Group Selection Page HELP DOC Controls Group Data Analysis Group ITDM WP76 DET Vacuum XRO EEE WP78 WP74 FXE SCS SPB MID HED SQS SXP Sample Environment Photon Commissioning Team Operation PSPO XO TS
Technical integration and coordination SASE1 Status and SASE3 Readiness
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 458     Entry time: 09 Oct 2023, 09:23
Author: Andreas Galler 
Location: General 
Severity: Information 
Subject: Notes XO Integration Meeting 09.10.2023 

General Announcement:

  •  

CTRL:

  • nothing major 

DA:

  • nothing major 

EEE:

  • nothing major

VAC:

  • nothing major

XPD:

  • nothing
    •  

DET:

  • nothing

ITDM: 

  •  

XRO:

  • miror setup tuned for grazing incidence with high photon energy.
  • higher backlash at M6, XRO is monitoring this.

LAS:

  • SA2 treacy compressor  smaract stage not operational --> EEE informed
  • SA3 AMPHOS still suffering from low puse energy

UNSYS: 

  • gap scan
  •  

SPB/SFX:

  • nothing major

FXE:

  • nothing major

MID:

  • nothing to report

HED:

  • nothing to report

SCS:

  • no issues

SQS:

  • uTCA in rack room --> EEE will be informed
    • crate power cycled

SXP:

  • M6 backlash

DRC

  •  

PRC

  •  
ELOG V3.1.4-7c3fd00