219
|
26 Apr 2021, 11:08 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 26.04.2021 |
General Announcement:
- The deadline to submit the maintenance task list is on 30.04. We thank all the groups that have already submitted. In case of any question and comments, please contact
us at xo-planning@xfel.eu
- Patrick Gessler reminds on the DRC meeting on Mondays 13:00. This meeting is done together with instruments to exchange information for the weekly plan. The e-mail for
contact is drc-jour-fixe@xfel.eu
- Andreas G. says that with the new 7-11 operation mode, XO is interested in knowing how longtime instruments need to be ready to take the beam in the early morning.
Please inform us for that XO checks the efficiency of this model.
CTRL:
- Remind on Beckhoff training next Wednesday (following e-mail to readiness).
- Upgrades of two Karaboo Beckhoff servers today (Karabo devices go down for 5-10 minutes, proposed to be done today during lunch time): SA2 master tunnel loop; and the
HED loop.
- Bug on ADQ for twelve devices, affecting SQS and others: EEE has discovered it and CTRL is analyzing to come up with a fix.
DA:
- Nothing to report.
EEE:
- Nothing to report.
VAC:
- Nothing to report.
XPD:
- PES in SA3 was provided and operated last week for instrument's usage.
DET:
- Nothing to report.
ITDM:
- Nothing to report.
XRO:
- Maurizio V. requests the SA2 experiments to provide information to XRO on issues related with mirror alignments or transport beamline.
LAS:
- Received info from Desy on a power glitch today at around 6AM. At the same time SA1 Amphos switched OFF due to not enough water.
It’s under investigation with TS. Jan G. points that also there was a beam loss in delivery around the same time.
- SA2 and SA3 PP-lasers are still in operation.
UNSYS:
- Issue with undulator SA1 /cell33 and cell1/SA3 needs ZZ. Currently the impact in operation is minimal and ZZ is postponed to the next available date.
SPB:
- Nothing to report.
FXE:
- Run with beam delivery went smooth.
MID:
- Quite successful beam week with small hick-ups to be addressed with experts.
HED:
- Commissioning beamtime this week; Data analysis will be made this week.
- Test of the PLC synchronization with Relax laser to be done this week.
SCS:
- Not present.
SQS:
- uTCA in ADQ had been mentioned already by CTRL. It has been tackled. |
599
|
26 Mar 2025, 09:43 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 26.03.2024 |
General Announcement:
- A. Galler reminds on the LIMP-2025 meeting taking place next Friday. If any group misses an invitation, please contact Martin Doering.
XO expects that the information distributed on Friday will be shared between the group by the present representative.
CTRL:
- Nothing to report.
DA:
- Not present.
EEE:
- Nothing to report.
VAC:
- Nothing to report.
- GATT/SA3 returned to normal operation after last week with gas exchange.
XPD:
- Nothing to report.
DET:
- Nothing to report.
ITDM:
- Nothing to report.
- Gateway issue just happened and may need a reboot after investigation.
XRO:
- A ZZ in XTD2 happened to CRL accumulated problems. It found one encoder is finally dead.
It was communicated to instruments that arm#2 vertical motion is in open loop as does not have an encoder reading. Realignment is needed as position is lost. Operation can continue and replacement of part
will be organized.
LAS:
- Can not access the gateway; ongoing fix with ITDM.
- SA1 PP-laser is down due to AMPHOS computer down.
- A. Galler enquires on responsibility for the AMPHOS shutter safety; clarification between LAS and SRP has to be done.
- SA3 ADC PP-laser missing values: understood by LAS and EEE; issue with settings of number of pulses. An update will be done to permit pulses higher than 800.
UNSYS:
- Nothing to report.
SPB:
- Nothing to report.
FXE:
- Nothing to report.
MID:
- Nothing to report.
HED:
- Nothing to report.
SCS:
- Nothing to report.
SQS:
- Nothing to report.
SXP:
- Not present. |
591
|
26 Feb 2025, 09:24 |
Andreas Galler | General | Information | Notes XO Integration Meeting 26.02.2025 |
General Announcement:
-
CTRL:
- nothing major
DA:
- nothing major
EEE:
- PLC large detector mover worked yesterday but not on the weekend (MID)
- CRL1 Lens2Y SA1 encoder not working
VAC:
- only minor thing
XPD:
- ZZ yesterday
- pre vacuum for PES in XTD10, solved quickly and things back to normal. --> a valve was not completely closed putting load on the scroll pump thus in
DET:
- Nothing major
ITDM:
- nothing to report
XRO:
- access to XTD2
- exchanging proximity sensor for lens1y in CRL1, XTD2
- checked SRA on issues
LAS:
- not to report
UNSYS:
- nothing to report
SPB:
- nothing to report
FXE:
- CRL5Y motor issue in hutch, solved with help of Moises, tolerance had to be tweaked.
MID:
- all fine and thanks to EEE for helping with the large detector mover.
HED:
- all good
SCS:
- nothing to report
SQS:
- not present
SXP:
- nohting, all set |
493
|
26 Feb 2024, 09:42 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 26.02.2024 |
General Announcement:
- As PRC since Sunday, Maurizio Vannoni reports the weekend had no major issues.
CTRL:
- Nothing to report.
- Steffen H. updates that Saturday night issues at SPB/SFX DAQ happened. Seems to be related to a late data from Hirex. Decided to switch to legacy version and is running smoothly. New tests are schedule
for this week.
DA:
- Nothing to report.
EEE:
- Nothing to report.
VAC:
- Nothing to report.
XPD:
- Nothing to report.
DET:
- Nothing to report.
ITDM:
- Issue with data migration: strange pattern; under work.
XRO:
- Nothing to report.
LAS:
- Nothing to report.
UNSYS:
- Waiting for the ZZ on March 5th to fix PS in SA3.
SPB:
- Nothing apart of the DAQ issues.
- User collects data.
FXE:
- Nothing to report.
MID:
- Nothing to report.
HED:
- Running in general with very happy performance of HXRSS.
- Sample water stop update; a redmine ticket to EEE is sent and is under discussions.
- User wanted background measurements with HIREX. To be done on last hour of beamtime.
SCS:
- Nothing to report.
- Getting data at one color mode.
SQS:
- Nothing to report.
SXP:
- Not present. |
295
|
26 Jan 2022, 10:46 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 26.01.2021 |
General Announcement:
- The cold compressor failed this morning and beam operation is currently stopped. We expect the beam operation for the alignment of beam systems will resume tomorrow morning (Thursday).
CTRL:
- Nothing to report.
DA:
- Nothing to report.
EEE:
- Closing last tasks for the maintenance.
VAC:
- All fine.
XPD:
- Issues with PES were solved by CTRL.
- Jan G. asks when beam would be aligned to M1 and M2 in SA1 and SA2? (see XRO report).
DET:
- Nothing to report.
ITDM:
- Work ongoing with company regarding Monday's report on offline storage system.
- Jan asks for the DAQ Karabo test with XPD. Janusz S. suggested to contact Partha who is on charge for this.
XRO:
- Ahead of schedule with alignment until this morning: SA1 and SA2 beam established in all experiments. SA1 beam on mirror but it needs to finish Bender calibration (nice beam at the end of the SA1
tunnel).
- Currently cryo is down and pushes back next days plans: Today planned schedule of tuning 17.2 keV in SA1 as well as Apple-X in SA3 is shifted to tomorrow.
If beam comes tomorrow morning SA2 is available for alignment. By end of the week one starts with SA3.
LAS:
- SA2 almost ready: it shall be finished by end of the day.
- SA3 Amphos maintenance is finished: maybe ready end of the week or start next week.
- SA1 is making progress: 1.1MHz operation shall be OK but 280kHz can be have some difficulties.
UNSYS:
- Power failure in SA1 central control node prevented communication to undulators during the evening. It was solved after power cycle.
SPB:
- Busy with aligning beamline.
FXE:
- Same as SPB; nothing else to report.
MID:
- All fine.
HED:
- Not present.
SCS:
- All fine.
SQS:
- Nothing to report. |
568
|
25 Nov 2024, 10:02 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 25.11.2024 |
General Announcement:
- Martin Doering announces on the upcoming Winter Maintenance period:
1. Summary Task list was released last Friday 22.11;
2. A total of 10 working days is predicted for the WMP;
3. Dates for availability of Karabo, timing, DAQ, online storage were shown (selected period from Dec. 11 to Dec.18th);
4. Cooling water and technical gases maintenance (Dec.11th-20th);
5. Electricity: localized task in SA3 SCS exp. Hutch with installation of new emergency OFF button on January 15th: power will go OFF; Interlock tests light in all SASE hutches on January 15th;
6. In case of questions please contact xo-planning@xfel.eu
- As PRC, Jan G. mentions a full report for the weekend events is available at the Operations e-log:
1. events on Saturday limited SA1 and SA3 to a max of 30 bunches combined; caused by communication failure by the EPS - partially solved on Saturday but happened again on Sunday afternoon.
EPS loop was solved by replacing a communication terminal; The MOV loop relates to a terminal seemed to be burned (redundancy was working) – this needs to be worked on Tuesday's ZZ.
Limitation of 30 bunches came as communication was lost. Recovered after the work on Saturday and Sunday.
2. Broken bridges Karabo-Doocs went down on Friday evening: not caused a beam downtime but photon devices could not be seen at DOOCS.
A Desy CPU at the injector building failed and Tim Wilksen intervene to restore the bridge and will follow-up.
3. SRA slits and Filter are locked now until the ZZ on Tuesday or the WMP.
CTRL:
- Nothing to report.
DA:
- Nothing to report.
EEE:
- Issues in XTD2 (Sat and Sun) with PLCs and MOV loops: element had to be replaced to get back EPS on Sunday; Investigation for the cause are still ongoing.
- A new ZZ has to be done on Tuesday still related to the weekend events.
VAC:
- OCD involved on weekend activities to reset some EPS signals and ZZ.
XPD:
- Damaged YAG in SA1 XTD2 FEL imager was found during the weekend, to be worked in WMP.
DET:
- Nothing to report.
ITDM:
- Nothing to report.
XRO:
- Apart of the SRA issue reported in SA1, nothing else to report.
LAS:
- Not present.
UNSYS:
- Nothing to report.
SPB:
- Issue with detector motion limit switches; EEE will investigate.
- J. Gruenert says a downtime of 40mins happened due to a broken radiation interlock in SPB/SFX bringing down the machine. SPB/SFX will investigate the cause.
FXE:
- Thanks to OCD colleagues for the help during the weekend to restore full beam permission.
- Issues with gain acquisition with LPD happened and a ticket was created. Expert investigation is needed by EEE and DAQ.
MID:
- Nothing to report.
HED:
- Nothing to report.
SCS:
- Nothing to report.
SQS:
- Nothing to report.
SXP:
- Nothing to report. |
181
|
25 Nov 2020, 10:14 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 25.11.2020 |
General Announcement:
- There is no UOM or XO Int. Meeting next Friday 27.11. We will continue with XO Int. Meeting next Monday 30.11.
CTRL:
- Karabo Deployment in FXE takes place today. Schedule for full Karabo deployment was sent to the Readiness mailing list.
- Two SA2/SA3 Beckhoff devices topics will be updated today (5-10 minutes downtime).
DA:
- No issues or announcement to report.
EEE:
- PLC side: tunnel updates to be started with CTRL.
- Change requests also to start today in a couple of instruments.
VAC:
- Not present.
XPD:
- PES/MEA: there are individual tasks ongoing.
DET:
- Nothing major to report. AGIPD intervention is goes faster than planned.
ITDM:
- Offline storage update was done and is available since Tuesday.
- Online cluster update has started: SA1 already available since Tuesday. Today ITDM will finish SA2/SA3. Crosscheck and start DAQ will follow.
XRO:
- Not present.
LAS:
- Nothing special to report.
UNSYS:
- Not present.
SPB:
- AGIPD work is ongoing and fine.
FXE:
- Wille company is installing cables in the hutch.
- Issue with craning on SA3 / SXP activities above FXE area: FXE asks for coordination to avoid interrupting activities.
Gerd W. says it shall not be a problem as crane will be used for few period. Martin K. will inform his phone number for arranging craning times.
MID:
- All fine at MID.
HED:
- All fine at HED.
SCS:
- Shutdown activities ongoing.
- Situation of JJ X-ray will be clarified by SCS staff.
SQS:
- Nothing to report. |
463
|
25 Oct 2023, 09:26 |
Andreas Galler | General | Information | Notes XO Integration Meeting 25.10.2023 |
General Announcement:
CTRL:
- nothing major --> a couple of people on vacation, i.e. issue repsonse time may be a bit longer this week
DA:
EEE:
VAC:
XPD:
DET:
ITDM:
XRO:
LAS:
UNSYS:
SPB/SFX:
- SA3 background affecting focussing of x-rays
FXE:
- smooth, beam instability yesterday
- horizontal jitter entagled with PopIn measurements --> around lunch time
- beam was clipping and LPD was seeing poweder scattering from the collimator pipe
MID:
HED:
- Yesterday evening unexpected venting in the CRL3 (HED-Optics Hutch) --> X-ray Operation cancelled at least for Wed night
SCS:
- beam instability in pointing over night
- this cuased non optimal beam transport --> pulse energy decreased on sample
SQS:
SXP:
DRC
PRC
- SA1 pulse energy will be lower than possible, because of XGM settings that need to cater 7.8 keV and 12.5 keV
|
271
|
25 Oct 2021, 10:50 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 25.10.2021 |
General Announcement:
- An e-mail was sent to "xo-info" mailing list concerning the cooling water maintenance scheduled for one week starting on Dec. 6th.
More information will be sent by the end of this week and if you have any concerns, please contact us at xo-planning@xfel.eu.
CTRL:
- Shimadzu camera at SPB to be followed up; Also, the pop-up motor at HED needs a feedback.
- Related to DRC: on Friday SQS was using the bunch patter server and the machine server was going back to zero pulses. Cause was another Karabo device at SCS topic which was working / forgotten and was
setting bunches to zero.
Important is that none was knowing this was running. Follow up with XO for new procedures.
DA:
- Nothing major to report.
EEE:
- PLC side: backlash 2 step compensation successfully tested.
- Cabling at FXE had some troubles and today there will be a recheck.
VAC:
- Friday incident with Interlock on SA3 (faulty gauge at GATT): reason is known and was communicated to the involved parts. Long term plan to mitigate is in place.
XPD:
- Involved at high energy tests in SA1 and SA2; SA1 worked well delivering beam at SPB; SA2 had 300uJ in XTD1 but a high intensity at HED was not achieved. On Sunday HED colleagues did some tests;
Calorimeter did not see beam.
- Imagers YAG imagers could see the beam at the end of HED station. YAG is not too bad at these high energies (only factor 2x less). Diamond is not suitable as one needs to integrate lot of pulses to get
signal.
- Upgrade on Imagers together with Andrea Parenti is already concluded, tested and shall be working fine. Some Karabo devices had to be restarted in SA1, SA2 and SA3. In case of issue, please contact
Andrea Parenti.
DET:
- DSSC activities with DEPFET ladder measurements at SQS went well; happy with acquired data.
ITDM:
- Nothing to report.
XRO:
- SA1 re-alignment of mirror was not immediately possible and therefore done in several attempts. Started from none position but went well at the end.
- In SA2 re-alignment was not possible (settings of mirrors not ideal and therefore drop of beam intensity); In future a second attempt shall be made with the lessons learned. In SA1 went well.
- SA3 activities went well without problems.
LAS:
- From SQS high energy fluctuations were seen at PP-L and fixed after switching to another setting.
UNSYS:
- Motor of monochromator of chicane 2 / SA2: remotely action did not recover it. Access is needed. Suren K. needs a 2-3 hours of access (realistic time) and there is no guarantee it will work.
SPB:
- Got beam at 24keV.
- On Saturday a problem with camera Shimadzu not communicating to PLC was solved.
- Beam drift at downstream of SA1 (mm order) was seen.
FXE:
- Preparing for Users this week.
- Work with cabling ongoing.
MID:
- All fine.
HED:
- Having the 30keV beam and trying to align; Diffraction seen but could not say that the beam goes to the beam stop. Beam intensity too low for absorption edges.
- Preparing for Users this week.
SCS:
- Not present.
SQS:
- Nothing to report. |
551
|
25 Sep 2024, 09:57 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 25.09.2024 |
General Announcement:
- Machine had a rough day yesterday and last night with downtimes due to problems with L-IBFB, dump communication, vacuum in A14.
Files for beam delivery were prepared and small pointing corrections had to be done this early morning. Beam is currently in delivery mode.
- Martin Doering present the schedule on the preparation for the next Winter Maintenance Period: task list will be sent to groups on 11.10 and shall be returned to XO by end of October.
CTRL:
- Nothing to report.
DA:
- Not present.
EEE:
- EEE reminds the group will be in a retreat today and tomorrow.
VAC:
- Issue with GATT this morning in SA3: Argon supply line shows interruption and need a ZZ to evaluate the issue.
- As PRC, Jan G. says that it is organized with BKR and SPB/SFX and ZZ can happen as soon as VAC colleagues are ready to enter tunnel.
XPD:
- Changed PES setup to run this week.
DET:
- Nothing to report.
ITDM:
- Nothing to report.
XRO:
- Nothing to report.
LAS:
- In theory nothing to report.
- Daniel Kane will speak to XO and LAS about THz delivery last week to FXE.
UNSYS:
- Nothing to report.
SPB:
- Water leak in top of control room today: TS is working; humidity is still high.
- Installing the new chiller and AGIPD being cooled down.
FXE:
- Nothing to add.
MID:
- All fine at MID; vacuum issues in hutch but A. Parenti is on it or already solved.
HED:
- Not present.
SCS:
- Nothing to report.
SQS:
- Nothing to report.
SXP:
- Not present. |
454
|
25 Sep 2023, 12:31 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 25.09.2023 |
General Announcement:
- Two severe power glitches happened on the weekend (SAT and SUN around 7AM). We thank all colleagues that were in shift, OCD or volunteered to help assessing the situation and restoring their operation
ability.
- The presentation of the Winter Maintenance planning period is postponed due to time issues.
- Janusz S. reminds on cyber security: tomorrow the next step to secure Zimbra mail client takes place. A detailed e-mail will be sent.
- XO will create a report on the power issues.
CTRL:
- Issues with power glitch: restoring parameters, Karabo, SEPS, SA2 started from scratch.
DA:
- Nothing to report; end of chain regarding the power issues.
EEE:
- Same issues with power.
- Will follow up the SCS train ID.
VAC:
- No effect on VAC; no access to SA2 then it was blind / no Karabo, but at the end was fine.
- Issue with HED and MID Monochromator - to be investigated. Access is needed today.
XPD:
- As PRC Jan thanks all people who helped to restore SA and SUN (two power glitches around 7AM); Also Desy/MKK confirmed that machines were briefly affected. EuXFEL accelerator recovered quickly.
- Consequences on SAT: 1. Power went away of whole SA3 area; 2. Tunnels mostly not affected but water cooling pumps were switched OFF (affecting also balcony rooms).
One auxiliary pump did not turned ON and several hours later (10-11AM this was too hot) and brought down services. SA2 tunnel cooling water temperature raised but on SUN it was faster to act/recover (MKK;
30mins).
- XGM at XTD6 went down.
- MKK does not see the temperature but only humidity. To be implemented in the coming days.
- SA2 Karabo totally down.
- Interlocks went down (EEE, D3, SRP) and had to unblock radiation alarms. A Desy mTCA crate went down and had to be manually power cycled (due to cooling water lack at balcony room).
- PP-laser in SA3 went down. SA3 experiment at SCS was cancelled at the point.
DET:
- No specific feedback for DET; shall be OK.
- Broker pile up was not fully understood. SA2 was restarted and back to normal; MID restarted yesterday and will get in touch with them.
ITDM:
- Cooling issue: discovered by alarm (Kimon who informed MKK); it needs a better procedure to inform MKK.
- After 30 mins called from MKK saying T was going down, but due to open doors.
- Steffen H. says a report has to be done with goal oriented to avoid this in future.
XRO:
- Looking into systems: in tunnels, if power is OFF then mean cooling shall be OFF. Cameras do not work remotely (connection to servers; only one is accessible).
LAS:
- SA3 is down: problems with main amplifier;
- Checking for damage after second power glitch.
UNSYS:
- All fine.
SPB:
- Nothing to report. User got data.
FXE:
- SA1 was also affected by power glitch (interlock crashed): had to be reset by D3; AIBS went to error and be reset by DOC.m
- Prevented continued with user (lost 6+4 hours of beamtime). User went well and collected data.
- On Saturday the AMPHOS laser broke down in FXE. SRP and Management took measure to bypass. Not sure if caused by electricity. To be followed up this week.
MID:
- Nothing to report. Request: in such severe power glitches an e-mail to MID has also to be sent.
HED:
- Could recover after SA2 Karabo broke down. Recovery faster than expected.
- Continued with user program. Data was successful.
SCS:
- Stopped running experiment.
- Interlock problem with laser helped by Pouneh (thanks!).
SQS:
- Nothing to report.
SXP:
- Challenging communication. Manuel gave phone number to PRC and will give to XO.
- Power glitch: Desy colleagues do not have access to SXP hutches. |
254
|
25 Aug 2021, 10:08 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 25.08.2021 |
General Announcement:
- A power glitch happened this morning at around 5:46AM. The drop of voltage was seen in two stations (about 0.6kV) and it's smaller than the last Monday's one. In case groups find affected systems, please
let XO know.
CTRL:
- Last night DOC informed on a Broker pileup at FXE. The FXE loop was restarted and mitigated the situation. Further investigations are ongoing and will be coordinated with FXE.
DA:
- Nothing to report.
EEE:
- EEE helps on the Loop 6 pileup reported by CTRL.
- Call from DOC reporting connection issue to Karabo (broker PLC was replaced and had to be configured the connection).
VAC:
- Effects of power glitch seem to be none. Cooling water for the vacuum systems was not affected.
XPD:
- XGM in SCS being offline due to surge of pressure. This was informed by e-mail from SCS last night; interlock tripped due to high-voltage. XPD checked and put back during the night.
Laurent M. says it was not clear why the pressure was increased. It is under investigation and SCS will inform XPD.
DET:
- Nothing to report.
ITDM:
- Nothing to report.
XRO:
- Nothing to report.
LAS:
- Amphos were not switched OFF due to power glitch. PP-laser in SA3 are under maintenance.
UNSYS:
- Nothing to report.
SPB:
- Issue with EPS at 14:10 yesterday: beam permission was blocked by EPS despite both shutters closed and all gate valves open. The signals had to be manually restarted (this info was not transmitted and
EPS blocked beam permission).
Issue appeared when they use beam for the first time; EEE / Nerea J. will further investigate.
FXE:
- Nothing to report.
MID:
- After the power glitch the SA2 beam intensity decreased by 10%. BKR will not do any interaction right now. It is still fine for MID to work in such conditions.
HED:
- Nothing to report.
SCS:
- Apart of the XGM issue, nothing else to add.
SQS:
- Nothing to report. |
344
|
25 Jul 2022, 09:14 |
Andreas Galler | General | Information | Notes XO Integration Meeting 25.07.2022 |
General Announcement:
CTRL:
- Today "bring up" works at FXE
DA:
- Nothing special to report
EEE:
- PLC team is trying to find solutions for slowness in big loops
VAC:
XPD:
DET:
ITDM:
XRO:
LAS:
UNSYS:
- K- Mono Scan last week
- S. Arbeghyan assisted but new undultaor offsets will only be implemented after Aug 5th
SPB/SFX:
- nothing special to report
- bring up days are very successful
FXE:
MID:
- ITDM please keep MID in the loop with SA2 GPFS updates, as MID plans to save data today
- opening of the beam shutter is an issue
- over the weekend MID was forced to open
HED:
SCS:
SQS:
DRC
PRC
SH
- VAC loops SA1 SA2, don't panic because of slowness
|
328
|
25 May 2022, 09:25 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 25.05.2022 |
General Announcement:
- Reminder that the UOM planned for Friday is taking place apart of the holiday on Thursday.
CTRL:
- Nothing to report.
DA:
- Nothing to report.
EEE:
- Two OCD calls related to FXE setups, but solved and working fine now.
VAC:
- Nothing to report.
XPD:
- ZZ on Monday went fine. Imager is repaired.
- Wolfgang F. planning a ZZ for K-mono in XTD1 but needs to talk with Nerea and XO.
DET:
- Nothing major to report.
ITDM:
- Not present.
XRO:
- Yesterday there was stability data taken at HED; data to be processed.
LAS:
- Nothing to report.
UNSYS:
- Planned ZZ for next Monday to relocate Pandora.
SPB:
- Issue regarding Hexapod: trying to fix it for the user measurements; DOC, CTRL, EEE informed.
FXE:
- Preparing devices in the experiment hutch.
MID:
- All fine at MID.
HED:
- Nothing to report; not aware of stability measurements.
SCS:
- Experiment is running.
SQS:
- Not present. |
124
|
25 May 2020, 15:29 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 25.05.2020 |
General Announcement:
- Machine started SA2 lasing last weekend. Currently photon energy is 0.5mJ at 9keV.
- CTRL OCD was called Friday on the SR slits position and movement. It was quickly solved.
- XO ask people who carries work in tunnels to use this meeting to raise questions and concerns.
- XO also ask people to discuss during this series of meetings possible resource conflicts among the support groups for the upcoming week(s).
CTRL:
- New Karabo version installed at MID is working nicely. Instrument staff is creating new panels with Karabo9 and CTRL hopes to integrate
this Karabo version in the whole facility during summer shutdown.
DA:
- Not present.
EEE:
- Working in normal duties.
- Cabling installation in SQS is done. The FXE installation has a mismatch with a rack planning (XGMD) and responsible company for installation
may come back on Wednesday to solve it.
VAC:
- Tunnel works are nicely ongoing.
XPD:
- Working on tunnels and looking at lasing in SA2.
DET:
- Nothing to report.
ITDM:
- Nothing to report.
XRO:
- Nothing to report.
LAS:
- A water leakage in an amplifier box in SA1 laser occurred last Thursday. It is repaired but LAS will have to investigate on possible damages on optics
(due to water inside). Laser operation will be possible only tomorrow or at the end of the week. LAS will provide further details on Wednesday.
SPB:
- Nothing to report.
FXE:
- Nothing to add besides the cabling installation issue mentioned by EEE.
MID:
- New Karabo is working nicely up to now.
- Tunnels work is also finished; MID staff continues with work on the hutch/optics.
HED:
- No issues to report.
SCS:
- SCS will be busy with an external company and needs assistance of SRP on hot work permit. Sandra Plett will communicate with Michael Prollius.
- SCS has informed DET that there is data in the computer to be saved. DET is aware and has taken needed actions.
SQS:
- Nothing to report: activities are progressing normally. |
319
|
25 Apr 2022, 10:09 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 25.04.2022 |
General Announcement:
- Regarding the use of special diagnostics devices: on THU XPD received a call for supporting the use of HIREX in the tunnels. XO would like to ask instruments to inform XPD or XO well in advance for such
requests, if possible.
Please include that in the "Comments" column of the X-ray delivery tables.
- Deadline for submitting the 2022 summer maintenance period is next Friday 29.04.
- A. Silenzi reminds instruments to join the Jour-Fixe meeting with DRC today at 13:00.
- Thomas Michelat reminds that during the night the instruments shall call the regular DOC number and not directly e.g. the CTRL OCD number.
- A. Galler inform the operation affair on the FXE mono is to be prepared in the next week or so, following the updated process for Operation Affairs.
CTRL:
- CTRL reminds that today at 13:00 there is an update of Karabo device in tunnels (for Beckhoff systems).
- Also at 13:00 an update of Aravis cameras in tunnels will take place.
DA:
- Nothing to report.
EEE:
- EEE is continuing the work with PnCCD issues.
- A ZZ in XTD6 will be done today for HED Mono.
- Investigating a motor in a CRL that showed issues.
VAC:
- Nothing to report.
XPD:
- Nothing to report.
DET:
- Marcin S. says that one of the AGIPD central tiles was lost last week after a sudden beam jump. This will be discussed/investigated by DET / Olivier M.
ITDM:
- Sync&Share service is not accessible tomorrow 26.04.
- Today at 10AM the Redmine service will be updated.
XRO:
- Nothing to report.
LAS:
- Nothing to report.
UNSYS:
- Issue on Friday with SA2/cell33 not moving the gap. A remote reset solved the problem.
- Last night when moving SA3/cell21: it did not move and the cause was a strong applied taper. Now it is solved.
SPB:
- Experiments went well.
- AGIPD was affected due to beam movement.
FXE:
- Commissioned the Johann spectrometer last week and this week the plan is commissioning the Gotthard spectrometer.
MID:
- All fine at MID.
HED:
- Different settings for M1 and M2: changed positions have to be coordinated with MID, XPD and XRO when beam will be aligned again to HED. It caused problems for the HIREX alignment.
- A meeting/communication among these groups have to be organized. Angel R.-F. says that today and tomorrow morning work on the mirrors will work. XRO will lead and new positions to be communicated to HED.
SCS:
- Problems with cell21 last night.
- MDL devices for multi-pattern showed issues and will be discussed among SCS and CTRL.
SQS:
- Issue with two digitizers in the same uTCA board that can not be used in interleaved. Current understanding is that one has to ship device back to the manufacturer. |
501
|
25 Mar 2024, 10:24 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 25.03.2024 |
General Announcement:
- A power glitch happened last night around 02:50AM.
CTRL:
- Nothing to report.
- DAQ update: MID had operation during the weekend and seems to run fine; one issue after several hours needed a recycling but further investigation is ongoing to provide a fix in the coming days.
DA:
- Nothing to report.
EEE:
- Nothing to report.
VAC:
- Nothing to report.
XPD:
- Nothing to report.
DET:
- Nothing major to be report.
- AGIPD in SPB/SFX is running with 16modules; issue with connection caused one module to do not work (due to positions). There is a golden position and for next quadrant move has to be observed.
For a fix one needs a heavy intervention (disassemble half the detector - for the big shutdown).
ITDM:
- Nothing to report.
XRO:
- Nothing to report.
LAS:
- Not present.
UNSYS:
- Everything is fine.
SPB:
- Nothing to report.
FXE:
- Not present.
MID:
- All fine at MID.
HED:
- Nothing to report.
SCS:
- Experiment goes well so far.
- Hall crew will support SCS this week.
SQS:
- Nothing to report.
SXP:
- Not present. |
389
|
25 Jan 2023, 11:01 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 25.01.2022 |
General Announcement:
- As PRC, Raul V. thanks to CTRL and EEE for the work with the SEPS yesterday.
CTRL:
- New version for bunch alignment monitor devices (for pulse resolved operation). An e-mail will be sent to xo-info list.
- Regarding the issue reported by LAS: Karabo Beckhoff device went in error and a work around solution has been developed and to be implemented to reset the system.
- Issues with SEPS interlocks: PLCs devices went down at HED during tests.
Steffen H. says an interface issue with Karabo happened; interlock settings are protected; yesterday CTRL had to implement a new update and as consequence many PLCs went down.
DA:
- Bring up days going smoothly; few issues found were fixed.
EEE:
- Nerea J. informs that fix for the MDL for IMGS is deployed and shall work.
- SEPS modifications were done by lunch time yesterday. SA1 and SA2 were tested by end of the day. The SA3 SEPS tests will be done on Monday.
VAC:
- Nothing to report.
XPD:
- Hard X-ray PES was recommissioned last week. New Metrocal acquisition did not work; DA will investigate and inform XPD.
DET:
- Bring up days are ongoing.
ITDM:
- E-mail was sent for the dCache maintenance scheduled for next Monday.
XRO:
- Not present.
LAS:
- Issues with stages are under work and to be implemented today.
UNSYS:
- A ZZ in SA2 to replace PS motor in cell 17 took place. The motor was replaced and a few spares are still remaining.
- This or next week Pb shields will be received and ZZ would be required for their installation.
- Tomorrow the alignment of 4mm aperture in SA2 will take place.
SPB:
- Not present.
FXE:
- Nothing to report.
MID:
- Comment to XRO: alignment in tunnel XTD1 in ongoing.
HED:
- Broken pile-up on Monday happened. Steffen H. says that macros can be restarted now.
- Alignment in tunnels by XRO: HED needs some information on activities.
SCS:
- Busy with bring up days at hutch.
SQS:
- Not present. |
193
|
25 Jan 2021, 09:28 |
Arvid Gebhardt | General | Information | Notes XO Integration Meeting 25.01.2021 |
General Announcement:
- Test of automatic switch of power bridge is shifted to Feb.2: this affects all devices connected to orange or green power sockets (no power for few seconds/minute). General e-mail will be sent. Instruments will need to care for equipment which is connected to these sockets. This also affects the E0 level as well as office space in XHQ. Pease plug devices out or re-plug in other sockets.
- The Covid-19 regulations continue valid. Only critical work in the XHEXP1 or tunnel activities shall take place.
- Work on the Soft Mono in XTD10 (SA3) takes place this week. XRO and ME asks everybody to do not move any motors in this device during the whole week.
CTRL:
- New Script to fix label issues in Karabo is ready and will be run today. An e-mail will be sent.
- ITDM and CTRL managed to get updated the “Read the docs”. It runs properly.
DA:
- Not present due to Satellite Workshop.
EEE:
- nothing to report
VAC:
- continuing with tunnel works
XPD:
- Ongoning with few tasks in the tunnel
DET:
- Not present
ITDM:
- nothing to report. Offline GPFS under work today: no Maxwell access during this time.
XRO:
- Not present. Please see general announcements on the Soft Mono.
LAS:
- Error with remote operation on mirrors for SA3/SQS PP-laser is found. A discussion after the meeting will take place between LAS and XO.
UNSYS:
- Nothing to report
SPB:
- Nothing to report
FXE:
- Nothing to add
MID:
- all fine
HED:
- Nothing to report
SCS:
- Nothing to report
SQS:
- Nothing to report |
281
|
24 Nov 2021, 09:56 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 24.11.2021 |
General Announcement:
- Discussions on 3G rules access controlling are ongoing by the Covid task force. However, there is nothing else apart of what was recently announced.
- Next Monday and Tuesday (29-30.11) is dedicated to the ramp-down of the accelerator and photon systems and from Wednesday 01.12 it is the start of the Maintenance period.
CTRL:
- Nothing to report.
DA:
- P. Schmidt informs that instruments noticed early in the morning some issues with calibration.
DA is catching up to make it stable again (it relates to the new measure/state for the expected high data on this week). Please contact DOC if issues can't be solved by staff instrument.
EEE:
- Nothing to report.
VAC:
- Not present.
XPD:
- SA2 Filter interlock is put back (EPS limit of 300 bunches).
DET:
- DSSC cooling system issue (reported at SCS operation e-log): chiller had an alarm due to low level of coolant. The detector was stopped; chiller was refilled and brought back to operation; it seems to be
fine.
DET is investigating why the level had dropped. SCS is also investigating if it relates to a leak or low temperatures. Monica T. is in contact with Jan-Torben D.
ITDM:
- Nothing to report.
XRO:
- Nothing to report.
LAS:
- Nothing to report.
UNSYS:
- Nothing to report.
SPB:
- Confirm that data will be taken also during the night.
FXE:
- Nothing to report; happy with beam performance.
MID:
- Organizing to get a training for the compressor to be able to switch it off when this is not needed.
HED:
- User onsite at the end of the week.
SCS:
- PLC-1 crashed on Monday taking time away for the experiments. A fan went off. Patrick G. says this is recognized that the fan went off and some cooling had to be switched down.
The maintenance of cooling systems is done by TS and it relates to a closed/sealed rack that can't exchange heat.
A solution permitting to spot/alarm when issues with cooling system appears in the racks must be put in place.
SQS:
- Nothing to report. Users are expected this week. |