Message ID: 508     Entry time: 22 Apr 2024, 09:28
Author: Andreas Galler 
Location: General 
Severity: Information 
Subject: Notes XO Integration Meeting 22.04.2024 

General Announcement:

  •  

CTRL:

  • Broker Issue in SA2 on Saturday evening
    • LA2 and SA2 topic restarted

DA:

  •  

EEE:

  • nothing to be reported

VAC:

  •  

XPD:

  • everything fine

DET:

  • nothing major

ITDM: 

  • nothing major

XRO:

  •  

LAS:

  •  

UNSYS: 

  • Everything fine

SPB/SFX:

  • everything worked fine

FXE:

  • nothing to report

MID:

  • all fine

HED:

  •  

SCS:

  • nothing

SQS:

  • nothing

SXP:

  • nothing

DRC

  •  

PRC

  • HED was not taking beam during the SA2 broker issue, as a hardware change was being done
    • by 2 am Sunday the systems were recovered and working

AOB:

  •  