SASE1 Status and SASE3 Readiness
|
Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther |
Not logged in |
|
|
Message ID: 284
Entry time: 06 Dec 2021, 11:54
|
Author: |
Frederik Wolff-Fabris |
Location: |
General |
Severity: |
Information |
Subject: |
Notes XO Integration Meeting 06.12.2021 |
|
|
General Announcement:
- Cooling water situation at XHQ: initially there is no cooling water until possibly 13.12. To the best of XO knowledge all groups are informed. If this is not the case please contact XO.
As soon as water comes back to normal an e-mail will be sent.
- Jorg H. asks on the safety trainings for employees (relates to the sexual harassment traning from an e-mail of Sven M. / Desy this morning).
Sandra Plett comments that this is not mandatory to XFEL colleagues but it will be clarified today via an e-mail. The Basic training and hygiene trainings are the ones mandatory to all the staff.
CTRL:
- Last week Karabo deployment done except of the Lasers (to be done this week). If any issue is found please contact CTRL.
- Control network maintenance: control server maintenance takes place on Wednesday between 07:00 and 09:00.
DA:
- Online data analysis service is also down due to maintenance tasks.
EEE:
- Start this week with tunnel loop updates.
- Ongoing HED installation cables; also cabling work at SPB ongoing.
VAC:
- Continuing with shutdown activities (ongoing accordingly to the schedule).
- Power cut in XTD2 last Friday is not yet understood.
- Broken power supply that affected fire extinguisher system was resolved.
XPD:
- Continuing with maintenance tasks: XTD2 differential pumping systems; transport of hard X-ray PES taking place tomorrow at XTD2.
DET:
- Nothing to report.
ITDM:
- Wednesday early 7:00 to 9:00 no control network due to switches upgrade.
- Today and tomorrow online storage system will be upgraded in offline mode by being disconnected from the clients (therefore it takes shorter time).
- Planned for today and tomorrow the exchange of switches to Desy.
XRO:
- Continuing the list of activities: due to the stop of cooling water the preparation of the re-installation of the bender in XTD2 is delayed.
Lab is currently at 28C and when temperature is stable activities will resume. Only then will evaluate if intervention will be feasible or not.
- Tasks with EEE and motors will start next days.
LAS:
- Confusion with cooling water on lab area that was lost around 15:00 on Friday. Apart of that all is fine. XO will look into it when cooling water is back.
UNSYS:
- Two Apple-X undulators are in the shaft building for connecting vacuum pipes.
- Undulator SA#1-cell#33 to be moved to cell#2. Collimator/Pb shield was moved to downstream of Diagnostic Undulator.
SPB:
- Installations of hardware planned for this week.
- Working with EEE and others to get hardware moved to the new rack room.
- Needs to negotiate to keep vacuum running.
FXE:
- Not present.
MID:
- All fine at MID with maintenance works.
HED:
- Laser interlock update at HED: laser interlock not functional this week;
- Tunnel activities by HED is done.
SCS:
- Activities are ongoing accordingly to the plan.
- Experimental chamber is moving to SCS hutch today.
- Contacted TS in order to run the air flow in the laser run (due to SXP installations): discussed and solved with Alexander K. (TS). About the rack room the 20C is running but rack rooms must be kept
open.
- Alarm of the Draeger cabinets appeared this morning but not yet understood.
SQS:
- Nothing to report. |