Message ID: 458     Entry time: 09 Oct 2023, 09:23
Author: Andreas Galler 
Location: General 
Severity: Information 
Subject: Notes XO Integration Meeting 09.10.2023 

General Announcement:

  •  

CTRL:

  • nothing major 

DA:

  • nothing major 

EEE:

  • nothing major

VAC:

  • nothing major

XPD:

  • nothing
    •  

DET:

  • nothing

ITDM: 

  •  

XRO:

  • miror setup tuned for grazing incidence with high photon energy.
  • higher backlash at M6, XRO is monitoring this.

LAS:

  • SA2 treacy compressor  smaract stage not operational --> EEE informed
  • SA3 AMPHOS still suffering from low puse energy

UNSYS: 

  • gap scan
  •  

SPB/SFX:

  • nothing major

FXE:

  • nothing major

MID:

  • nothing to report

HED:

  • nothing to report

SCS:

  • no issues

SQS:

  • uTCA in rack room --> EEE will be informed
    • crate power cycled

SXP:

  • M6 backlash

DRC

  •  