Technical integration and coordination
SASE1 Status and SASE3 Readiness
|
Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther |
Not logged in |
 |
|
Message ID: 573
Entry time: 11 Dec 2024, 09:43
|
Author: |
Frederik Wolff-Fabris |
Location: |
General |
Severity: |
Information |
Subject: |
Notes XO Integration Meeting 11.12.2024 |
|
|
General Announcement:
- A. Galler comments the maintenance period started; already yesterday tunnels were opened due to the stop in operation from caused by the power glitch at Desy.
CTRL:
- Preparing for the Karabo deployment, to be done next week accordingly to the schedule.
- Dennis Goeries presents on the authentication factor:
1. tunnel SA1 topic was deployed months ago - the Open Access form is used to generate a 6-digit number that can copied and pasted in the login window.
2. Thus authentication is then done; One can escalate the access user to have high level access (it is highlighted in Green color at the Karabo);
3. After 1 hour the session will be closed; When choosing the “remember me” option one needs to make it only once.
DA:
- Nothing to report.
EEE:
- Schedule for tunnels updates was shared and will be started today. In case of question please get in touch with EEE or Nerea Jardon.
VAC:
- Started with maintenance activities in tunnels.
XPD:
- Working on the maintenance tasks: PES already vented; SA1 XFELO was also vented; Progressing well.
DET:
- Nothing to report.
ITDM:
- Ongoing with maintenance tasks; some were postponed due to unavailability of software.
- Announcement will be sent for consolidating Maxwell display mode into the cluster mode. Second try to happen tomorrow. Session will be disconnected and users shall connect again later.
XRO:
- Working in tunnels since yesterday.
LAS:
- Start with activities; so far so good.
UNSYS:
- Fixed problem with PS in cell20 SA3.
SPB:
- All fine at SPB.
FXE:
- Nothing to report.
MID:
- Nothing to report.
HED:
- Nothing to mention.
SCS:
- Start maintenance activities.
SQS:
- Not present.
SXP:
- Not present. |