an e-mail to the task force with this enquire;
P. Gessler asks if EuXFEL considers to prepare documents (passport) again as in the first lockdown: A. Galler answers that this is in discussion but currently it will not
to be implemented once no curfew is ongoing.
CTRL:
- Working with ITDM to get the Docs system running again.
- Working with EEE to have systems running by Friday.
DA:
- Nothing to report.
EEE:
- EEE reminds the update of SA1 motion loop (to allow work for Hirex) will take place today.
VAC:
- Not present.
XPD:
- Progressing with tunnel works, e.g. installation of viewports.
- A. Koch asks on the tunnel closure plans for XTD6 and XTD9.
A. Galler says XTD9 will close around February 5th and for XTD6 one has to discuss with MXL-DESY on the possibility to keep it open for one week longer (until 12.02).
DET:
- Nothing to report on detector operation.
ITDM:
- ITDM needs to finalize GPFS work which requires one day maintenance. The proposed date is next Monday 25.01. It means no access to data from Maxwell during the all day.
Instruments shall contact ITDM until tomorrow 21.01 in case of restrictions.
- Tickets on e-mail lists (e.g. not authorized sending e-mails to some lists): ITDM is investigating.
XRO:
- XTD6 will have photon beam for recommissioning during the third week of February.
LAS:
- LAS asks instruments on their plans for when to use lasers (mid-February?). HED and MID confirm plans to have it by middle February. SQS, FXE and SCS will consult
internally and let LAS known.
UNSYS:
- Two quad movers in SA2 are working again.
- Afterburner (winter shutdown tasks): Fire extinguishing system to be build; Cleaning the tunnel has to be made prior switching on the PKG.
SPB:
- Nothing to report.
FXE:
- Upgrade of Jungfrau and related work is postponed to Friday.
MID:
- All fine at MID.
HED:
- Nothing to report.
SCS:
- Nothing to report.
SQS:
- Nothing to report. |
191
|
18 Jan 2021, 09:44 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 18.01.2021 |
General Announcement:
- Clarification on the definition of a critical work will be made this afternoon during a discussion with group leaders and will be communicated to the staff.
It includes also tasks carried out by two different groups.
- On Thursday there is going to be a switch of MPS components in the balcony room.
This affects the timing signal distributed to XFEL, e.g. Lasers will not be able to follow timing.
- Test of automatic switch of power bridge is shifted to Feb.2: this affects all devices connected to orange or green power sockets (no power for few seconds/minute).
General e-mail will be sent. Instruments will need to care for equipment which is connected to these sockets.
This also affects the E0 level as well as office space in XHQ. Pease plug devices out or re-plug in other sockets.
CTRL:
- CTRL enquires ITDM on the issue with DOC (disk space full error). ITDM will take a look into it.
DA:
- Getting prepared for involvements such as the data operation center.
EEE:
- Update of SA1 loop motion to take place by Wednesday. Affected staff is already informed.
- Firma Wille work on cabling is ongoing.
VAC:
- Continuing with works in the tunnels.
XPD:
- Tunnels works in XTD6 and XTD9 are ongoing. No incidents to report.
DET:
- Working on data analysis calibrations and installing the DOC.
ITDM:
- Nothing to report.
XRO:
- Nothing to report.
LAS:
- Regarding the Timing signal interruption mentioned in general announcements: it is not a problem as usually LAS keep the laser systems in the local timing during
shutdown periods.
- Upgrading hardware that should be updated accordingly to the plans for the shutdown.
UNSYS:
- Works in tunnel are proceeding.
- Issues with SA2 cell 26 and cell27 were found and experts are going to the tunnel to solve it.
SPB:
- Working on making experimental plans for the Covid-19 beamtime.
FXE:
- Detectors: software upgrade taking place from today.
MID:
- All fine.
HED:
- Nothing to report.
SCS:
- Nothing to report.
SQS:
- Nothing to report. |
190
|
13 Jan 2021, 10:04 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 13.01.2021 |
General Announcement:
- Test of power grid switching affecting green and orange power sockets: this was planned for tomorrow 14.01 but it is not shifted to 02.02.
For a second or so it may trigger power OFF in equipment. Groups have to identify devices that are connected to these sockets, for example at the instrument hutches.
Devices shall be made safe. On the instruments rack room, equipment have two power supplies and therefore they shall be transparent to this intervention.
CTRL:
- Nothing to report.
DA:
- Nothing to report.
EEE:
- Today EEE connects the new PLC for the AIBS project in SASE1 balcony room. One needs to restart momentarily EPS, SPB and FXE loops in SASE1 Tunnel after lunch.
An e-mail was sent yesterday and clarified with instruments.
VAC:
- Tunnels are closed today for the interlock tests. XO thanks HED and FXE for making their hutches available.
XPD:
- Tomorrow XPD restarts with tunnel works, e.g., alignment of PES/XTD10 together with MEA.
DET:
- Nothing to report.
ITDM:
- Nothing to report.
XRO:
- Not present.
LAS:
- Proceeding with small steps but lasers are OFF.
- LAS waits for feedback from SRP and MB on the safety issue. Thomas Tschentscher will bring the safety issue to be discussed offline with MB, LAS and SRP.
Zunaira A. questions if there were problems to re-start the Seeder Lock-in. Tomasz Z. says it is currently locked but after much additional work (no guarantee it can be
locked again if Seeder is once more OFF).
UNSYS:
- Working in the completion of SA3 undulator system.
SPB:
- Drilling ongoing: please keep in mind access to hutch may be affected.
FXE:
- Nothing to add.
MID:
- Wille Firma is working on cabling installation from today afternoon.
HED:
- Expecting Wille will be working from today but shall not interfere with Interlock tests. Zunaira A. says that interlock activities take around 20 minutes during this
afternoon.
SCS:
- An external company is currently working onsite.
SQS:
- Nothing to report. |