Technical integration and coordination SASE1 Status and SASE3 Readiness
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 290     Entry time: 10 Jan 2022, 09:22
Author: Frederik Wolff-Fabris 
Location: General 
Severity: Information 
Subject: Notes XO Integration Meeting 10.01.2022 
General Announcement:
- The "Readiness" mailing list will be discontinued and substituted by the "xo-info@xfel.eu" list. This new list is owned by XO and please use it in future for sharing information to a broad audience.
- Next News on the Covid regulations will be communicated on Wednesday 12.01 or for the next Thursday's staff meeting.
- Please take attention to Zunaira A. e-mail on the radiation safety training. It shall be done until the end of January to avoid disruption in access rights.

CTRL:
- No major updates.

DA:
- Nothing to report.

EEE:
- SASE1 VAC loop will be update tomorrow including the PES system.

VAC:
- No issues to report. Continuing with small tasks being done at XTD2 and XTD6.

XPD:
- All continued tasks are fine, mainly XTD2, XTD6 and XTD9.

DET:
- Nothing to report.

ITDM: 
- Nothing to report.

XRO:
- Carry on with maintenance works - SASE1 and SASE2 are in vacuum;
- XTD6 PBLM diamond to be exchanged this week as well as screens.

LAS:
- Not present.

UNSYS:
- Alignment for the Apple-X to be done this week and vacuum will be closed until Thursday.

SPB:
- Small issues with things moved into new racks; being followed with EEE.

FXE:
- Continuing with tasks.

MID:
- MID looks for a CL flange with SmartAct connection. Please contact MID or Joerg H. if you have one to help MID.

HED:
- All fine at HED.

SCS:
- Nothing to report.

SQS:
- Nothing to report.