Subject: Notes XO Integration Meeting 11.11.2024 
General Announcement:
- Last day of the FD taking place and switching back to 16.3GeV today.

CTRL:
- Nothing to report.

DA:
- Nothing to report.

EEE:
- Nothing to report.

VAC:
- Nothing to report.

XPD:
- FD studies went fine during the weekend; Attoseconds went fine; XFELO progressed.
- PES can be used for the remaining delivery weeks for 2CPP but not for polarization.

DET:
- Nothing major to report.

ITDM: 
- Nothing special to report.

XRO:
- XFELO: Alignment problems as expected; first time using 4 undulators from inside the cavity; pointing/trajectory inside had changed and to be re-done on Sunday.
- In general, all studies brought some results even if not majors.

LAS:
- Not present.

UNSYS:
- Nothing to report.
- Polarized attoseconds need more time in FD weeks.

SPB:
- Nothing to report.

FXE:
- Nothing to report.

MID:
- Nothing to report.

HED:
- Setting up for two programs this week; all fine so far.

SCS:
- Nothing to report.

SQS:
- Take beam this week for IHR; finishing preparation.

SXP:
- Not present.