Group Selection Page HELP Controls Group ITDM DET Vacuum WP78 FXE SPB HED SQS SXP Sample Environment PSPO XO TS Migrated2Zulip Archived2GitlabPages Archived2PDF MigratedByGroup
SCS Photon Commissioning Team XRO DOC WP74 MID XO_mig XO_Operation SQS Migrated2Zulip
Technical integration and coordination
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 504     Entry time: 08 Apr 2024, 09:27
Author: Andreas Galler 
Location: General 
Severity: Information 
Subject: Notes XO Integration Meeting 08.04.2024 

General Announcement:

  •  

CTRL:

  • Nothing major

DA:

  • nothing major

EEE:

  • nothing major

VAC:

  •  

XPD:

  • everything fine, maybe ZZ tomorrow

DET:

  • nothing major

ITDM: 

  • short interuption of DAQ Switch for SA1 tomorrow
    • in coordination with CTRL 
  • GPFS clients on all PClayer servers planned for tomorrow

XRO:

  •  XTD1 ATT repair planned for next Monday

LAS:

  • not present

UNSYS: 

  • everything fine

SPB/SFX:

  • Nothing major

FXE:

  • train issue with JUNGFRAU

MID:

  • nothing major

HED:

  • nothing major

SCS:

  • nothing major

SQS:

  • not present

SXP:

  • not present

DRC

  • Broker issue on Friday
    • SA2 topic restarted

PRC

 

AOB:

  • XPD is planning for a ZZ in SA2 tomorrow, UNSYS wishes for ZZ in SA3 --> both topics to be discussed in the following RC meeting
ELOG V3.1.4-7c3fd00