Group Selection Page HELP DOC Controls Group Data Analysis Group ITDM WP76 DET Vacuum XRO EEE WP78 WP74 FXE SCS SPB MID HED SQS SXP Sample Environment Photon Commissioning Team Operation PSPO XO TS
Technical integration and coordination SASE1 Status and SASE3 Readiness
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther, Page 28 of 29  Not logged in ELOG logo
ID Date Authordown Location Severity Subject
  63   03 Jul 2019, 10:18 Adriano ViolanteGeneralInformationMinutes of the Technical integration meeting 03.07.19

XO

  • In SASE3 the apertures of the GATT have to be realigned. The upstream apertures have been alreadz realigned. The downstream ones will be probablz realigned tomorrow. If not succesfull some restrictions of the operation have to be evaluated.

FXE

  • Loops update has to be coordinated between EEE and FXE. No feedback received from EEE. AG will remind TKorsh. 

SPB/SFX

  • Loop updates continue.
  • Loop 8 will be commissioned on monday with EEE.

SCS

SQS

  • Aerosol will be commissioned next week. EEE waiting for the precise dates.

​​MID

HED

  • Suffered overhead due to the power cut occured on Monday.

Optical lasers

VAC

  • All XTDs apart from XTD 6 and 9 will be closed on Monday
  • XTD6/9 will be stay opened until Tuesday. Confirmation will be given during the dispatch meeting on Monday.
  • XTD1,2 ready for beam formt he VAC point of view
  • XTD6 -  mono works ongoing.
  • XTD9 -  Maybe worls planned by FXE on the gratings. To be double checked whether it is feasible.

XRO

XPD

DET

EEE

  • Electrical safety regulation. From the beginning of July the new electrical safety regulation is supposed to be in place. According to this regulation the work at the back of the racks in the XHEXP1 and in the entire racks in the tunnels can only be done by certified EFK (Elektrofachkraefte) or by EUPs with an additional training. The additional training can only be provided after summer. The nomination of XFEL EFKs is suffering a delay due to the fact that is not clear who should nominate them (TS, UBR, HR?).  PG reported the problem and also the fact that no official statements were made in the past concerning the topic. THaas is trying to clarify the status, and come up with a statement and proposal in the Operations meeting. ==> there was no meeting on Friday. Still pending.

CAS

ITDM

  • Additional CAT connections planned for SQS, FXE, SCS were installed and approved by ITDM.
  • During the maiinenance of the cooling water system the doors of the balcony rooms and racks were left open to cool down the electronics. Although in the past that worked, it is no longer the case. ITDM will discuss with MKK2 how to make the cooling of the balcony rooms more efficient during planned mainenance of the cooling water system or in case of emergency.

SRP

TS

AoB

On Monday Torsten Schoen informed AV that the power went off in MID and HED experiment hutch because of the radiation interlock test. This was due to the fact that according to the original plan (circulated and approved at the beginning of May), the SASE1 test was supposed to happen on Monday and the SASE2 test the day after. On monday, SASE1 system was accordingly bridged to avoid issues with the power. A last minute change in the plan was agreed between MID and MPS but the info unfortunately did not reach Torsten, hence the issue. Also, nobody from SRP, D3, HED was timely informed. 

There was obviously a lack of communication that has to be improved. AV will write a report and circulate it to the involved people for review and provide it to the MB.

 

  64   05 Jul 2019, 09:54 Adriano ViolanteGeneralInformationStatus report after dispatch meeting 09.00

XO

FXE

  • Loops update has to be coordinated between EEE and FXE. No feedback received from EEE. AG will remind TKorsh. ==> Nothing was received by EEE.

SPB/SFX

SCS

SQS

​​MID

  • Loops required are all up and running.
  • RSchaffer is working on the SDL coordinated motion simulation.

HED

Optical lasers

VAC

  • SASE1, 3 and MID ready for beam
  • HED mono is leaking. Fix hopefully today.
  • For the monos in SASE2 a loop update is required before switching the power supplies on. EEE will tray to do it today.

XRO

  • An encoder for the mirrors in SASE1 shows an error. This is known. XRO will notify EEE if they want to have special actions taken.

XPD

DET

  • Karabo 2.5.0 update OK.

EEE

CAS

  • Karabo 2.5.0 will be deployed in HED and SASE1. So far no major issues in the other beamlines.

ITDM

SRP

TS

AoB

 

 

  65   08 Jul 2019, 10:25 Adriano ViolanteGeneralInformationStatus report after dispatch meeting 09.30

XO

FXE

  • Loops update has to be coordinated between EEE and FXE. No feedback received from EEE. AG will remind TKorsh. ==> TK will discuss the topic in the FXe group meeting today and contact EEE.

SPB/SFX

SCS

SQS

​​MID

  • The VAC interlock tests performed on Friday showed some unexpected behavior of the system. Change request is being prepared to fix these (minor) issues.
  • Quadrant motion tests foreseen for this week

HED

  • Tunnel installations have been completed
  • VAC final leak tests today
  • High power laser being aligned to bring beam into the HED experiment enclosure
  • In the optics hutch a new grating is being installed.

 

Optical lasers

VAC

  • All tunnel closed apart from XTD9 and 6

XRO

  • An encoder for the mirrors in SASE1 shows an error. This is known. XRO will notify EEE if they want to have special actions taken.

XPD

DET

  • Karabo 2.5.0 update OK. Update of the calibration system still has to happen for all the detectors apart from DSSC

EEE

CAS

  • On Friday many requests were sent to CAS about final checks needed for commissioning of the components. Priorities have to be set since CAS does not have the resources to deal with all of them.
  • Data loggers for HED will be brought online today.
  • In the 2.5.0 the MPODs were moved to the new configuration. MPC and PES have also been updated. XPD knows that in the standard configuration 0V is set as voltage target since the old values probably were not making sense anymore. A summary/update mail will be sent by CY to readiness@xfel.eu today.

ITDM

SRP

TS

AoB

  66   10 Jul 2019, 16:16 Adriano ViolanteGeneralInformationMinutes of the Technical integration meeting 10.07.19

XO

  • In SASE3 the apertures of the GATT have to be realigned. The upstream apertures have been alreadz realigned. The downstream ones will be probablz realigned tomorrow. If not succesfull some restrictions of the operation have to be evaluated. ==> Done.
  • Turnstile issue: 2 days ago the hall was not accessible for some hours because of non functioning turnstiles. The problem was a change in the desy firewall configuration that lead to the transponders system not working. 

FXE

  • Loops update has to be coordinated between EEE and FXE. No feedback received from EEE. AG will remind TKorsh. Still pending.

SPB/SFX

  • No major issues
  • BB is coordinating the loops update with SPB/SFX

SCS

  • No Major issues
  • Loop1 has been updated

SQS

  • Aerosol will be commissioned next week. EEE waiting for the precise dates.==> Still waiting.

​​MID

  • XRO will agree with MID which functionalities of the attenuators in XTD1 have to be tested. 'to do list' will be issued. XRO will put the results in the operation logbook. If XRO will not make it to test everything, MID will be informed and will help.
  • XTD 6 will be closed tomorrow after lunch. CY points out that there is a list of issues to be fixed in XTD6 (e.g. motors not working) and many people in CAS are ill, hence, not available, NJ checks with MS and CY sends the list to EEE.
  • By the end of the week MID should send the requirements for the vacuum interlock to EEE.

HED

  • The monochromator can be cooled down now. The vacuul is still not optimal but the device is operable,.
  • Today loop 3 will be updated.

Optical lasers

VAC

XRO

  • M1 in SASE2 and 1 will be commissioned this week end. New positions will be found and written diwn in the logbook. Difference of some mm with respect to the old positions is expected.

XPD

DET

  • Tests with Karabo 2.5.0 OK.

EEE

  • Electrical safety regulation. From the beginning of July the new electrical safety regulation is supposed to be in place. According to this regulation the work at the back of the racks in the XHEXP1 and in the entire racks in the tunnels can only be done by certified EFK (Elektrofachkraefte) or by EUPs with an additional training. The additional training can only be provided after summer. The nomination of XFEL EFKs is suffering a delay due to the fact that is not clear who should nominate them (TS, UBR, HR?).  PG reported the problem and also the fact that no official statements were made in the past concerning the topic. THaas is trying to clarify the status, and come up with a statement and proposal in the Operations meeting. ==> there was no meeting on Friday. Still pending. ==> implementation of the electrical safety regulation has been postponed to the end of the year (mail from SRP).

CAS

  • Deployment of Karabo 2.5.0 has been completed

ITDM

SRP

TS

AoB

 

 

  67   15 Jul 2019, 10:01 Adriano ViolanteGeneralInformationStatus report after dispatch meeting 09.30

XO

FXE

SPB/SFX

  • After the loops update the MPS signals have to be tested. The plan is to start today. (AS+EEE support is required)

SCS

SQS

​​MID

  • The VAC interlock tests performed on Friday showed some unexpected behavior of the system. ==> have been almost 100% fixed.
  • hexapods can be controlled by Karabo now.
  • Servo motor drivers are now in the EEE lab and would be needed asap in MID to start commissioning. Could happen this week already.

HED

  • High power laser being aligned to bring beam into the HED experiment enclosure. ==> It was not possible to bring the laser into the hutch apparently because of some communication problems with safety. 
  • Mirror s could not be aligned for HED during the WE because of a crash of the MOV loop. This was due to a NaN delivered to the plc instead of a motor position. This problem has been fixed with the last loop update, which was not implemented in the XTD6 MOV loop yet. It will be discussed with EEE, MDommach and L.Samoylova whether to perform the update now.
  • EEE should return the nanocube controllers as soon as possible for commissioning.
  • Hexapods remote controls needed.

 

Optical lasers

  • the status of the SASE1 PP laser is not yet clear.

VAC

XRO

XPD

DET

  • Karabo 2.5.0 update OK. 
  • Online calibration tools will be available for MID and SPB/SFX starting from tomorrow.

EEE

CAS

  • Not a number values  can be filtered by karabo. AS will have a look at that. 

ITDM

SRP

TS

AoB

  • Mail has been sento to the STGL and readiness mailing list. Deadline is the 2.08. for the delivery of the info to XO/PM
  68   17 Jul 2019, 10:05 Adriano ViolanteGeneralInformationMinutes of the Technical integration meeting 17.07.19

XO

FXE

SPB/SFX

  • 2 screens require the intervention of EEE today. Being agreed offline.

SCS

SQS

​​MID

  • XRO will agree with MID which functionalities of the attenuators in XTD1 have to be tested. 'to do list' will be issued. XRO will put the results in the operation logbook. If XRO will not make it to test everything, MID will be informed and will help. ==> Ongoing
  • M2 bender: motor issue. HSinn is following it up.
  • By the end of the week MID should send the requirements for the vacuum interlock to EEE. ==> tests are ongoing. AS will organize a meeting with CAS, VAC and EEE to define a test procedure to be followed by the instruments when testing the vacuum interlocks.

HED

  • Lase is fully integrated in Karabo now.
  • Yesterday the loop 6 was updated. There were issue with pumps switching off and causing overhead for HED. PG will investigate why this happened...

Optical lasers

  • SA1 PP laser: the damage is worst than expected. More info to come.

​VAC

XRO

  • M1 in SASE2 and 1 will be commissioned this week end. New positions will be found and written diwn in the logbook. Difference of some mm with respect to the old positions is expected.

XPD

DET

​EEE

CAS

  • Karabo 2.5.1. hotfix is being prepared (Fixing 2 bugs in the framework and several GUI issues).
  • Tomorrow at 14:00 there will be a test of the pulse on demand feature (conditional triggers) in FXE. (AS/BF)

​ITDM

​SRP

TS

AoB

  • People are reminded to send XO/PM the shutdown activities by the 2.08.
  69   19 Jul 2019, 10:48 Adriano ViolanteGeneralInformationStatus report after dispatch meeting 09.00

XO

FXE

SPB/SFX

SCS

SQS

MID

  • Vacuum interlock tests should be done on Monday.. 
  • CY and RS are working on the nanocube scan device, also operated with an external trigger signal. CAS/MID/EEE technical discussions happen offine.

HED

  • main loop has to be updated on Monday in order to ensure proper implementation of the interlock signals.
  • Hexapod controls are needed: KS wrote an EEE ticket. EEE will coordinate with KS and M.Makita. 

Optical lasers

VAC

XRO

XPD

DET

EEE

  • SQS smaract motors commissioning being supported
  • There is an issue in the PLC firmware for the scroll pumps. Update needed. Will be scheduled and coordinated with the intruments.

CAS

ITDM

AoB

  70   22 Jul 2019, 12:42 Adriano ViolanteGeneralInformationStatus report after dispatch meeting 09.30

XO

FXE

  • DAQ issue reported (data not being recorded). Comment from ITDM is that this was a miro issue solved with the re initialization of the proposal. More details will eb discussed offline.
  • Contact person for EEE is now Timo Korsh (deputy is Paul Frankenberger)

SPB/SFX

SCS

SQS

MID

  • Vacuum interlock tests have been (almost completely) performed
  • ITDM OCD was quite busy last week because of some DAQ instabilities. MID/ITDM to discuss offline.
  • CY and RS are working on the nanocube scan device, BF needed today at 13:00 for futher trigger tests.

HED

  • Commissioning ongoing.
  • Problems with data migration: to be discussed with ITDM
  • Epix DAQ issue: solved restarting the server.

Optical lasers

VAC

XRO

XPD

DET

EEE

  • Some issues were reported from NK about motors in SASE1 M2. EEE will need to have a look.
  • Some OCD calls concerning errors from encoders (due to cabling issues)
  • Conditional trigger test in SASE1 was successful.

CAS

ITDM

  • Calibration server for mid has memory problems and needs to be replaced. Calibration pipeline has to be moved to a different servers. Will be discussed offline with MID.
  • SASE3 data migration issues: has to be checked by ITDM
  •  

AoB

  71   24 Jul 2019, 10:54 Adriano ViolanteGeneralInformationMinutes of the Technical integration meeting 24.07.19

XO

FXE

  • DAQ issue reported (data not being recorded). Comment from ITDM is that this was a miro issue solved with the re initialization of the proposal. More details will eb discussed offline.==> issue fixed (it was due to a misconfiguration in the DAQ server)

SPB/SFX

  • Loop 12 has to be updated
  • SASE1 M3 issues with the pitch motor lead to FXE losing beamtime. EEE to follow it up.

SCS

SQS

MID

  • By the end of the week MID should send the requirements for the vacuum interlock to EEE. ==> tests are ongoing. AS will organize a meeting with CAS, VAC and EEE to define a test procedure to be followed by the instruments when testing the vacuum interlocks.
  • Calibration server for mid has memory problems and needs to be replaced. Calibration pipeline has to be moved to a different servers. Will be discussed offline with MID.==>

HED

  • Yesterday the loop 6 was updated. There were issue with pumps switching off and causing overhead for HED. PG will investigate why this happened... ==> the procedure was clear to EEE and foresaw the switching off of the pumps at some point. This was supposed to be clear also to the instruments buy clearly it was not the case. 
  • Nanocube PLC has been integrated.

Optical lasers

VAC

XRO

XPD

DET

EEE

  • Crash of PLCs because of not a number values. The fix on the PLC side requires the update of the loops framework and can be done only in the August shutdown. By the end of the week a filtering tool will be availbale in Karabo.

CAS

  • Karabo 2.5.1. hotfix is being prepared (Fixing 2 bugs in the framework and several GUI issues). ==> Done
  • Tomorrow at 14:00 there will be a test of the pulse on demand feature (conditional triggers) in FXE. (AS/BF) ==> Done

ITDM

  • Calibration server for mid has memory problems and needs to be replaced. Calibration pipeline has to be moved to a different servers. Will be discussed offline with MID.==> It is ongoing. In general this issue led to a loss of beamtime for MID. Alessandro suggests that in case of hardware failure there should be a joint ITDM-CAS decision/effort on what to do.
  • Data migration: it was slow in the past days due to some script not being used for safety reasons. This is being fixed. Hovewer, due to the queue of old data to be migrated it will take some more time until full performance will be reached. 

SRP

TS

AoB

  72   26 Jul 2019, 14:07 Adriano ViolanteGeneralInformationStatus report after dispatch meeting 09.00

XO

FXE

SPB/SFX

SCS

SQS

MID

  • Nanocube being used with the scan tool. Seems fine. Some test of the velocity scan has to be done (CY will coordinated with MID)
  • Exapods have been integrated. Some feedback from TF is needed for EEE to complete the hand over.

HED

  • Loop 6 will be updated next week. KS will talk to HED and EEE to make sure vacuum systems are safe during the update.

Optical lasers

VAC

XRO

XPD

DET

EEE

  • Crash of PLCs because of not a number values. The fix on the PLC side requires the update of the loops framework and can be done only in the August shutdown. By the end of the week a filtering tool will be availbale in Karabo. ==> Filter is ready and can be deployed on Monday.

CAS

ITDM

  • Some issues with the GPFS will results in slowness of the system. This is being investigated and probably already fixed today.

SRP

TS

AoB

  73   29 Jul 2019, 10:16 Adriano ViolanteGeneralInformationStatus report after dispatch meeting 09.30

XO

FXE

SPB/SFX

SCS

SQS

MID

  • Nanocube being used with the scan tool. 
  • Cleanup and preparation for the next experiments ongoing
  • VAC interlock has been tested due to an accidental trigering of a vacuum valve. Some dcetails will need to be fixed.

HED

  • Loop 6 will be updated as soonas the new interlock definitions will be available. KS will talk to HED and EEE to make sure vacuum systems are safe during the update.
  • Loop 7 and 9 will be updated today.

Optical lasers

VAC

XRO

XPD

DET

EEE

 

CAS

  • Crash of PLCs because of not a number values. Karabo client is now available to filer NaN values.
  • 2.5.1. available. FIxes a bug for cameras (restricted ROI), and GUI machines. 

ITDM

  • Some issues with the GPFS will results in slowness of the system. Has been fixed.
  • Cleanup of the GPFS during the weekend. Petabytes of data have been recorded. This may reduce the time in which the data is available on the GPFS for the next user runs. 
  • Xfel gateway will be shut down for a short time today around lunchtime. JS will send a mail to readiness with the precise time.

SRP

TS

AoB

  74   31 Jul 2019, 10:46 Adriano ViolanteGeneralInformationMinutes of the Technical integration meeting 31.07.19

XO

FXE

SPB/SFX

  • Loop 12 has to be updated ==> Done.
  • SASE1 M3 issues with the pitch motor lead to FXE losing beamtime. EEE to follow it up. ==> Basically fixed. Some remaining issues will be fixed during the shutdown week in August.
  • Some issues reading the encoders of the JJ XRay CSLIT. EEE checks whether similar issues are also present in other instruments.

SCS

SQS

  • Commissioning of smaract stages ongoing.

MID

  • By the end of the week MID should send the requirements for the vacuum interlock to EEE. ==> tests are ongoing. AS will organize a meeting with CAS, VAC and EEE to define a test procedure to be followed by the instruments when testing the vacuum interlocks. ==> to be done.

HED

  • New update of Loop 6 will be done propably today after new interlock definitions have been delivered.
  • Hexapod: Loop 9 has been updated. Loop 7 to follow.

Optical lasers

VAC

XRO

XPD

DET

EEE

  • Crash of PLCs because of not a number values. The fix on the PLC side requires the update of the loops framework and can be done only in the August shutdown. By the end of the week a filtering tool will be availbale in Karabo.==> Karabo client has been deployed in the tunnels and FXE. The other instruments will get it during the August shutdown.
  • XPD reported some issues with digitizers for MCPs. It should be fixed already by now.

CAS

  • CAS received host alerts regarding sa2-br-sys-con-1, sa2-br-sys-con-2, sa2-br-sys-con-5 resources usage. To avoid the worst issues during experiments, we will do maintenance on these machines today from 12:00 to 14:00.
  • CAS/SQS working on karabo scenes to display the LaserMet laser isnterlock status.

ITDM

SRP

TS

AoB

  • RBean reported that by the end of the week a macro will be run by HSinn to decouple machine interlocks in SASE1 and SASE3. For more details AGaller should be addressed.
  75   02 Aug 2019, 09:10 Adriano ViolanteGeneralInformationInfo on dispatch meeting 09.00

The meeting did not take place since only EEE was attending.

  76   05 Aug 2019, 10:19 Adriano ViolanteGeneralInformationStatus report after dispatch meeting 09.30

XO

FXE

  • Photon3 detector has been fully implemented.

SPB/SFX

  • Some issues reading the encoders of the JJ XRay CSLIT. EEE checks whether similar issues are also present in other instruments. ==> has been fixed.

SCS

SQS

MID

  • 2 Motors have to be checked: Rotation of the hexapod and the y motion of the AUX3 are needed for next week.
  • DPS turbo pump 3 behaving strangely. EEE to have a look
  • Loop 7 has to be updated. Offline discussion MS/JH

HED

  • Grating holder motion HED OPT. Motors to be commissioned. EEE required
  • Cable needed for the Jungfrau timing signal. KS BF to discuss offline.

Optical lasers

VAC

XRO

XPD

DET

EEE

CAS

ITDM

SRP

TS

AoB

 

  77   07 Aug 2019, 11:55 Adriano ViolanteGeneralInformationMinutes of the Technical integration meeting 07.08.2019

XO

The accelerator is now working at 2.25 MHz. Kicker can be used. DET informs that for repetition rates different to the ones been used so far the calibration can be significatively different.

FXE

SPB/SFX

  • Hexapods are being integrated. 
  • Master loop has to be updated. EEE to agree offline with SPB/SFX

SCS

SQS

  • Commissioning of smaract stages done. 1 encoder cable is being checked (seems a problem of definition).

MID

  • DPS turbo pump issue. A software workaround exists. The problem is that the used controller has not been commissioned firmwarewise before. This is not a showstopper and wil be addressed later. 

HED

Optical lasers

VAC

XRO

XPD

DET

  • Offline calibration update has been performed in SCS. Tests are foreseen for today.

EEE

  • A new karabo device updating the digitizers with the beam parameters in real time has been successfully tested last week.

CAS

  • 2.6.0. being prepared.

ITDM

SRP

TS

AoB

The dispatch/tech. integration meetings will be re organized in the near future. Slides are attached.

Attachment 1: Technical_Integration_Meeting_07.08.2019_-_Copy_(4).pptx
  80   19 Aug 2019, 11:11 Adriano ViolanteGeneralInformationReport after dispatch meeting 09.30

General

  • Still recovering from the power loss occured on Saturday (The primary line was affected). In the hall the power was down for about 30 minutes, while in the tunnels it seems it was only a glitch.
  • It is clear that it was a major system failure. Optimization of procedures and responsibility will be discussed within the DOD.

FXE

  • Issues with the acquisition of images fromt he Jungfrau detector with the last version of Karabo. DET to follow it up offline.
  • There are concerns about the replacement of the simple motor with the MC2 library, in particular about whether all functionalities will still be available (e.g. step-up/down). According to EEE this should be okay. CAS has already release the new library for testing. ==> will be done in thw WS for FXE, later for th tunnels and the other instruments.
  • Remote control of the radiation shutter dows not work. IP of the new computer is needed. Will be solved offline between FXE, CAS and ITDM.

SPB/SFX

  • Hexapods are being integrated. ==> This was rescheduled due to the issues with hexapods at HED and MID. Currently, there is no dire need to integrate the SPB/SFX hexapod, it can be run from TwinCAT. ==> postponed.

SCS

  • Support from EEE is needed to make sure motors needed for the user experiments in 2 weeks are actually working (e.g. Elmo).
  • If issues with the pulse IDs occur, AS, PG and BF are to be contacted (part of the trigger board)

SQS

MID

  • DPS turbo pump issue. A software workaround exists. The problem is that the used controller has not been commissioned firmwarewise before. This is not a showstopper and wil be addressed later. ==> The cabling is done differently. EEE is testing the device + firmware. ==> Ongoing
  • Vacuum interlock worked fine following the power failure.
  • Recovering from the power failure. Definition of check list in progress.

HED

  • Recovering of Loop 9 is ongoing (motors fpor Mono1 and 2). EEE is supporting.
  • Jungfrau has been fully recovered. Epix in progress.

Optical lasers

VAC

XRO

  • There was an issue with a drift of the HED mirror. As a consequence, VAC and XRO have switched of the mirror cooling. HED and MID should report about the change of the situation. ==> still exchange of information needed.

XPD

DET

  • In general, it seems that no major issues occured after the power loss. 
  • In FXE the power supply and the chiller for the LPD are connected on different power lines and this lead to the fact that, after the power came back, the power supply was back on while the chiller was off. This should be avoided anc hecked by the instruments.

EEE

CAS

  • 2.6.0. being prepared. ==> Sneak peak was deployed in SPB/SFX. Actual deployment datas can be found in the Shutdown planing, will be discussed in the chapters and with the SASE responsibles. ==> tests with ITDM being planned.

ITDM

SRP

TS

AoB

  81   21 Aug 2019, 11:15 Adriano ViolanteGeneralInformationMinutes of the Technical integration meeting 21.08.19

XO

  • A review of the procedures in case of power failure is in progress. Thanks to everybody for the efforts during the last days.

FXE

  • Remote control of the radiation shutter dows not work. IP of the new computer is needed. Will be solved offline between FXE, CAS and ITDM. ==> Done for FXE. Small issues being fixed for MID.

SPB/SFX

SCS

  • Support from EEE is needed to make sure motors needed for the user experiments in 2 weeks are actually working (e.g. Elmo). ==> fine tuning of the support plan will be made between SCS and EEE.

SQS

MID

  • DPS turbo pump issue. A software workaround exists. The problem is that the used controller has not been commissioned firmwarewise before. This is not a showstopper and wil be addressed later. ==> The cabling is done differently. EEE is testing the device + firmware. ==> Ongoing

HED

  • The smaract stages with the current firmware can be either driven fast or precise. EEE will discuss with the isntruments involved how to modify the stages implementation to be able to have both options available.

Optical lasers

VAC

XRO

  • There was an issue with a drift of the HED mirror. As a consequence, VAC and XRO have switched of the mirror cooling. HED and MID should report about the change of the situation. ==> still exchange of information needed. ==> Measurements from MID have been received. HED will do the same. Investigation of the problem will happen next week (shutdown)

XPD

DET

  • Calibration database haes been migrated. If problems are experienced please send a ticket to DET.

EEE

  • Loop updates in the tunnels and instruments being scheduled together with the involved groups.

CAS

  • 2.6.1. being prepared.  Deployment plan is still valid.

ITDM

SRP

TS

AoB

  82   26 Aug 2019, 09:52 Adriano ViolanteGeneralInformationReport after dispatch meeting 09.30

XO

  • Today a test of the fire alarm system will take place. Mail has been circulated by SRP.
  • From next monday the dispatch meeting time slot will change to 8.30. Chair will be with XO.

FXE

  • Leak in the LPD cooling system has been found. DET on it.
  • Laser went out of synch several time during the last weeks. Being addressed with CAS.
  • Mono middle layer is not working properly. Calibration parameters are not reloaded correctly after restart. CAS on it.

SPB/SFX

  • CSLITS - discrepancies between the behavior of normal motors vs MC2 motors. CAS on it.

SCS

SQS

MID

  • During last WE big issues with the AGIPD were experienced. Probably calibration pipeline related. DET on it.

HED

  • Hirex 2 commissionig ongoing.
  • Mono commissioning - cameras were found not to work. CAS/EEE to check.
  • Access to the experiment hutches will be restricted this week due to laser shots tests.

Optical lasers

VAC

XRO

  • SASE1 FEL imager was damaged following the last power cuts and EPS/MPS issues. Will be replaced by Thursday.

XPD

DET

EEE

CAS

  • 2.6.1. ready to be deployed. Deployment schedule has been agreed with individual groups.

ITDM

SRP

TS

AoB

  83   28 Aug 2019, 10:33 Adriano ViolanteGeneralInformationMinutes of the Technical integration meeting 28.08.2019

XO

FXE

  • Leak in the LPD cooling system has been found. DET on it. Ongoing
  • Laser went out of synch several time during the last weeks. Being addressed with the synch. group.
  • Mono middle layer is not working properly. Calibration parameters are not reloaded correctly after restart. CAS on it. Ongoing.
  • SA1 MOV loop has been updated. Minor issues with the CRL encoders are being addressed.

SPB/SFX

  • CSLITS - discrepancies between the behavior of normal motors vs MC2 motors. CAS on it. ==> will be fixed once Karabo 2.6.1. has been deployed.

SCS

SQS

MID

  • During last WE big issues with the AGIPD were experienced. Probably calibration pipeline related. DET on it.
  • Laser hutch A.07 is not supposed to be accessible in the next weeks because of the laser operation. SRP points out that they are not sure whether the interlocks are properly working and active. To be clarified offline between MID, HED and SRP.

HED

  • Access to the experiment hutch, Optics and Rackroom will be restricted this week due to laser shots tests.

Optical lasers

VAC

XRO

  • Change of middle layer devices for the attenuator in SASE2 will be discussed offline with CAS

XPD

DET

EEE

  • Loops are being updated in coordination with the instruments.

CAS

  • 2.6.1. ready to be deployed. Deployment schedule has been agreed with individual groups.

ITDM

  • Maxwell cluster maintenance on 2-3. 09.
  • Control PCs wil be deployed during the shutdown week
  • Claoud service (DESY platform) will be put into operation. An official announcement will details will follow.

SRP

TS

AoB

  84   12 Nov 2019, 09:49 Adriano ViolanteGeneralInformationStatus report after dispatch meeting 09.00

FXE

  • FXE – radiation tests and LPD tests planned for this week. Small issues with the scan tools are being addressed.

SPB/SFX

SCS

SQS

MID

  • First measurements with the pulsed magnet have been performed last week with the power supply installed temporarily in the experiment hutch. This week only the cryostat is going to be used. Next step will be to bring the magnet power supply in the rackroom to comply with the electrical safety requirements. MID will follow it up.

 

HED

Pptical lasers

VAC

XRO

XPD

DET

EEE

Controls

  • Many IT/controls services will be down in KW48 (shutdown)

ITDM

  • Server 13 for SCS will be down today.
  • General remark from Controls and ITDM: devices and functionalities (e.g. new devices in the DAQ, data aggregators…) that have not been tested during the normal working ours should not be used during shifts in the weekend or during the night. This creates a huge and evitable overhead for the people in OCD.

SRP

TS

AoB

ELOG V3.1.4-7c3fd00