Technical integration and coordination SASE1 Status and SASE3 Readiness
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 328     Entry time: 25 May 2022, 09:25
Author: Frederik Wolff-Fabris 
Location: General 
Severity: Information 
Subject: Notes XO Integration Meeting 25.05.2022 
General Announcement:
-  Reminder that the UOM planned for Friday is taking place apart of the holiday on Thursday.

CTRL:
- Nothing to report.

DA:
- Nothing to report.

EEE:
- Two OCD calls related to FXE setups, but solved and working fine now.

VAC:
- Nothing to report.

XPD:
- ZZ on Monday went fine. Imager is repaired.
- Wolfgang F. planning a ZZ for K-mono in XTD1 but needs to talk with Nerea and XO.

DET:
- Nothing major to report.

ITDM: 
- Not present.

XRO:
- Yesterday there was stability data taken at HED; data to be processed.

LAS:
- Nothing to report.

UNSYS:
- Planned ZZ for next Monday to relocate Pandora.

SPB:
- Issue regarding Hexapod: trying to fix it for the user measurements; DOC, CTRL, EEE informed.

FXE:
- Preparing devices in the experiment hutch.

MID:
- All fine at MID.

HED:
- Nothing to report; not aware of stability measurements.

SCS:
- Experiment is running.

SQS:
- Not present.