Group Selection Page HELP Controls Group ITDM DET Vacuum WP78 FXE SPB HED SQS SXP Sample Environment PSPO XO TS Migrated2Zulip MigratedByGroup
SCS Photon Commissioning Team XRO DOC WP74 MID XO_mig XO_Operation WP76 EEE
Technical integration and coordination
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther, Page 27 of 33  Not logged in ELOG logo
ID Date Authordown Location Severity Subject
  288   20 Dec 2021, 09:25 Andreas GallerGeneralInformationNotes XO integration meeting 20.12.2021

General Announcement:

  •  

CTRL:

  • no update

DA:

  • nothing

EEE:

  • nothing

VAC:

  • nothing to report

XPD:

  • nothing special, shtudown tasks are in schedule, HXPES / XTED2 cable work ongoing

DET:

  • nothing special

ITDM:

  •  

XRO:

  •  

LAS:

  • lasers ramped down

UNSYS: 

  • APPLEXv inv place, VAC to be closed next year

SPB/SFX:

  • working on mirrors
    • checking vacuum today
  • not clear what is the status with the movement of racks wrt SXP (SPB/SFX optics hutch racks currently powered down)
    • electrical installation?
    • PG comments: Brad won't allow operation until 230 V power distribution is calrified, once Brad gives the OK, the racks can be switched on
      racks are being finalized by EEE, but some checks need electrical power
    • RB: SPB/SFX were promised that the move of the racks were finished before X-Mas, but it seems the electrical work is not up to satandards

FXE:

  • shutdown task in schedule

MID:

  • all fine
    • some loop updates planned for Today

HED:

  •  

SCS:

  •  

SQS:

  • nothing

AOB:

  • light OCD over X-Mas for XPD in case of floowings, power outages.lists will be

  289   05 Jan 2022, 09:29 Andreas GallerGeneralInformationNotes XO Integration Meeting 05.01.2022

General Announcement:

  •  

CTRL:

  • no major updates

DA:

  • no major updates

EEE:

  • 1 MID plC dead
    • replaced on Monday
  • cable work planned for next week
    • HED, SXP

VAC:

  • In general excellent progress
  • closing of M2 XTD2 (SA1) in progress, sealing issues mitigated

XPD:

  • XTD10, XTD6
    • improvements, commissioning ongoing
  • clean room tent water leak reported on 23.12.
    • fixed by TS befroe X-Mas

DET:

  • no major issues

ITDM:

  • Jan 19: dCachce maintenance

XRO:

  • progress as planned
  • changes to existing components will be posted to respective elogs

LAS:

  •  

UNSYS: 

  • progress as planned

SPB/SFX:

  • Vac monitoring recoverd

FXE:

  •  

MID:

  • PLC outage on Jan 1 st caused VAC issues (reported by EEE)
    • fixed
  • no access to MID optics hutch due to interlock test

HED:

  • everything on schedule
  • leak on a hose to humidifier device in A12. This leaked a few litres on the floor.
    • to be fixed by Caverion

SCS:

  • progress as planned

SQS:

  • progress as planned
  297   02 Feb 2022, 08:39 Andreas GallerGeneralInformationNotes XO Integration Meeting 02.02.2022

General Announcement:

  •  

CTRL:

  • observation from DOC
    • macros some times after the upgrade to Python 3.8 --> please contact CTRL?

DA:

  • significant upgrade to Offline Analysis -->
    • proc data won't inlcude a copy of raw data any longer

EEE:

  • fast electronics

VAC:

  • no issues

XPD:

  • no incidents
    • 2 tunnel accesses on Monday --> succesful

DET:

  • DET commissioning at SPB (AGIPD JUNGFRAU 1M), MID (AGIPD), HED (ePIX, JUNGFRAU)

ITDM:

  • E0.604 rack room, Wed next week
    • fixing power distribution units in every rack --> TS and external company will need a full day
    • affected services are: Lab DAQ, LAB control servers (EEE; CTRL, DET), GitLab runners, one machine for data analysis, PLC database, karabo project database (?)
  • Yesterday short interruption with influx reading note --> test requested for next Monday causing a 1 hour interruption

XRO:

  • SA1 / SA2 M3 PBLMs have been equipped with diamond plates and can be used for beam stability measurements
  • Backlash Controls implemented last week --> values
  • report of lost positions of vertical slit in SA3
    • in case of similar issues please contact DOC prior to self fixing.

LAS:

  • SA2 PPL is good
  • SA3 PPL planned to be up today
  • SA1 PPL being investigated as agreed with SA1 instruments

UNSYS: 

  • transparency test  for APPLE X went successful

SPB/SFX:

  • SPB/SFX aligned since yesterday, no issues

FXE:

  • blown fuses in crates --> solved with EEE

MID:

  • all fine

HED:

  • Com yesterday
    • outstanding issue: fastADC not working EEE aware of that

SCS:

  •  

SQS:

  • GATT always worked but very slowly responding
    • OCD contacted
    • Raul comments that this is a known issue and should be communicated to CTRL
    • SH nesures that Raul creates the ticket
  • XTD10_PES
    • digitizer display frozen almost all time (connected to 2 DAQs) --> reported to DOC
    • SH comments that when connecting to two DAQs (tunnel and SQS), should be connected to only one DAQ.

  314   04 Apr 2022, 09:26 Andreas GallerGeneralInformationNotes XO integration meeting 04.04.2022

General Announcement:

  •  

CTRL:

  • PP LAS restarting device servers for upgrading the device tag --> autoinstantiate some servers all topics

DA:

  • Planned maintenance today for Cal and gpfs delayed at least until next Monday

EEE:

  • nothing major to report

VAC:

  • 1 ZZ ongoing to XTD4 to shiled an ion pump controller, suspicion of radiation damage.
    • AK Dump XTD10? --> yes

XPD:

  • similar Diamond cracks as in solid attenuator had been observed in the transmissive imagers
  • Last weeek FEL imager issue had been clarified (image was rotated by 180 °, occured due to faultly config load)

DET:

  • AGIPD1M (SPB/SFX), Friday morning some DAQ issues induced train losses. Didn't happen again after careful checking

ITDM:

  • Issue at HED with data migration --> discussion will take place

XRO:

  • Tomorrow and after tomorrow late shift some CTRL support might be required

LAS:

  • PLL LAS SA1 sync issues (LbSYNC informed and arriving 10:00)
  • PPL LAS3 NOPA setup

UNSYS: 

  • ZZ ongoing

SPB/SFX:

  • Experiment went well, no major issue
  • Run Controller crashd a few times over the weekend. Could be restarted but crashes some time later and has to be restarted

FXE:

  • affecetd by LAS Sync issue
  • issue with doocs panel for shutters (yifeng)

MID:

  • all fine
  • SSRY motor issue (ELMO)
    • Nerea updated the ticket --> motor is working

HED:

  • DA1 got stuck for a while (fixed by restarting)
  • lot of short runs (1min) and only one train isneed from that -> requires fast data migration and analysis -> doesn't always work
    • discussion with ITDM commencing
  • PAM was missing from DAQ

SCS:

  • no major issues
  • RIXS on liquids went well

SQS:

  • mono shift becuase

DOC /DRC

issues with call forwarding

  315   06 Apr 2022, 09:15 Andreas GallerGeneralInformationNotes XO integration meeting 06.04.2022

General Announcement:

  •  

CTRL:

  • influxDB outage (telegraf issue)
    • SA1 and SA3 affected
    • currently fixed but linked to a device in SQS

DA:

  • nothing major

EEE:

  • PLC colleagues are working on CR and support requests
  • pulling cables for SQS and SCS
  • reported to XO uTCA in XTD1
    • remote reboot planned for Friday, reserve ZZ slot for Friday

VAC:

  • repair of XTD2 solid attenuator ongoing

XPD:

  • FD @ SA2

DET:

  • nothing to report

ITDM:

  • nothing to report
  • next Monday GPFS update will take place

XRO:

  • mirror calibration started in SA2
    • beam path through offset mirros not visible -> no beam on M3 pop in, but visible on M2 pop in MCP in beam?
    • JG: no MCP in beam, how about PBLM?
    • LS: no PBLM in beam
    •  

LAS:

  • Sync issue from Monday cannot be replicated by Sebastian -->
  • tests for SPB happening tomorrow

UNSYS: 

  • circular polratizaton lasing achievd in APPLE-X in left and right hand polarization, also linear horizontal and vertical and 45° measured at 900 and 700 eV
    • thanks to UNSYS and DESY APPLE-X comm team.

SPB/SFX:

  • no major

FXE:

  • nothing to add

MID:

  • all fine

HED:

  • nothing to report

SCS:

  • reservation of nodes for jupyter hub.
    • requested during drc hour fix to reserve 3 nodes
      • didn't work out
    • is it possible to reserve 3 nodes by default?
  • Olivier reports there was a misunderstanding and it got fixed very quickly
  • Janusz reports that by standard 4 nodes are reserved for each experiment.

SQS:

  • nothing to report

 

  316   11 Apr 2022, 09:10 Andreas GallerGeneralInformationNotes XO integration meeting 11.04.2022

General Announcement:

  •  

CTRL:

  • small intervention --> udpate of karabo-gui client exflagteway

DA:

  • maxwell gpfs software maintenance --> offline calibration pipeline affected see ITDM

EEE:

  • OCD call on rack 2.01 which was powered down. After fuse repaired

VAC:

  • see above ...

XPD:

  • Rack 2.01 --> Camera of SR imagare is not working
    • situation not clear, being investigated --> IP conflict?
    • Janusz suggests to powercycle the camera

DET:

  • many to report

ITDM:

  • 10:00 maxfell gpfs update

XRO:

  • SA2 mirror calibration

LAS:

  • remainder change of set point for SCS to 112 kHz

UNSYS: 

  • nothing to report

SPB/SFX:

  • nothing to report

FXE:

  • preparing for user experiments
    • concerned about optical sync of PP Laser, probelm of last week was fixed but no reason found
    • test last thursday optical sync lost again while moving optical delay stage
    • FXE

MID:

  • alignment of optical laser alignment in joined hutch.
    • please

HED:

  • nothing to report

SCS:

  • nothing to report
    •  

SQS:

  • last week Thursday night
    • mono drift investigated --> preliminary analyisis points to the grating as the drifting component

  317   13 Apr 2022, 09:28 Andreas GallerGeneralInformationNotes XO Integration Meeting 13.04.2022

General Announcement:

  • No User operation meeting this Friday, instead cw 16 / cw 17 check will happen in Daily Operations Meeting at 15:30 on Thu Apr 14. Link available on ttfinfo in XFELelog

CTRL:

  • nothing major to report

DA:

  • nothing major to report

EEE:

  • nothing major to report

VAC:

  • nothing to report

XPD:

  • nothing to report

DET:

  • offline calib with JUNGFRAU --> tickets closed already

ITDM:

  •  

XRO:

  • request to SA1 instruments
    • please check the repaired XTD2 solid attenuators
    • attenuators cannot sustain too much power, offline discussion follows
  • SA2 mirror recalib
    • roll of M1 and M2 was completely misaligned, recalibration successful
    • geometrical center of the kinematic system roughly identified
      • required for Euler MDL,

LAS:

  • nothing to report

UNSYS: 

  • nothing to report

SPB/SFX:

  • nothing to report

FXE:

  • not present

MID:

  • pump probe looks stable and getting ready for the user
    • BAM doocsbridge stopped --> manual restart necessary

HED:

  • nothing to report

SCS:

  • nothing to report
    •  

SQS:

  • nothing to report

DRC

  • one hour data lost in influxDB in SA2

PRC

  •  

 

  320   27 Apr 2022, 09:04 Andreas GallerGeneralInformationNotes XO Integration Meeting 27.04.2022

General Announcement:

  •  

CTRL:

  • bug noticed in BEckhoof karabo device --> already fixed from some topics, see xo-info comm from yesterday

DA:

  • all fine

EEE:

  • CRL-HED-OPT isue solved

VAC:

  • two devices went into error --> likely because of Beckhoff Karabo bug

XPD:

  • nothing to report

DET:

  • AGIPD 1M at SPB partially vented yesterday --> detector went into interlock, no damage
    • who should be called at SPB (or any instrument for that matter)
    • Turbo pumps went into error state which triggered the partial vent --> karabo Beckhoff update?
    • Wajid comments: karabo beckhoff update does not correlate with this incident, judging from time stamps

ITDM:

  • no update

XRO:

  • nothing to report

LAS:

  • nothing to report

UNSYS: 

  • not present

SPB/SFX:

  •  

FXE:

  • software limits of phase shifter of PP Laser
    • DK solved by PP Laser

MID:

  • all fine at MID
    • HXRSS very much appreciated

HED:

  • HIREX offset

SCS:

  •  

SQS:

  •  

DRC

  •  

PRC

  • SCS incident on Monday, photon energy scanning script was left running --> had to be stopped manually

  338   04 Jul 2022, 09:30 Andreas GallerGeneralInformationNotes XO Integration Meeting 04.07.2022

General Announcement:

  • M. Döring:
    • almost all of the activities that should have been done until last Friday had been done

CTRL:

  • last week karabo topic updates had finishedexcept for LAS
  •  

DA:

  • nothing

EEE:

  • SA3 exit slit

VAC:

  • leak search on M6 (SA3) chamber
  • leak search in XTD9
  • all in all well

XPD:

  • almost all tasks have been completed
  • XTD1 new crate connected on Friday,

DET:

  • nothing

ITDM:

  • all updates are finsihed
  • some activities continuing on the offsite --> should be comüpletely transparent
  • after the prox change there are some PCs which are using the old host names --> relavant people will be contacted by Janusz Szuba

XRO:

  • M6 mirror installation beign finished
    • end switch checks shoudl be finished by today
    • ramp up procedure being written down
      • instruments are asked to submit any additional requests for ramp up

LAS:

  • fastADCs should be finished by Wed this wek

UNSYS: 

  • control system has to be adjusted after removal of APPLE X, i.e. the control system looks for motors and

SPB/SFX:

  • checks

FXE:

  • motor commissioning ongoing

MID:

  • nothing
    •  

HED:

  • when modifying cables downstairs, make sure modules upstairs are switched off

SCS:

  • PLC updates

SQS:

  • not present

DRC

  •  

PRC

  • SCS incident on Monday, photon energy scanning script was left running --> had to be stopped manually

  342   18 Jul 2022, 09:31 Andreas GallerGeneralInformationNotes XO integration meeting 18.07.2022

General Announcement:

  • none

CTRL:

  • fastADC karabo Version updated
    • everything looks fine
  •  

DA:

  • nothing

EEE:

  • PLC and cabling as scheduled
  • fastADC update
    • MID and SPB issues being solved by lunch time

VAC:

  • HED Mono
  • SXP tunnel interface

XPD:

  • ZZ on Tuesday for XTD1 SR imager camera reset

DET:

  • DSSC update
    • test not yet conclusive on whether operation is safe or not.
    • current suggestion: postpone experiments until repair is done
  • AGIPD firmware update went well

ITDM:

  • nothing

XRO:

  • not present

LAS:

  • Timing issues solved, solved by Lars Froehlich
  • LAS may suffer from limited available resources

UNSYS: 

  • all fine

SPB/SFX:

  • issue with Elmo motors

FXE:

  • nothing

MID:

  • nothing
    •  

HED:

  • nothing

SCS:

  • mobile compressor will be used this week

SQS:

  • nothing

DRC

  •  

PRC

  •  

  343   20 Jul 2022, 09:30 Andreas GallerGeneralInformationNotes XO Integration Meeting 20.07.2022

General Announcement:

  • none

CTRL:

  • everzthing as planned
  •  

DA:

  • currently there is a gpfs issue affecting the online cluster
    • delays in online analysis have to be expected
    • delays in obtaining new constants, can take much longer than normally -->

EEE:

  • nothing to report
  • a couple of boards are not reachable, maybe connected to the power glitch we've had

VAC:

  • ongoing activities
    • XTD 6&9
      • HED Mono works closing
      • SXP beamline ready for beam
    • operation at very low photon energies at SA3:
      • GATT will use Ar --> System had been tested
  • power glitch yesterday was seen in water distribution

XPD:

  • ZZ on Tuesday for XTD1 SR imager camera
    • successful

DET:

  • nothing major to report

ITDM:

  • nothing

XRO:

  • nothing major to report
    •  

LAS:

  • nothing major to report

UNSYS: 

  • nothing to report

SPB/SFX:

  • issue with Elmo motors had been mitigated
  • DA and Detector recovery

FXE:

  • acces to air comperssor and support for moving LPD required for July 22nd for BTM tests.

MID:

  • after loop update wrong parameters had been put to LDM motors
    •  

HED:

  • not present

SCS:

  • nothing to report

SQS:

  • nothing to report

DRC

  •  

PRC

  •  

  344   25 Jul 2022, 09:14 Andreas GallerGeneralInformationNotes XO Integration Meeting 25.07.2022

General Announcement:

  •  

CTRL:

  • Today "bring up" works at FXE

DA:

  • Nothing special to report

EEE:

  • PLC team is trying to find solutions for slowness in big loops

VAC:

  • nothing to report

XPD:

  • nothing special

DET:

  • nothing major to report

ITDM:

  • SA2 GPFS updates today

XRO:

  • not present

LAS:

  • SA1 AMPHOS back as

UNSYS: 

  • K- Mono Scan last week
    • S. Arbeghyan assisted but new undultaor offsets will only be implemented after Aug 5th

SPB/SFX:

  • nothing special to report
  • bring up days are very successful

FXE:

  •  

MID:

  • ITDM please keep MID in the loop with SA2 GPFS updates, as MID plans to save data today
  • opening of the beam shutter is an issue
    • over the weekend MID was forced to open

HED:

  • shutter issue as MID

SCS:

  • nothing to report

SQS:

  • nothing to add

DRC

  •  

PRC

  • s

SH

  • VAC loops SA1 SA2, don't panic because of slowness

 

  352   24 Aug 2022, 09:28 Andreas GallerGeneralInformationNotes XO Integration Meeting 24.08.2022

General Announcement:

  •  

CTRL:

  • nothing special

DA:

  • nothing

EEE:

  • actions from Monday (SA3 PLC master update,  PNACT testing) successful

VAC:

  • vacuum ok

XPD:

  • nothing

DET:

  • nothing major to report

ITDM:

  • nothing to report

XRO:

  • nothing to discuss

LAS:

  • nothing

UNSYS: 

  • nothing

SPB/SFX:

  • nothing

FXE:

  • all fine

MID:

  • all fine

HED:

  • undulator setting off by 100 eV --> HED had means to accurately measure the delivered photon energy and compensate for that.

SCS:

  • nothing

SQS:

  • nothing

DRC

  • nothing

PRC

  • nothing

 

  365   12 Oct 2022, 09:16 Andreas GallerGeneralInformationNotes XO integration meeting 12.10.2022

General Announcement:

  •  

CTRL:

  • nothing major

DA:

  • nothing special

EEE:

  • nothing special

VAC:

  • XTD6 HED monochromator
    • pumping down continues

XPD:

  • nothing to report

DET:

  • nothing to report

ITDM:

  • SA2 online system (gpfs) one enclosure is bahving strangely, intervention may be required --> to be investigated

XRO:

  • XTD6/XTD9 tunnel works

LAS:

  • no issues

UNSYS: 

  • cell 19, 20, 21 motors for phase shifters had been replaced. Delivery for lead shields is going to be next year --> installation will have to be done through ZZ access
    • radiation damage is high after chicane, delivery time for new motors is 1 years, 7 are left in stock

SPB/SFX:

  • nothing special

FXE:

  • nothing to report

MID:

  • all fine at MID

HED:

  • nothing to report

SCS:

  • hRIXS combined motuion requires PLC to be exchanged

SQS:

  •  

DRC

  •  

PRC

  •  

  366   17 Oct 2022, 09:31 Andreas GallerGeneralInformationNotes XO Integration Meeting 17.10.2022

General Announcement:

  •  

CTRL:

  • nothing major

DA:

  • nothing special

EEE:

  • OCD call on Friday
    • ion pump controller broken in XTD1

VAC:

  • see EEE --> additionally over the weekend the pump was taken out of the interlock

XPD:

  • nothing

DET:

  • JungFrau damagat at SPB/SFX in cw 40
    • two powder rings permantnly burned into detector

ITDM:

  • SA2 online system (gpfs) one enclosure is bahving strangely, --> fixed no replacement needed

XRO:

  • nothing to report

LAS:

  • crash of PPLaser in SA1 over the weekend
    • TRGDly was upgraded recently/ crashed for SPB --> TRGDly device being rolled back and PPLAS1 should be back up today.

UNSYS: 

  • ccell 25 SA1 fixed --> now only 6 motors are left.
    • Lead shields ETA beginning of February --> will have to be done through ZZ
    • broken motors and encoders are sent back to Beckhoff
      • repair time approx. 2 - 3 months

SPB/SFX:

  • Jet control stopped
  • PPLAS
    • on Friday there was no LAS output --> fixed
      • no LAS OCD in blue weeks, and on Friday no LAS group member on site --> earliest service on Saturday through good will.
    • shift change not successful due to miscommunication
      • SPB let the laser run over night for measurements --> FXE did shift change over night eventually destroying the SPB measurement
    • see LAS TRGDLY device
  • SPB requests to not upgrade software thorugh run for PPLasers.
    • recently there were some upgrades on a Monday which then later fail for operation
  • SPB notest that there is only limited OCD by LAS group and then LAS cannot cover critical components

FXE:

  • set up built for User Experiment
    • HallCrew supported in build up
    • LAS use --> see SPB/SFX

MID:

  • all fine at MID

HED:

  • user experiment being set up

SCS:

  • not present

SQS:

  • nothing to report

DRC

  •  

PRC

  •  

  367   19 Oct 2022, 08:45 Andreas GallerGeneralInformationNotes XO Integration Meeting 19.10.2022

General Announcement:

  •  

CTRL:

  • nothing major

DA:

  • nothing special

EEE:

  • Group retreat on Monday, Tuesday next week --> OCD available
    • ion pump controller broken in XTD1

VAC:

  • not present

XPD:

  • nothing

DET:

  • 25th of October group retreat

ITDM:

  • nothing major
  • change of FastX on max-display from FastX2 to FastX3

XRO:

  • nothing to report

LAS:

  • AMPHOS Shutter Laser issue

UNSYS: 

  • ccell 25 SA1 fixed --> now only 6 motors are left.
    • Lead shields ETA beginning of February --> will have to be done through ZZ
    • broken motors and encoders are sent back to Beckhoff
      • repair time approx. 2 - 3 months

SPB/SFX:

  • Laser interlock error
  • extra foam 4 center modules from AGIPD
    • DOC / DRC to be contacted
  • jet motion
    • dynamic brake engaged because the cable was loose --> fixed

FXE:

  • extra foam issues had been sorted out
    • 16 cell mode of Jungfrau not being used

MID:

  • all fine at MID

HED:

  • collimated beam showed jitter --> downfocussing reduced the effect
  •  

SCS:

  • nothing major

SQS:

  • nothing to report

DRC

  •  

PRC

  •  
  410   12 Apr 2023, 09:23 Andreas GallerGeneralInformationNotes XO Integration meeting 12.04.2023

General Announcement:

  •  

CTRL:

  • not much to report

DA:

  • not much more to report

EEE:

  • not much to add

VAC:

  • successful intervention for Turbo Pump intervention of PES in XTD10

XPD:

  • Diamond Detector Study in SA2 on Thu

DET:

  • not much to report

ITDM: 

  • last week was super successful with SPB taking 5 PB of data
    • however please provede better estimations, here a factor of 5 overshoot was seen.

XRO:

  • not present

LAS:

  •  

UNSYS: 

  • one terminal SA3 cell 5 issue over the week --> replaced on Tuesday

SPB/SFX:

  • EPS issue SPB_XTD9_IMGPI out siwtch not working --> limited to two pulses --> taken out of EPS interlock
    • later repaired by XPD

FXE:

  • nothing

MID:

  • all fine

HED:

  • excellent performance of the self-seeded x-ray beam last week, for the user experiment #3326 (Fri-Sat).
    The beam is very stable both in terms of intensity (700-800 uJ constant) and the pointing jitter! Users were very happy with the performance and the experiment was successful. 

SCS:

  • issues with electronics
    • EEE contacted and Bernard going to support today

SQS:

  • not present

SXP:

  • nothing to report

DRC

  • n/a

PRC

  • n/a
  411   17 Apr 2023, 09:26 Andreas GallerGeneralInformationNotes XO Integration meeting 17.04.2023

General Announcement:

  •  

CTRL:

  • nothing major

DA:

  • nothing major

EEE:

  • nothing major

VAC:

  • nothing major

XPD:

  • nothing

DET:

  • nothing

ITDM: 

  • nothing

XRO:

  • not present

LAS:

  • all good

UNSYS: 

  • everything fine

SPB/SFX:

  • nothing

FXE:

  • nothing

MID:

  • XRO did alignment in XTD2 --> successful, euler MDL recommissioned

HED:

  • nothing

SCS:

  • issues ar being taken care of

SQS:

  • XRO investigated damage threshold mirrors 

SXP:

  • nothing 

DRC

  •  

PRC

  •  
  412   19 Apr 2023, 09:27 Andreas GallerGeneralInformationNotes XO Integration meeting 18.04.2023

General Announcement:

  •  

CTRL:

  • nothing major

DA:

  • nothing major

EEE:

  • nothing major

VAC:

  • nothing major

XPD:

  • nothing major

DET:

  • nothing major

ITDM: 

  • jhub update went though at 9:00

XRO:

  • nothing major

LAS:

  • failure of a piazo in the beam stability in SA2, laser is being recovered

UNSYS: 

  •  

SPB/SFX:

  •  

FXE:

  • nothing mjor

MID:

  • waiting for laser
  • missing data from the JF, and motor 

HED:

  • nothing major

SCS:

  • nothing major

SQS:

  • nothing major

SXP:

  •  

DRC

  • qiet week

PRC

  • quiet week
  433   10 Jul 2023, 09:30 Andreas GallerGeneralInformationNotes XO Integration meeting 10.0723
General Announcement:
- 

CTRL:
- Bring Up Days start next Monday

DA:
- DA and DET sessions are alwys the same days following CTRL and EEE

EEE:
- nothing to report

VAC:
- VAC is ready for beam

XPD:
- Nothing to report.

DET:
- Nothing to report

ITDM: 
- Nothing to report.

XRO:
- nothing to report

LAS:
- Nothing to report.

UNSYS:
- nothing to report


SPB:
- Couple of open things with crates --> EEE in discussion

FXE:
- Nothing to report

MID:
- Nothing to report.

HED:
- Not present.

SCS:
- Not present

SQS:
- Not present.

SXP:
- Not present.
ELOG V3.1.4-7c3fd00