Technical integration and coordination
SASE1 Status and SASE3 Readiness
|
Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther |
Not logged in |
 |
|
Message ID: 181
Entry time: 25 Nov 2020, 10:14
|
Author: |
Frederik Wolff-Fabris |
Location: |
General |
Severity: |
Information |
Subject: |
Notes XO Integration Meeting 25.11.2020 |
|
|
General Announcement:
- There is no UOM or XO Int. Meeting next Friday 27.11. We will continue with XO Int. Meeting next Monday 30.11.
CTRL:
- Karabo Deployment in FXE takes place today. Schedule for full Karabo deployment was sent to the Readiness mailing list.
- Two SA2/SA3 Beckhoff devices topics will be updated today (5-10 minutes downtime).
DA:
- No issues or announcement to report.
EEE:
- PLC side: tunnel updates to be started with CTRL.
- Change requests also to start today in a couple of instruments.
VAC:
- Not present.
XPD:
- PES/MEA: there are individual tasks ongoing.
DET:
- Nothing major to report. AGIPD intervention is goes faster than planned.
ITDM:
- Offline storage update was done and is available since Tuesday.
- Online cluster update has started: SA1 already available since Tuesday. Today ITDM will finish SA2/SA3. Crosscheck and start DAQ will follow.
XRO:
- Not present.
LAS:
- Nothing special to report.
UNSYS:
- Not present.
SPB:
- AGIPD work is ongoing and fine.
FXE:
- Wille company is installing cables in the hutch.
- Issue with craning on SA3 / SXP activities above FXE area: FXE asks for coordination to avoid interrupting activities.
Gerd W. says it shall not be a problem as crane will be used for few period. Martin K. will inform his phone number for arranging craning times.
MID:
- All fine at MID.
HED:
- All fine at HED.
SCS:
- Shutdown activities ongoing.
- Situation of JJ X-ray will be clarified by SCS staff.
SQS:
- Nothing to report. |