Technical integration and coordination
SASE1 Status and SASE3 Readiness
|
Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther |
Not logged in |
 |
|
Message ID: 559
Entry time: 23 Oct 2024, 09:19
|
Author: |
Andreas Galler |
Location: |
General |
Severity: |
Information |
Subject: |
Notes XO Integration Meeting 23.10.2024 |
|
|
General Announcement:
CTRL:
- MPOD voltage limiter of PES is being investigated
DA:
EEE:
- see SCS report issues with HXRIXS PLC
VAC:
XPD:
- continuing assessing the damage of the PES, possibly supported by ZZ next week.
- calorimater removed from HED hutch
DET:
ITDM:
XRO:
LAS:
UNSYS:
- presenting Thomas Schmidt
- all fine with undulators , last phae shifter in SA3 (cell 26) ZZ pending
SPB/SFX:
- preparing for IHR, nothing special
FXE:
MID:
HED:
SCS:
- mechanical issues at HRIXS, issues with associated PLC as it was crashing, however EEE (SDilvia and Nerea) brought the PLC back up again
SQS:
SXP:
DRC
- gentle reminder to participate in the DRC journey fixe
PRC
AOB:
|