Technical integration and coordination SASE1 Status and SASE3 Readiness
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 296     Entry time: 31 Jan 2022, 10:03
Author: Frederik Wolff-Fabris 
Location: General 
Severity: Information 
Subject: Notes XO Integration Meeting 31.01.2022 
General Announcement:
-  On this current run, beam delivery to instruments will start on Tuesday at 07:00AM.

CTRL:
- New version of DeviceClone and Doocsml device will be updated today which contains a bug fix;
- Minor update on Karabo framework version on the datalogger machines will be performed today
- CTRL will proceed with the update today at 13:00 if they didn't hear any objection till 12:00. Intervention will not take longer than half an hour. No need to check afterwards.

DA:
- Nothing to report.

EEE:
- Nothing to report.

VAC:
- Notification on power interruptions on the weekend: it seems to have no impact but please check the systems.
- Zunaira A. says the AIBS looses connections to network during glitches and has to be restarted if not masked. She will take a look.

XPD:
- Nothing to report.

DET:
- Nothing to report.

ITDM: 
- Nothing to report.

XRO:
- No big issues during the weekend; smaller ones were solved.

LAS:
- SA2 PP-laser is ON;
- SA3 PP-laser will need tomorrow to fix final things.
- SA1 PP-laser: LAS has negotiated with instruments to further investigate more.

UNSYS:
- SA1 issue on Saturday: problem with CPU;
- Ongoing tests with Apple-X this morning.

SPB:
- Aligning instrument to take beam tomorrow.

FXE:
- Nothing to report.

MID:
- All fine at MID.
- MID did not look yet in the PP-laser but will do so tomorrow or Wednesday.

HED:
- Waiting for DAQ rollout. In contact already with DA.
- Zunaira A. reminds on the reply for scheduling the hutch search training. HED will inform after their afternoon group meeting.

SCS:
- Nothing to report. SCS will also make a schedule and will contact Zunaira A.

SQS:
- Nothing to report.