Technical integration and coordination SASE1 Status and SASE3 Readiness
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 462     Entry time: 23 Oct 2023, 09:26
Author: Andreas Galler 
Location: General 
Severity: Information 
Subject: Notes XO Integration Meeting 23.10.2023 

General Announcement:

  •  

CTRL:

  • nothing major

DA:

  • nohting major

EEE:

  • nothing 

VAC:

  • nothing

XPD:

  • nothing major

DET:

  • nothing major

ITDM: 

  • nothing major

XRO:

  • nothing major

LAS:

  • SA3 PPLaser up and running
  • SA1 PPLaser went down from time to time
    • Windows PC crashed
    • instabilities in NOPA

UNSYS: 

  • Everything is fine

SPB/SFX:

  • SA1 PPLASER ISSUES

FXE:

  • Smooth

MID:

  • all fine

HED:

  • all fine

SCS:

  •  

SQS:

  • all good

SXP:

  • nothing 

DRC

  •  

PRC

  • 2 long down times over the weekend
    • from 7 to 12:30 fast valve in BC
    • Sun 10:30 - 19:00  broken network switch