Technical integration and coordination SASE1 Status and SASE3 Readiness
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther, Page 32 of 32  Not logged in ELOG logo
ID Date Author Location Severitydown Subject Text Attachments
  625   02 Jul 2025, 10:03 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 02.07.2025General Announcement:
- M. Doering announces on the LIMP-25: 
1. Old's AIBS removal is starting already
  
  626   07 Jul 2025, 09:44 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 07.07.2025General Announcement:
- Martin Doering announces: 
1. Karabo will be stopped this week accordingly
  
  627   09 Jul 2025, 08:32 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 09.07.2025General Announcement:
- LIMP-25 update for this week: elevators
were to be maintained this week but it is
  
  628   14 Jul 2025, 09:59 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 14.07.2025General Announcement:
- On Crane activities: 
1. Next craning activity from truck bay to
  
  629   16 Jul 2025, 09:51 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 16.07.2025General Announcement:

- Martin Doering informs on the LIMP-25 on
  
  630   21 Jul 2025, 09:54 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 21.07.2025General Announcement:
- M. Doering informs on the Limp-25 / current
week: 
  
  631   23 Jul 2025, 09:25 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 23.07.2025General Announcement:
- Martin Doering informs on the LIMP-25:
  
  Draft   30 Mar 2020, 08:57 Andreas Galler   CTRL:


Broker Pile Up in 4 topics
over the weekend

LAS affected
  