SASE1 Status and SASE3 Readiness
|
Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther |
Not logged in |
 |
|
Message ID: 344
Entry time: 25 Jul 2022, 09:14
|
Author: |
Andreas Galler |
Location: |
General |
Severity: |
Information |
Subject: |
Notes XO Integration Meeting 25.07.2022 |
|
|
General Announcement:
CTRL:
- Today "bring up" works at FXE
DA:
- Nothing special to report
EEE:
- PLC team is trying to find solutions for slowness in big loops
VAC:
XPD:
DET:
ITDM:
XRO:
LAS:
UNSYS:
- K- Mono Scan last week
- S. Arbeghyan assisted but new undultaor offsets will only be implemented after Aug 5th
SPB/SFX:
- nothing special to report
- bring up days are very successful
FXE:
MID:
- ITDM please keep MID in the loop with SA2 GPFS updates, as MID plans to save data today
- opening of the beam shutter is an issue
- over the weekend MID was forced to open
HED:
SCS:
SQS:
DRC
PRC
SH
- VAC loops SA1 SA2, don't panic because of slowness
|