Technical integration and coordination SASE1 Status and SASE3 Readiness
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther, Page 21 of 33  Not logged in ELOG logo
ID Date Author Location Severity Subjectdown
  434   12 Jul 2023, 10:18 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 12.07.2023
General Announcement:
- There were two power glitches last night observed at Desy which switched OFF some cooling water pumps. Please check your systems and let XO know if you were also affected.
- SEPS Interlock tests driven by RPOs with help from Maurizio V. and CTRL colleagues are now scheduled to take place on Monday 17.07 instead of tomorrow. 
This is because the required bunch patterns may not be provided by machine in due time this week. A tentative schedule for each instrument/SASE will be made in the coming day(s).
- Martin Doering mentions an e-mail was sent out to groups asking for the feedback on tasks that were postponed or cancelled. Please inform xo-planning if you have tasks in these situations.

- Steffen H. says starting today responsibility for the Data Acquisition services (Karabo devices and data group configuration) has been transferred from ITDM to CTRL. 
So CTRL will be the support contact together with DOC. A small task force develops the DAQ at CTRL. Please contact CTRL and Steffen H. in case of questions.

CTRL:
- Deploy Karabo beckoff loops due to some bugs at PLC side which affects communication at Karabo. Patch for Karabo was prepared and will be deployed today at 13:00 in SA1-2-3 the moving loops; downtime few 
minutes.
- Hardware intervention done by IT in replacing a mother board at SA3 which runns PLC loops. Takes longer (30 mins) to replace and restart Karabo. 

DA:
- Calibration team will migrate offline calibration to different nodes. No interruption of services. DET is informed.

EEE:
- Bug of PLC and work around by CTRL: bug was there before and now that makes issues (see CTRL). 
- MID: update of master loop as wished from MID.
- Next Monday busy with bring up days.

VAC:
- No impact of power glitch.

XPD:
- ZZ successful at XTD9 yesterday with Bassler cameras..

DET:
- Nothing to report.

ITDM: 
- Message from Luis: update of myMDC takes place.
- Power glitch: around 03:00-03:30 the cooling failed. At 604 around 20 servers switched OFF as cooling water went down (as prevention mechanism to mitigate temperature raises). Tomasz. P. is working to 
bring servers up.
- Tobias C. also confirms TS sees the 8C water was affected (which is used for the 20C water). 

XRO:
- Nothing to report.

LAS:
- SA3 laser was shut down yesterday due to Lasermet work. Pouneh S. says additional Lasermet works for today were then cancelled and no more work will happen in this maintenance.

UNSYS:
- 4 Quadrupoles are not moving and are under investigation.

SPB:
- Nothing to report.

FXE:
- Nothing to report.

MID:
- All fine.

HED:
- Not present.

SCS:
- Not present.

SQS:
- Nothing to report.

SXP:
- Not present.
  241   12 Jul 2021, 09:29 Andreas GallerGeneralInformationNotes XO Integration Meeting 12.07.2021

General Announcement:

  •  

CTRL:

  • InFlux, still experiencing delay with querying the database (20min, karaba; 5min Grafana)
    • Jan reports that in the XGM trendlines a similar effect is seen

DA:

  • nothing to report

EEE:

  • Friday call from BKR, because of MPS blocking
    • FXE SHUT MPS signal was not reset
    • ZA comments, that the reason is not yet clear --> ZA is contact with Rathjen and MPS experts

VAC:

  •  

ME:

  •  

XPD:

  • For the FXE SHUT it seems MPS and karabo data are differeing
  •  

DET:

  • LPD
    • Hazem is back on Friday --> Supermodules will be tested then in the Lab
  • AGIPD
    • special dark procedur currently not working well

ITDM:

  • nothing to report

XRO:

  • This week, component check in all SASE tunnels
  •  

LAS:

  • nothing to report

UNSYS: 

  • Friday
    • SA1 cell 10, Suren exchanged the coupler

SPB/SFX:

  • nothing to report

FXE:

  • nothing to report
    • PLC issues loop4 and loop7 solved

MID:

  • nothing to report

HED:

  • nothing to report

SCS:

  • nothing to report

SQS:

  • nothing to report

AOB:

  • Zunaira --> beam shutter keys

  521   12 Jun 2024, 10:01 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 12.06.2024
General Announcement:
- This is the last operation week with beam delivery for users for this Run.

CTRL:
- Nothing to report.

DA:
- Nothing to report.

EEE:
- Nothing to report.

VAC:
- Yesterday afternoon an issue with V0 closing was solved.

XPD:
- A. Galler informs that on SPB/SFX branch the XGM was switched OFF by Theo M. as part of preparation for the summer maintenance that triggered the V0 valve.

DET:
- Nothing to report.

ITDM: 
- Announcement: upgrades of some systems will happen in last week of June after agreement with Desy-IT.
- Dcache system will also be updated in the same days, for about 2 days.
- General announcements will be sent around in due time.

XRO:
- Nothing major to report.

LAS:
- Unexplained issue in SA1 by oscillator shifted against the triggers. Under investigation.

UNSYS:
- Nothing to report.

SPB:
- Issue with AGIPD with intervention on chiller + modules exchanges and will not take beam this Run.

FXE:
- Nothing to report.

MID:
- All fine at MID.

HED:
- Not present due to Fusion workshop.

SCS:
- Not present.

SQS:
- Nothing to report.

SXP:
- Not present.
  425   12 Jun 2023, 10:03 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 12.06.2023
General Announcement:
-	 

CTRL:
- FXE sample motor: CTRL will investigate the status of the issue.

DA:
- Nothing to report.

EEE:
- Nothing to report.

VAC:
- Work with vacuum leak of SA2 Solid Attenuator: solved with XRO and VAC tunnel entry by removing the Arm6 from the device. Vacuum is now good and the overall solution will be prepared in future.

XPD:
- Nothing to report.

DET:
- AGIPD 512K at MID had a module with a start/stop error and it is not related to the damaged module.

ITDM: 
- Remind on closing the commissioning proposals: an e-mail was sent to interested staff. Please note the software migration requires all data collected in the last half year to be copied/cleared.
- Saturday overnight: issue with Maxwell cluster that affected calibration/correction jobs; Jobs were pending even with free partition available. 
It was solved on SAT morning with help from Desy colleagues. Reason is also not yet understood and will be followed up this week. 

XRO:
- Nothing to report apart of the solid attenuator in SA2.

LAS:
- SA1 PP-laser works on AMPHOS is ongoing to optimize beam better and improve energy.

UNSYS:
- Quad mover in SA3/cell16 issue.
- X-axis motor at the second monochromator in SA2 has issue and needs a ZZ access this morning (ongoing).

SPB:
- Nothing to report.

FXE:
- Issue with frequent error started in motor: ticket sent. 

MID:
- Difficult week; thanks to XPD, XRO and VAC for the help.
- Experiments somewhat successful.

HED:
- Preparing the last experiment taking place this week.

SCS:
- Finished experiment this morning.

SQS:
- Nothing to report.

SXP:
- Not present.
  131   12 Jun 2020, 13:48 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 12.06.2020
General Announcement:
- There will be tunnel ventilation additional maintenance on two mornings next week from 6:30 to 8:00AM. An e-mail to Readiness list will be send when dates are known.
- There was again a situation that the interlock door between XTD4 and XTD10 was blocked open. SRP reminds all that please do not leave this door opened. 
Further investigation with Desy side will be done if this was a mistake done by an external company. 
- EuP training: Tobias Haas has extended trainings until end of August. There will be refreshers and first time trainings starting on week 26 as in-person EuP training.

CTRL:
- CTRL is done with 2.9.0 deployment - now DAQ and calibrations checks are ongoing.
- No major issues during deployment: still few devices need to be updated again; CTRL is working on it.

DA:
- DA has released new version of extract data. Documentation will be send around and people are invited to give feedback.

EEE:
- Activities are running fine.
- PLCs side: this week there is migration for mc2 in SA2 - EEE ask people to crosscheck systems.
- Two cables in MID will be finished late next week (regarding personal interlock).
- EEE is conducting migration microTCA systems/crates: SA1 and balcony rooms.
- Timing for the Lasers updates has to be arranged with LAS. CTRL and EEE recommend making it during the shutdown. It needs green flag from LAS and Instruments. 
- Upgrade of firmware of timing system: this will not be done to avoid stop timing system for lasers. Tunnels are done.
- Puppetization work is ongoing. SA2 and SA1 tunnel remains to be completed at beginning of next week. 

VAC:
- No issues to report.

XPD:
- Follow up of SA2 mc2 migration: we recheck motors in tunnel; update scenes with CTRL.
- XPD is almost finished with large interventions.

DET:
- Test of Agipd with new Karabo is successful. The DSSC is also working.

ITDM: 
- DAQ updates: to be started today or next week.
- Hardware updates in SASEs that ITDM will be performing.

XRO:
- Nothing to report: XRO is finished with big installations. Only small tasks to be done next week.

LAS:
- The broker update caused the timing in SA3 to be lost. It took several hours to bring up the system. 
- Updates in SA2 (affecting timing) will be performed next Tuesday.
- SA1 and SA3 have to be scheduled and it depends also on instrument's plans. 

SPB:
- It has planned tests on the calibration of pipeline / DAQs for next week.

FXE:
- It has upgraded to new Karabo and some controls will be updated today.

MID:
- Work ongoing as planned.
- CTRL test the influx data logger today and Monday and this causes loosing of information for few minutes. 

HED:
- Water incident in SA2: Water spills caused a flooded experimental hutch. TS have repaired and will check with the external company if systems have been exchanged. 
Such events must be avoided in future. 
- In many hutches there are water sensors in the floor which are not connected: TS and SRP shall take a look.
- Summer shutdown: there was scheduled task (presumably from Desy groups) on June 8-10th that nobody showed up. By the other side, suddenly someone was working inside the 
laser room. 
Ulf would like to see Desy people working with better planning and coordination. As positive, EEE tasks on microTCA are an example of good practice in communication and 
coordination. 

SCS:
- Not present.

SQS:
- No issue to report.
  611   12 May 2025, 09:36 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 12.05.2025
General Announcement:
- Successful delivery last days with exceptional machine performance. From tomorrow we have a FD week followed by a 12GeV week.

CTRL:
- Nothing to report.

DA:
- Quiet at DA.

EEE:
- Nothing to report.

VAC:
- Nothing to report.

XPD:
- Nothing to report.

DET:
- Nothing to report.

ITDM: 
- Nothing to report.

XRO:
- Nothing to report.

LAS:
- Wednesday CTRL helped with SPB/FXE but fixed.

UNSYS:
- Nothing to report.

SPB:
- Challenges with PP-laser not being able to use WED and THU (switch between masters FXE/SPB); also SAT alignment issues all fixed with help from OCD. LAS and SPB will further discuss.

FXE:
- Nothing to report.

MID:
- Nothing to report.

HED:
- Not present.

SCS:
- Nothing to report.

SQS:
- Nothing to report.

SXP:
- Not present.
  224   12 May 2021, 09:21 Arvid GebhardtGeneralInformationNotes XO Integration Meeting 12.05.2021

General Announcement:

- User Operations Meeting takes place on next Friday 09:00.

CTRL:

- CTRL would like to excuse itself to people receiving an automatic SMS tonight for notification. This was a test message and now it’s turned OFF (Good side: test for lasers went well).

- ADQ digitizers: two fixes are driven and based for SQS commissioning. CTRL encourage instruments to get in touch with contacts for making the update for the last version.

DA:

- Follow up from Monday / calibration update (on behalf of cal team): it worked as planned. AGIPD seems to run faster now.

- For SQS Remi detectors/digitizers can also be used.

EEE:

- nothing to report

VAC:

- nothing to report

XPD:

- are preparing for FD studies next week

DET:

- Follow-up on LPD online calibration pipeline pointed last Monday’s meeting: work is on progress and is expected to be ready for next week.

- DAQ processing for AGIPD: a minor bug in validation is reported and under investigation. But it is currently working.

- Issue reported for SPB for data aggregators: follow up with CTRL.

ITDM:

- nothing to report

XRO:

- nothing to report

LAS:

- nothing to report

UNSYS:

- nothing to report

SPB:

- not present

FXE:

- Thank to DET and DA for pipeline calibration. Initially it looks promising.

- Last week: digitizer went to wrong configuration. To be fixed with new updated.

- FXE will use the beam during the nights. D. Khakhulin will inform PRC and XO via e-mail.

MID:

- all fine

HED:

- not present

SCS:

- nothing to report

SQS:

- nothing to add

  214   12 Apr 2021, 14:40 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 12.04.2021
General Announcement:
-	 

CTRL:
- Broker pile-up on Friday: Alessandro S. says that was triggered by network configurations; it took time to recover situation. 
Started SA3 topics for deployment and for few tickets related to that, please get in touch with DRC or try re-starting devices.
- Deployments: 1. Fix for data loggers and timing servers. We propose to do next Monday; 2. Karabo 2.10.4 was released with few bug fixes. CTRL is in touch with 
instruments.

DA:
- Nothing to report.

EEE:
- Nothing to report.

VAC:
- Found on Saturday a problem with SA3 gas attenuator. It was solved with the DOC.

XPD:
- Power increase tests ongoing this morning.
- A. Koch says two servers were not running this morning and will make contact to DRC.

DET:
- Couple of OCD calls received and fixed.

ITDM: 
- Network failure: systems are very sensitive to network failures (switch failure). Relates to replacement of devices.

XRO:
- Some SA3 cameras lost configurations (maybe related to the SA3 event during the weekend): fixed by M. Vannoni. 
- SCS/SQS teams: structure for the M6 chamber has to be fixed (motors): XRO will communicate with the instruments, to keep the motors in proper conditions.

LAS:
- PP-lasers are running. Small minor issues: 
1. SA3 problem with displaying number of pulses. Solved by CTRL by installing latest Karabo server;
2. SA2 still shows small problem with regulations/settings, spectrum started drifting. Can be fixed by OCD but ticket was created.

UNSYS:
- Nothing to report.

SPB:
- Preparing for user experiment this week.

FXE:
- Nothing to report:
- Last Friday PP-laser could not config laser pattern. Tomasz J. says the OCD laser is aware and asks to please also inform DOC/DRC in such cases as LAS can't help in 
this time. 
Monica T. confirms that one has to call the DOC and invite instruments that do not get beam to also join the Monday 13:00 DOC meetings.

MID:
- Suffered with SA2 PLC downtime - mono lost positions.
- Scan energies on the undulators will be needed on next week.
- Last week operation was smooth.

HED:
- Starting operation this week.

SCS:
- Nothing to report.

SQS:
- Spectrum of detectors - two spectras were split. This was reported to BKR and DOC.
  595   12 Mar 2025, 09:36 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 12.03.2025
General Announcement:
- A. Galler informs the beam delivery start is delayed currently up to 15:00 due to difficulties in setting up the machine after the FD week.
- Couple of meetings regarding the LIMP are scheduled; plans have been distributed and will be shared during the meetings. 
Please attend the meetings and if you want an invitation, contact Martin Doering. Also a DATA meeting on LIMP is happening today and please contact Patrick G., Steffen H. or Martin Doering for invitation.

CTRL:
- Nothing to report.

DA:
- Not present.

EEE:
- Nothing to report.

VAC:
- Nothing to report.

XPD:
- Nothing to report; all fine.

DET:
- Nothing major to report.

ITDM: 
- Nothing to report.

XRO:
- Not present.

LAS:
- Nothing to report.

UNSYS:
- Nothing to report; everything fine.

SPB:
- Nothing to report.

FXE:
- Nothing to report.

MID:
- Nothing to report.

HED:
- Nothing to report.

SCS:
- Preparing for next weeks.

SQS:
- Nothing to report.

SXP:
- Nothing to report.
  587   12 Feb 2025, 09:53 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 12.02.2025
General Announcement:
- Delivery to instruments restarted this morning with good FEL performance (above the average). HXRSS in SA2 to be done during the day.
- As PRC, Maurizio Vannoni has nothing to report. So far so good.

CTRL:
- Instrument Control Integration team has a retreat today and tomorrow. So far only a "nothing to report" arrived to XO.

DA:
- Nothing to report.

EEE:
- Nothing to report.

VAC:
- Nothing to report; all fine.

XPD:
- Nothing to report.

DET:
- Nothing major;
- Jungfrau MID issue: looks to be permanently solved; further analysis on the reason behind is being done.

ITDM: 
- Nothing to report.

XRO:
- Nothing to report.

LAS:
- It had to replace a uTCA in SA3 which was causing timing drifts; after replacement the restarted is ongoing and EEE helps. Hope to have delivery today by lunch time.

UNSYS:
- Nothing to report.

SPB:
- Nothing to report.

FXE:
- XTD2 CRL motion issue is solved: Nerea J. informs Leandro Z. did tests with SPB and motor is behaving properly.
- Issue with LPD appeared this morning (no further info on the issue details) but experts are contacted.

MID:
- Nothing to report.

HED:
- Nothing to report.

SCS:
- Thanks for EEE for recent help.
- Lasermet work is done accordingly to LAS.

SQS:
- Not present.

SXP:
- Nothing to report.
  489   12 Feb 2024, 09:40 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 12.02.2024
General Announcement:
- As PRC, Andreas G. informs the week went smooth so far.

CTRL:
- Announcement: CTRL will shut down one control host in SA1 and SA3 to let maintenance by ITDM. It affects one server at each part. To be done tomorrow at 10:00AM by half an hour. 
The GUIs that are open and connected will not work during this time.
- DAQ upgrade: not good news - few issues with DAQ at SPB/SFX. Under detailed investigation and working from that lessons. SPB rolled back to old DAQ and worked as it had been before.

DA:
- Nothing to report. Quiet week from DA.

EEE:
- Nothing to report.

VAC:
- Nothing to report.

XPD:
- Nothing to report.

DET:
- Nothing to report.

ITDM: 
- Nothing to report.

XRO:
- Nothing to report.

LAS:
- Not present.

UNSYS:
- SA3 / cell12 status: waiting for the power cycling but seems not to be necessary. All fine.

SPB:
- Issues with DAQ (as reported by CTRL).
- Happy users so far; the change on Saturday went smooth.

FXE:
- Nothing to report.

MID:
- Nothing to report.

HED:
- It went overall well for the experiment. HXRSS was done well with a bit larger background.
- N. Kujala asks for the HIREX must stay inserted on Tuesday allowing further studies.

SCS:
- Nothing to report.

SQS:
- Nothing to report.

SXP:
- Nothing to report.
  291   12 Jan 2022, 10:06 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 12.01.2022
General Announcement:
- SEPS interlock tests are scheduled for January 21st: starting early morning from 08:00 to 16:00 across all the SASEs; 
In parallel D-3 tests the interlocks in all hutches including SXP. An e-mail to instruments was sent and a reply has to be directed to Zunaira A.
- Disabling SEPS interlock yesterday night was not necessary. Further discussion with A. Galler will follow.

CTRL:
- No planned updates.

DA:
- No updates to report.

EEE:
- Yesterday the SA1 vacuum update took place.
- MPS contacted Nerea J. on the SEPS interlocks issue: Nerea J. to be included in further discussions.

VAC:
- Nothing to report.

XPD:
- Preparing for tunnel closure: finishing Hard X-ray PES tests; works in XTD9 are completed.
- Works in XTD6 finishing EPS switches and installing upgrade M-ports in MCP (crate coming on Thursday and update interlock connection).

DET:
- Nothing to report.

ITDM: 
- Remind on the Wednesday maintenance on the dCache and GPFS; Access to XFEL related data from Maxwell compute cluster is not guaranteed during the intervention. Please contact ITDM in case of conflicting 
with it.

XRO:
- Not present.

LAS:
- Failed to upgrade the SASE1 front ends during Winter Maintenance (company did not come due to Corona regulations). 
- 8D report for the Seeder shutdown issue at the start of the maintenance period: A. Galler informs that by the end of this week it shall be ready and distributed.
- Power supply connection: Max L. asks for XO support to follow up with TS.

UNSYS:
- Apple-X undulators are aligned and currently the intersection is being aligned together with air coils. Vacuum shall also be connected permitting to close tunnel tomorrow.

SPB:
- Nothing to report.

FXE:
- Nothing to report.

MID:
- Thanks to SPB group for helping with providing a flange.

HED:
- Apart from the SEPS all is fine.

SCS:
- Not present.

SQS:
- All fine.
  573   11 Dec 2024, 09:43 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 11.12.2024
General Announcement:
- A. Galler comments the maintenance period started; already yesterday tunnels were opened due to the stop in operation from caused by the power glitch at Desy.

CTRL:
- Preparing for the Karabo deployment, to be done next week accordingly to the schedule.
- Dennis Goeries presents on the authentication factor: 
1. tunnel SA1 topic was deployed months ago - the Open Access form is used to generate a 6-digit number that can copied and pasted in the login window. 
2. Thus authentication is then done; One can escalate the access user to have high level access (it is highlighted in Green color at the Karabo); 
3. After 1 hour the session will be closed; When choosing the “remember me” option one needs to make it only once. 

DA:
- Nothing to report.

EEE:
- Schedule for tunnels updates was shared and will be started today. In case of question please get in touch with EEE or Nerea Jardon.

VAC:
- Started with maintenance activities in tunnels.

XPD:
- Working on the maintenance tasks: PES already vented; SA1 XFELO was also vented; Progressing well.

DET:
- Nothing to report.

ITDM: 
- Ongoing with maintenance tasks; some were postponed due to unavailability of software.
- Announcement will be sent for consolidating Maxwell display mode into the cluster mode. Second try to happen tomorrow. Session will be disconnected and users shall connect again later.

XRO:
- Working in tunnels since yesterday.

LAS:
- Start with activities; so far so good.

UNSYS:
- Fixed problem with PS in cell20 SA3.

SPB:
- All fine at SPB.

FXE:
- Nothing to report.

MID:
- Nothing to report.

HED:
- Nothing to mention.

SCS:
- Start maintenance activities.

SQS:
- Not present.

SXP:
- Not present.
  476   11 Dec 2023, 09:51 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 11.12.2023
General Announcement:
-	 

CTRL:
- Last week updates on Karabo were done. Please check systems for functionality.
- Another update of data loggers will be done in coming days.

DA:
- Following the Karabo updates DA is checking their devices.

EEE:
- Suffering from illnesses in the group: colleagues that are not sick try to get all work done but some delay in some activities is expected in some areas;
- Also Wille company is suffering with sickness and they try to find substituted colleagues.
- Vacuum updates were fixed; plan to update of SA2 VAC was postponed from Friday to today.

VAC:
- Nothing to report.

XPD:
- Request to EEE when updates for XGM are to start, please inform Florian Dietrich and Jan Gruenert for that they prepare beforehand. After update is done one needs to restart vacuum and XGM.

DET:
- AGIPD at SPB/SFX intervention: replaced all modules; three attempts were needed and the situation is that detector is fully operational and all modules are working. 
Also tests after Karabo deployment worked nicely. Next is a test with DAQ and everything looks very promising.
- At MID AGIPD: Bias issue is also fixed; tested at real conditions went successful. Cause was a wire.

ITDM: 
- Most of the activities are done.
- Problem with exchange of switch in SA2 for DAQ collection: power supply had a problem but not only it, so new chassis will be delivered and needs to be replaced. DAQ connections for SA2 is not working.

XRO:
- Planned works are continuing and everything is going fine.

LAS:
- Nothing to report.

UNSYS:
- More two last Apple-X are being installed; from today Beckhoff technicians will connect the cabling.
- Issues with encoders are solved (radiation damage). Replacement was done and calibration was successful.

SPB:
- Nothing to report.

FXE:
- Nothing to report.

MID:
- Nothing to report.

HED:
- Not present.

SCS:
- Nothing to report.

SQS:
- Nothing to report.

SXP:
- Not present.
  564   11 Nov 2024, 09:46 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 11.11.2024
General Announcement:
- Last day of the FD taking place and switching back to 16.3GeV today.

CTRL:
- Nothing to report.

DA:
- Nothing to report.

EEE:
- Nothing to report.

VAC:
- Nothing to report.

XPD:
- FD studies went fine during the weekend; Attoseconds went fine; XFELO progressed.
- PES can be used for the remaining delivery weeks for 2CPP but not for polarization.

DET:
- Nothing major to report.

ITDM: 
- Nothing special to report.

XRO:
- XFELO: Alignment problems as expected; first time using 4 undulators from inside the cavity; pointing/trajectory inside had changed and to be re-done on Sunday.
- In general, all studies brought some results even if not majors.

LAS:
- Not present.

UNSYS:
- Nothing to report.
- Polarized attoseconds need more time in FD weeks.

SPB:
- Nothing to report.

FXE:
- Nothing to report.

MID:
- Nothing to report.

HED:
- Setting up for two programs this week; all fine so far.

SCS:
- Nothing to report.

SQS:
- Take beam this week for IHR; finishing preparation.

SXP:
- Not present.
  177   11 Nov 2020, 10:49 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 11.11.2020
General Announcement:
- XO is in contact with some groups regarding the winter shutdown, in order to get additional information or solve potential conflicts. 
If there are any question, please contact us in this meeting or via e-mail.
- Steffen adds on the idea of using FXE for initial deployment of updated Karabo version. It will take place after 23/Nov.
- Jan asks how XO needs to be informed for tasks that groups deal with each other. A. Galler says XPD is on the list for setting a date to discuss this. 
Groups are encouraged to communicate with other support groups beforehand.

CTRL:
- Misbehaving timing server at MID yesterday was initially solved by EEE. EEE replaced the hardware of the timing system itself but problem continued. 
System seems now to be healthy but from time to time there are small timing interruptions. Investigation is ongoing and will be discussed in the digitizer meeting of Data 
department.
- One CTRL ticket on Doocs device at SCS: it was a problem with custom installation. CTRL asks to be informed in case groups have custom installations. This may pose a 
risk when deploying new updates.

DA:
- AGIPD train-ID issue: a small workaround until shutdown is in place. One has to set the individual channel and seems to be now working. Next intervention to take place 
during Winter maintenance time.

EEE:
- Nothing else to report aside of the MID timing system.

VAC:
- Nothing to report.

XPD:
- SA3 XGM was switched to Ne as requested by instruments.

DET:
- Preparation for activities on AGIPD at SPB/SFX during the winter time is ongoing.

ITDM: 
- Pre-announcement: at the start of the maintenance, ITDM has activity on the computer cluster. A separate announcement will be sent.

XRO:
- Nothing to report.

LAS:
- Nothing to report.

UNSYS:
- Nothing to report.

SPB:
- No issues to report.
- Intervention date of AGIPD: SPB requires due to highest priority work that between 16/11-18/12 no interruptions of electrical power or the need of EQP may happen. 

FXE:
- Crosstalk SA1/SA3 was not seen yesterday as SQS used only 1 bunch.

MID:
- Nothing to add besides what CTRL and EEE have mentioned.

HED:
- Next week HED does not use X-ray beam: commissioning of the high power laser and test of pulse on demand are planned. A. Galler says it pulse on demand was fixed by 
CTRLs and can be used. 
- Question on use of ADCs: Bruno says some trains will not be recorder or be repeated. This may be related to the timing issue like in MID. 
But data can be acquired. It is under investigation accordingly to Bruno, with CTRL, DA, ITDM.

SCS:
- Not present.

SQS:
- Nothing to report.
  459   11 Oct 2023, 10:15 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 11.10.2023
General Announcement:
- Reminder that next week, on 20.10, is the deadline to submit the Winter maintenance task lists to XO. In case of help, please contact Martin Doering at xo-planning@xfel.eu.

CTRL:
- Nothing to report.

DA:
- Nothing to report; all quiet at the DOC also.

EEE:
- Nothing to report.

VAC:
- Nothing to report.

XPD:
- Nothing to report.

DET:
- A Silicon oil leak at DET cleaning room happened: leak comes from Jungfrau cooling loop (built by external company); status is area was cleaned and leak point is being searched;
- AGIPD setup at SPB got a failure of Julabo chiller; it does not work properly and it does not cool as expected. Detector is interlocked and there was no problems for itself; to be further investigated.

ITDM: 
- Gitlab was down for about 30 mins and now is available again.

XRO:
- Nothing to report.

LAS:
- Status of SA3 PP-laser: still investigating and in contact with AMPHOS. Still to be seen.
- Smaract in SA2 is fixed.

UNSYS:
- All good.

SPB:
- Issue with AGIPD chiller. Installed yesterday mid-day and was cooling slowly but not reaching base temperature.

FXE:
- Handover laser to SQS.

MID:
- Nothing to report.

HED:
- Not present.

SCS:
- In contact with EEE (Bernard) regarding the commissioning of our additional local box for the THz experiment.

SQS:
- Not present.

SXP:
- Nothing to report; backlash of M6 seems to be fine.
  267   11 Oct 2021, 09:27 Andreas GallerGeneralInformationNotes XO Integration Meeting 11.10.2021

General Announcement:

  •  

CTRL:

  • nothing report

DA:

  • nothing to report

EEE:

  • several motors in SPB/SFX had trouble, all originating from the same crate

VAC:

  • VAC problems at HED last Wed
    • monochromator section in the tunnel, two unidentified vacuum bursts

XPD:

  • nothing to be reported

DET:

  • nothing to report

ITDM:

  • nothing to report

XRO:

  • FXE (PZ) reported a large jump in the bender setting, sebsequently Ry and pitch drifted for days and stabilized later
    • M1 M2 alignment changed as well
    • currently stable and being investigated

LAS:

  • nothing to report

UNSYS: 

  • nothing to report

SPB/SFX:

  • unstable pulse energy jittering ~ 35% over days.

FXE:

  • Experiment went well, apart from minor issue with calibration pipeline with JF

MID:

  • all fine

HED:

  • nothing to report

SCS:

  • not present

SQS:

  • not present

AOB:

  •  

  547   11 Sep 2024, 09:50 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 11.09.2024
General Announcement:
-  Todays the machine setup is ongoing and from tomorrow it starts the beam delivery, as planned.

CTRL:
- Nothing to report.

DA:
- Nothing to report.

EEE:
- P. Gessler informs there is no DOC today as there is no beam delivery; DRC is normally reachable.

VAC:
- Yesterday ZZ to exchange preventively a pump controller was carried out successfully.

XPD:
- Nothing to report.

DET:
- Nothing to report.

ITDM: 
- Nothing to report.

XRO:
- Nothing to report.
- M. Vannoni says the SA1 drift (by M1) is being monitored and shall not be disruptive as feedback corrects it. XRO will keep an eye and assist in case of need.

LAS:
- SA3-PPL is being delivered.
- SA1-PPL being changed to THz experiment; to be ready today.
- SA2-PPL being changed to 1.1MHz, but no amplification was found; Rolled back to 188kHz to delivery to MID.
- Delay of trigger reported days ago: Desy looked into it and did not find anything specifically; Patrick G. will discuss with LAS.

UNSYS:
- Masking of undulator errors at BKR was addressed with MXL. 

SPB:
- Nothing to report.
- New Radiation constraints were issued and operation has to be with photon energies higher than 8keV.

FXE:
- This week’s nights will have operation higher than 8keV.

MID:
- Nothing to report. No limitations for photon energies on SA2 side.

HED:
- Nothing to report.

SCS:
- Detector calibration last Monday had issue with girder movement; EEE is aware and has to be working next beamtime.

SQS:
- Nothing to report.

SXP:
- Not present.
  450   11 Sep 2023, 09:47 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 11.09.2023
General Announcement:
- A Cryo issue taking place in the night Fri-SAT lead to beam not being delivered since them. The failure was at a magnetic bearing with a misreading of motor position. 
In parallel motors 3 and 4 were exchanged as preventive measure during this downtime. Cryo OK came back on Sunday afternoon and efforts are focusing in bringing machine up for cw37.

CTRL:
- Pulse on demand for FXE (main scene) will be updated today.

DA:
- Nothing to report.

EEE:
- Nothing to report.

VAC:
- Nothing to report.

XPD:
- Not present.

DET:
- Nothing to report.

ITDM: 
- Not present.

XRO:
- Change middle layer for the bunch patter at SA1 for fixing today.

LAS:
- Not present.

UNSYS:
- Nothing to report.

SPB:
- Nothing to report.

FXE:
- Nothing to report.

MID:
- Nothing to report.

HED:
- Between Synchronization issue and cryo failure only a total of 6-7hs of data were collected.

SCS:
- Beamtime affected by cryo failure.

SQS:
- Nothing to report.

SXP:
- Nothing to report.