Group Selection Page HELP Controls Group ITDM DET Vacuum WP78 FXE SPB HED SQS SXP Sample Environment PSPO XO TS Migrated2Zulip Archived2GitlabPages Archived2PDF MigratedByGroup
SCS Photon Commissioning Team XRO DOC WP74 MID XO_mig XO_Operation SQS Migrated2Zulip
Technical integration and coordination
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 462     Entry time: 23 Oct 2023, 09:26
Author: Andreas Galler 
Location: General 
Severity: Information 
Subject: Notes XO Integration Meeting 23.10.2023 

General Announcement:

  •  

CTRL:

  • nothing major

DA:

  • nohting major

EEE:

  • nothing 

VAC:

  • nothing

XPD:

  • nothing major

DET:

  • nothing major

ITDM: 

  • nothing major

XRO:

  • nothing major

LAS:

  • SA3 PPLaser up and running
  • SA1 PPLaser went down from time to time
    • Windows PC crashed
    • instabilities in NOPA

UNSYS: 

  • Everything is fine

SPB/SFX:

  • SA1 PPLASER ISSUES

FXE:

  • Smooth

MID:

  • all fine

HED:

  • all fine

SCS:

  •  

SQS:

  • all good

SXP:

  • nothing 

DRC

  •  

PRC

  • 2 long down times over the weekend
    • from 7 to 12:30 fast valve in BC
    • Sun 10:30 - 19:00  broken network switch
ELOG V3.1.4-7c3fd00