General Announcement:
- Todays the machine setup is ongoing and from tomorrow it starts the beam delivery, as planned.
CTRL:
- Nothing to report.
DA:
- Nothing to report.
EEE:
- P. Gessler informs there is no DOC today as there is no beam delivery; DRC is normally reachable.
VAC:
- Yesterday ZZ to exchange preventively a pump controller was carried out successfully.
XPD:
- Nothing to report.
DET:
- Nothing to report.
ITDM:
- Nothing to report.
XRO:
- Nothing to report.
- M. Vannoni says the SA1 drift (by M1) is being monitored and shall not be disruptive as feedback corrects it. XRO will keep an eye and assist in case of need.
LAS:
- SA3-PPL is being delivered.
- SA1-PPL being changed to THz experiment; to be ready today.
- SA2-PPL being changed to 1.1MHz, but no amplification was found; Rolled back to 188kHz to delivery to MID.
- Delay of trigger reported days ago: Desy looked into it and did not find anything specifically; Patrick G. will discuss with LAS.
UNSYS:
- Masking of undulator errors at BKR was addressed with MXL.
SPB:
- Nothing to report.
- New Radiation constraints were issued and operation has to be with photon energies higher than 8keV.
FXE:
- This week’s nights will have operation higher than 8keV.
MID:
- Nothing to report. No limitations for photon energies on SA2 side.
HED:
- Nothing to report.
SCS:
- Detector calibration last Monday had issue with girder movement; EEE is aware and has to be working next beamtime.
SQS:
- Nothing to report.
SXP:
- Not present. |