Technical integration and coordination SASE1 Status and SASE3 Readiness
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 285     Entry time: 08 Dec 2021, 11:02
Author: Frederik Wolff-Fabris 
Location: General 
Severity: Information 
Subject: Notes XO Integration Meeting 08.12.2021 
General Announcement:
- The temperatures in the Hall are warming and accordingly to Tobias C. this is related to cooling water as ventilation is also affected.
- A. Galler reminds on an e-mail sent yesterday related to check-in at XFEL today: one has to show vaccination status at the gate. For next week likely one can register the Covid status at the badge reader 
and further communication will be sent.
- On next Saturday 11.Dec tunnels between Osdorf-Born and XHEXP1 will also be closed in the context of the fire extinguisher maintenance. 
It is also reminded that all Schenefeld campus buildings are inaccessible and only SRP, TS and external company are allowed in the site.

CTRL:
- After the control server network update, Karabo is up again in all the topics.

DA:
- Nothing to report also including calibration team.

EEE:
- All maintenance tasks progressing in tunnels and instruments.

VAC:
- Not present due to tunnel works.

XPD:
- Progress yesterday was done by bringing hard Xray PES in XTD2 which was installed in the beamline with help from VAC and MEA groups
- Loop update with EEE. Bernard B. says SA3 motion2 PLC will be updated/finished today.

DET:
- Nothing to report.

ITDM: 
- Commissioning proposals: interested people got an e-mail on the closing/reviewing of the current proposals. ITDM will eventually close it this week.
- Request for changes on new proposals have to be sent today to ITDM, before its creation. After being created, remains valid for the next half year. New proposals will be available for use from Monday.
- Maintenance tasks: online storage was finished yesterday evening. Currently everything online is available again. DAQ will be brought up today and cross-checked specially for SA1 where servers were 
exchanged (new clean installation).
- Exchange of switches for transferring data between Desy and Schenefeld was done.
- Early morning network maintenance: just two routers need further investigation by NOC (using old firmware). Action shall be unnoticed as there is a redundant system. 

XRO:
- Proceeding with maintenance planned tasks.
- Reminder on the delayed installation of the XTD2 new bender for SA1 because of problems with cooling/ air conditioning at the labs.
- XTD9 distribution mirror M3 for SA1: XRO noticed the soft limits were changed and position of one mirror was different. 
Changes in soft limits may be related to power cut; XRO has changed back to the proper values but this has to be checked again during re-start of operation.

LAS:
- Nothing to report.

UNSYS:
- SA1 cell#33 undulator and rack have been shifted to cell#2.
- Apple-X small hiccups but optimistic that will be good for next week.

SPB:
- Nothing different from Monday.

FXE:
- Usual activities ongoing; tests with robot software library and middle layer devices for movements to be done today.

MID:
- All fine at MID.

HED:
- Nothing to report.

SCS:
- Nothing to report. All fine with transportation activities.

SQS:
- Nothing to report.