Group Selection Page HELP DOC Controls Group Data Analysis Group ITDM WP76 DET Vacuum XRO EEE WP78 WP74 FXE SCS SPB MID HED SQS SXP Sample Environment Photon Commissioning Team Operation PSPO XO TS
Technical integration and coordination SASE1 Status and SASE3 Readiness
  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther, Page 25 of 30  Not logged in ELOG logo
ID Date Author Location Severitydown Subject Text Attachments
  497   04 Apr 2018, 13:43 Gerd WellenreutherGeneralInformationStatus reports after dispatch meeting 13:00 4.4.SPB/SFX:


Mirror installation next
week


FXE:
  
  498   04 Apr 2018, 17:35 Janusz SzubaGeneralInformationControl network maintenanceTomorrow, 5.04, between 9:30 and 12:00
there will be urgent maintenance of one of
the two redundant main switches for the control
  
  499   04 Apr 2018, 17:46 Janusz SzubaGeneralInformationmaintenance of the online storage systemOn Friday, 6.04, there will be a maintenance
of the online storage system. This will tackle
the issues we had just before the last user
  
  500   09 Apr 2018, 11:50 Adriano ViolanteXHEXPInformationEmergency off test in SPB/FXE - UpdateDue to some delay in the installation of
some necessary cables, the emergency power
off test foreseen for today 06.04. in the
  
  501   09 Apr 2018, 14:25 Adriano ViolanteGeneralInformationStatus report after dispatch meeting 13:00General

Emergency off test in SPB is shifted.
Date to be agreed on Friday. FXE test stays
  
  502   09 Apr 2018, 14:37 Adriano ViolanteGeneralInformationKarabo deployment datesFYI

Below
the E-Mail from Hugo Santos with the Karabo
  
  503   11 Apr 2018, 13:48 Adriano ViolanteGeneralInformationStatus report after dispatch meeting 13:00SPB


Detector z motion would
be needed. AE checks the status of the crate.
  
  504   12 Apr 2018, 15:34 Adriano ViolanteGeneralInformationWater cooling mointenance by MKK doneDie Arbeiten an der Kühlwassersteuerung
konnten innerhalb des genannten

Zeitraums abgeschlossen werden,
  
  505   13 Apr 2018, 07:50 Adriano ViolanteGeneralInformationKarabo 2.2.3 installationHi all, for your information below a message
from Chris Youngman concerning Karabo 2.2.3
installations in SASE3.
  
  506   13 Apr 2018, 09:05 Torsten SchoenXHEXPInformationSASE3 E.21 and E.22 electrical power distributionchanges according to the racklist on the
electrical power distribution cabinets for
rackrooms E.21 and E.22 are done. Power supply
  
  507   13 Apr 2018, 09:40 Adriano ViolanteXHEXPInformationEmergency off test in SPB/FXEEmergency power test will be performed
at the following dates:

FXE - Mon. 16.04.
  
  508   13 Apr 2018, 13:01 Adriano ViolanteXHEXPInformationDates TÜV Test SASE3 IntelrocksInterlock systems SASE3 - TÜV test

The pre test by D3 will be held
on 20.06.
  
  509   13 Apr 2018, 13:50 NEREA JARDONGeneralInformationShutdown MicroTCA4 SPB and FXEThis entry is on behalve of Frank Babies,
if you have any doubt about it, contact him:

On 16.Apr.2018
  
  510   16 Apr 2018, 12:38 Adriano ViolanteXHEXPInformationEmergency off test in FXE - Update and next stepsDear all,

 

I was just informed by Ulf Brueggmann
  
  511   16 Apr 2018, 14:20 Adriano ViolanteGeneralInformationStatus report after dispatch meeting 13:00Summary of Karabo 2.2.3 deployment
dates:


Karabo 2.2.3 deployed in
  
  512   17 Apr 2018, 14:23 Torsten SchoenXHEXPInformationSPB emergency power off testsDear all,

 the emergency power off test
has been successfully performed in SPB.
  
  513   18 Apr 2018, 13:43 Adriano ViolanteGeneralInformationStatus report after dispatch meeting 13:00SPB


Karabo has been deployed 
without major  problems! 
Now
  
  514   18 Apr 2018, 15:06 Gerd WellenreutherGeneralInformationTunnel closing after shutdownDear all,

below please find the hottest and
most up-to-date times for the closing of
  
  515   23 Apr 2018, 15:35 Adriano ViolanteGeneralInformationStatus report after dispatch meeting 13:00SPB


Timing tool for optical
laser installed
Sample chamber's
  
  516   25 Apr 2018, 11:42 Marijan StuparXTD10InformationSASE3 MOV1 loop updateI will update the SASE3 MOV1 loop in 30
minutes. Please let me know if you would
like me to postpone the update.
  
ELOG V3.1.4-7c3fd00