Technical integration and coordination SASE1 Status and SASE3 Readiness
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 504     Entry time: 08 Apr 2024, 09:27
Author: Andreas Galler 
Location: General 
Severity: Information 
Subject: Notes XO Integration Meeting 08.04.2024 

General Announcement:

  •  

CTRL:

  • Nothing major

DA:

  • nothing major

EEE:

  • nothing major

VAC:

  •  

XPD:

  • everything fine, maybe ZZ tomorrow

DET:

  • nothing major

ITDM: 

  • short interuption of DAQ Switch for SA1 tomorrow
    • in coordination with CTRL 
  • GPFS clients on all PClayer servers planned for tomorrow

XRO:

  •  XTD1 ATT repair planned for next Monday

LAS:

  • not present

UNSYS: 

  • everything fine

SPB/SFX:

  • Nothing major

FXE:

  • train issue with JUNGFRAU

MID:

  • nothing major

HED:

  • nothing major

SCS:

  • nothing major

SQS:

  • not present

SXP:

  • not present

DRC

  • Broker issue on Friday
    • SA2 topic restarted

PRC

 

AOB:

  • XPD is planning for a ZZ in SA2 tomorrow, UNSYS wishes for ZZ in SA3 --> both topics to be discussed in the following RC meeting