General Announcement:
- XO reminds staff to check the safety trainings and the DACHS access rights/permissions for the tunnels when planning tunnel accesses during the maintenance period.
- A. Galler asks all instruments who work with X-ray beam that in case it is found any damaged component, please take a snapshot and post in the operation e-log.
This allows to get known prior/during the maintenance period.
- Last UOM prior maintenance period takes place next Friday.
CTRL:
- For the maintenance period: CTRL will send around the Karabo schedule for updates such as MC2 motors. CTRL will get also in touch with affected people.
- Macro update announcement on Monday will not take place anymore.
DA:
- Nothing to report.
EEE:
- EEE is gathering and scheduling all shutdown tasks and will start next week with tunnel works.
- SASE1 VAC, EPS and MOV, and SASE2 MOV2 loops will be updated next week.
- EEE will also assist, if needed, on the testing of the Mc2 interface migration that Steffen H. / CTRL has informed.
VAC:
- Nothing to report.
XPD:
- Nothing to report.
DET:
- This is the last week of DOC operation. The DOC will re-start on cw28.
ITDM:
- Nothing to report.
XRO:
- Nothing to report.
LAS:
- Man Jiang reports all 3 PP-Lasers are running.
- SCS can't open the shutter (interlock issue) but this is not related to LAS.
UNSYS:
- Nothing to report.
SPB:
- DOC has contacted SPB saying Maxwell calibrations failed. This will be checked.
FXE:
- Nothing to add.
MID:
- All fine at MID.
HED:
- Issue with camera at 10:30PM. It Needed to be power cycled. Steffen H. says that the camera worked this morning. Maybe case is already solved. One will keep an eye if
it happens again.
SCS:
- Issue with Interlock mentioned by LAS. Pouneh S. is working on it.
SQS:
- User operation this week including optical laser.
- Thomas B. says SQS struggles with temporal overlap but spatial overlap is fine. They have first to find clear signal to investigate more on the temporal overlap. |