Technical integration and coordination SASE1 Status and SASE3 Readiness
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 534     Entry time: 29 Jul 2024, 09:27
Author: Andreas Galler 
Location: General 
Severity: Information 
Subject: Notes XO Integration Meeting 29.07.2024 

General Announcement:

CTRL:
- nothing

DA:
- nothing

EEE:
- nothing

VAC:
- nothing

XPD:
- nothing

DET:
- AGIPD comm. data taken

ITDM: 
- nothing

XRO:
- attenuator arm 5 is stuck XTD2
 - not yet clear if it is a hardware issue.
 - limit sitches are stuck --> EEE can move the attenuator 

LAS:
- SA1: 

UNSYS:
- SA3 cell 11, ZZ needed
 -

SPB:
- attenuator issue

FXE:
- not present

MID:
- damage in the fastADC channel
- calibration pipeline crashed ...

HED:
- all good 

SCS:
- PLC issues
 - parameters lost on PLC level
 - some motors don't work correctly
 - ELMO motors often go into error states 

SQS:
- not present

SXP:
- not present