Technical integration and coordination
SASE1 Status and SASE3 Readiness
|
Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther |
Not logged in |
|
|
Message ID: 286
Entry time: 13 Dec 2021, 10:51
|
Author: |
Frederik Wolff-Fabris |
Location: |
General |
Severity: |
Information |
Subject: |
Notes XO Integration Meeting 13.12.2021 |
|
|
General Announcement:
- The cooling water various types shall be working/restored and it seems that temperatures are back to normal. In case of finding deviations in temperatures let TS or XO know. Racks and racks rooms can in
principle be closed.
- Tobias H. comments on the open rack doors: in general if racks have to be opened, please keep in mind the corridors in between the labs are fire safety doors and this has to be discussed with SRP or
Michael Prollius prior taking place.
The comment serves as a precaution for the future.
- An e-mail from SRP will be sent concerning disclosing the vaccination status and registration at the entrance gate.
CTRL:
- Upgrade/migration of all tunnel cameras to Aravis was concluded in tunnels.
DA:
- Nothing to report.
EEE:
- All runs smoothly at the moment.
VAC:
- Maintenance activities going accordingly with the plan.
XPD:
- Proceeding with shutdown tasks. Today alignment activities and vacuum activities at XTD2.
DET:
- Nothing to report.
ITDM:
- Nothing to report.
XRO:
- This week resume the work in lab after restoring cooling water.
- XRO reminds the need to resume discussion with the ramp-up activities to divide commissioning days - a plan has to be done due to the high number of updated devices.
A date for recommissioning of these devices shall be fixed. XO will discuss with XRO.
LAS:
- Restarting the lasers and proceeding maintenance.
UNSYS:
- Plan to install Apple-X from today on.
SPB:
- Installing granites in experimental hutch.
- Intervention in optics hutch today: please refrain to access it for staff other than the ones performing task.
FXE:
- Access XTD2 to check CRL; commissioning motors in hutch.
MID:
- All fine at MID.
HED:
- Laser interlock upgrade last week was successful with Klaus Witt.
SCS:
- Activities are going accordingly to the plan.
SQS:
- Nothing to report. |