Technical integration and coordination SASE1 Status and SASE3 Readiness
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 286     Entry time: 13 Dec 2021, 10:51
Author: Frederik Wolff-Fabris 
Location: General 
Severity: Information 
Subject: Notes XO Integration Meeting 13.12.2021 
General Announcement:
- The cooling water various types shall be working/restored and it seems that temperatures are back to normal. In case of finding deviations in temperatures let TS or XO know. Racks and racks rooms can in 
principle be closed.
- Tobias H. comments on the open rack doors: in general if racks have to be opened, please keep in mind the corridors in between the labs are fire safety doors and this has to be discussed with SRP or 
Michael Prollius prior taking place. 
The comment serves as a precaution for the future.
- An e-mail from SRP will be sent concerning disclosing the vaccination status and registration at the entrance gate.

CTRL:
- Upgrade/migration of all tunnel cameras to Aravis was concluded in tunnels.

DA:
- Nothing to report.

EEE:
- All runs smoothly at the moment.

VAC:
- Maintenance activities going accordingly with the plan.

XPD:
- Proceeding with shutdown tasks. Today alignment activities and vacuum activities at XTD2.

DET:
- Nothing to report.

ITDM: 
- Nothing to report.

XRO:
- This week resume the work in lab after restoring cooling water.
- XRO reminds the need to resume discussion with the ramp-up activities to divide commissioning days - a plan has to be done due to the high number of updated devices. 
A date for recommissioning of these devices shall be fixed. XO will discuss with XRO.

LAS:
- Restarting the lasers and proceeding maintenance.

UNSYS:
- Plan to install Apple-X from today on.

SPB:
- Installing granites in experimental hutch.
- Intervention in optics hutch today: please refrain to access it for staff other than the ones performing task.

FXE:
- Access XTD2 to check CRL; commissioning motors in hutch.

MID:
- All fine at MID.

HED:
- Laser interlock upgrade last week was successful with Klaus Witt.

SCS:
- Activities are going accordingly to the plan.

SQS:
- Nothing to report.