Technical integration and coordination SASE1 Status and SASE3 Readiness
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 295     Entry time: 26 Jan 2022, 10:46
Author: Frederik Wolff-Fabris 
Location: General 
Severity: Information 
Subject: Notes XO Integration Meeting 26.01.2021 
General Announcement:
- The cold compressor failed this morning and beam operation is currently stopped. We expect the beam operation for the alignment of beam systems will resume tomorrow morning (Thursday).

CTRL:
- Nothing to report.

DA:
- Nothing to report.

EEE:
- Closing last tasks for the maintenance.

VAC:
- All fine.

XPD:
- Issues with PES were solved by CTRL.
- Jan G. asks when beam would be aligned to M1 and M2 in SA1 and SA2? (see XRO report).

DET:
- Nothing to report.

ITDM: 
- Work ongoing with company regarding Monday's report on offline storage system.
- Jan asks for the DAQ Karabo test with XPD. Janusz S. suggested to contact Partha who is on charge for this.

XRO:
- Ahead of schedule with alignment until this morning: SA1 and SA2 beam established in all experiments. SA1 beam on mirror but it needs to finish Bender calibration (nice beam at the end of the SA1 
tunnel).
- Currently cryo is down and pushes back next days plans: Today planned schedule of tuning 17.2 keV in SA1 as well as Apple-X in SA3 is shifted to tomorrow. 
If beam comes tomorrow morning SA2 is available for alignment. By end of the week one starts with SA3.

LAS:
- SA2 almost ready: it shall be finished by end of the day.
- SA3 Amphos maintenance is finished: maybe ready end of the week or start next week.
- SA1 is making progress: 1.1MHz operation shall be OK but 280kHz can be have some difficulties.

UNSYS:
- Power failure in SA1 central control node prevented communication to undulators during the evening. It was solved after power cycle.

SPB:
- Busy with aligning beamline.

FXE:
- Same as SPB; nothing else to report.

MID:
- All fine.

HED:
- Not present.

SCS:
- All fine.

SQS:
- Nothing to report.