Technical integration and coordination SASE1 Status and SASE3 Readiness
  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther, Page 24 of 30  Not logged in ELOG logo
ID Date Author Location Severitydown Subject Text Attachments
  476   20 Feb 2018, 12:29 Eric BoydGeneralInformationFXE Beam Shutter KeyThe FXE beamshutter key has been installed
into the interlock system after satisfactory
completion of the FXE Chicane and Radiation
  
  477   21 Feb 2018, 10:55 Adriano ViolanteGeneralInformationStatus report after dispatch meeting 09.30SPB


KB chamber being pumped
down
Smaract commissioning ongoing
Coordinate
  
  478   21 Feb 2018, 13:49 Alessandro SilenziGeneralInformationRe: Status report after dispatch meeting 09.30Small correction:

The coordinated motion is the KB-mirror's,
not the Vacuum.
  
  479   23 Feb 2018, 15:54 Gerd WellenreutherGeneralInformationStatus and plans after Readiness Meeting 23.02. Photon Run Coordinator (L. Samoylova):


SASE1 tuning is ongoing
(350 microJ)
SASE3 3000microJ
SASE1
  
  480   26 Feb 2018, 12:09 Monica ArestéGeneralInformationStatus report after dispatch meeting 26.02SPB:


Ion pumps running in the
Mirror chamber.
Starting test
  
  481   28 Feb 2018, 10:55 Adriano ViolanteGeneralInformationStatus report after dispatch meeting 09.30SPB:


Ion pumps running in the
Mirror chamber. Vacuum level OK to run.
D.02
  
  482   02 Mar 2018, 14:36 Adriano ViolanteGeneralInformationStatus and plans after SASE1 Status/SASE3 Readiness Meeting 02.03.Photon
Run Coordinator (N. G. Kujala):


SASE1


  
  483   05 Mar 2018, 11:07 Adriano ViolanteXHEXPInformationStatus report after dispatch meeting 09.30 

SPB


Last night the beam disappeared
  
  484   05 Mar 2018, 16:37 Adriano ViolanteGeneralInformationDetails on SPB issues reported in the dispatch meetingsBelow some clarifications from R. Bean
on the issues reported in today's dispatch
meeting:
  
  485   07 Mar 2018, 11:14 Adriano ViolanteGeneralInformationStatus report after dispatch meeting 09.30SPB:


Monday morning Karabo failed.
It was not possible to operate anything.
  
  486   12 Mar 2018, 08:18 Adriano ViolanteGeneralInformationStatus and plans after SASE1 Status/SASE3 Readiness Meeting 09.03Photon Run Coordinator (L. Samoylova):


Commissioning during
  
  487   12 Mar 2018, 13:18 Adriano ViolanteGeneralInformationStatus report after dispatch meeting 09.30SPB (Weinhausen):


During the night there
was an interlock issue. The fast shutter
  
  488   14 Mar 2018, 10:06 Adriano ViolanteGeneralInformationStatus report after dispatch meeting 09.30SPB (Weinhausen/Round/Mancuso):


Again on the fast valve was
triggering the MPS interlock system. For
  
  489   19 Mar 2018, 08:42 Adriano ViolanteGeneralInformationStatus and plans after SASE1 Status/SASE3 Readiness Meeting 16.03..Photon Run Coordinator (H. Sinn):

1.) SASE1: User experiment SPB
could be finished sucussfully after several
  
  490   19 Mar 2018, 10:24 Adriano ViolanteGeneralInformationStatus report after dispatch meeting 09.30No new issues to be discussed where reported
by any groups.

The status and issues reported
  
  491   21 Mar 2018, 10:02 Adriano ViolanteGeneralInformationStatus report after dispatch meeting 09.30SPB

On monday there was an issue with
a detector related PLC due to misconnection
  
  493   26 Mar 2018, 13:10 Adriano ViolanteGeneralInformationStatus report after dispatch meeting 09.30General

Due to the triggering of the emergency
power off in FXE caused by electrical works
  
  494   27 Mar 2018, 14:18 Jan GruenertGeneralInformationXTD1 openInfo from BKR:  the southern tunnels
were opened, thus XTD1 can be accessed now.
  
  495   28 Mar 2018, 15:22 Adriano ViolanteGeneralInformationStatus report after dispatch meeting 09.30SPB


Sample delivery installed.
Tonight will be commissioned. Experiment
  
  496   29 Mar 2018, 09:48 Hugo Silva SantosGeneralInformationRe: Status report after dispatch meeting 09.30Update regarding Digitizer:

----- Forwarded Message -----
From: "hamed sotoudi namin"
  