Technical integration and coordination SASE1 Status and SASE3 Readiness
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 615     Entry time: 26 May 2025, 09:56
Author: Frederik Wolff-Fabris 
Location: General 
Severity: Information 
Subject: Notes XO Integration Meeting 26.05.2025 
General Announcement:
- A. Galler mentions the V0 was operated by another group after being interlock on Saturday by a vacuum issue in XTD6 while VAC-OCD was investigating the issue. 
Operation by anyone else has to be prevented in future and only VAC staff shall operate it.

CTRL:
- Issue at MID GUI server being investigated.

DA:
- Nothing major to report.

EEE:
- Nothing to report.

VAC:
- Issue with SA2 Saturday handled by VAC-OCD and PRC. 
- Several mails came from Karabo issue with vacuum pumps in SA1 - to be forwarded to CTRL and discussed.

XPD:
- Nothing to report.

DET:
- Nothing to report.

ITDM: 
- Not present.

XRO:
- Nothing major to be reported.

LAS:
- Not present.

UNSYS:
- Nothing to report.

SPB:
- Continue with measurements; some difficulties with sample synchronization; nothing else to report.

FXE:
- Nothing to report.

MID:
- Nothing to report apart of the mentioned vacuum issue.

HED:
- Nothing to report.

SCS:
- Nothing to report.

SQS:
- Not present.

SXP:
- Not present.