  14   01 Mar 2019, 14:18 Adriano ViolanteGeneralInformationReport after dispatch meeting 09.00SPB/SFX


Today Loop 8 could be ready
(AE)
Agipd - visualization of
  
  15   04 Mar 2019, 10:38 Adriano ViolanteGeneralInformationMinutes of the dispatch meeting 09.30SPB/SFX


Ongoing discussions with
the support groups to organize the shutdown
  
  16   06 Mar 2019, 10:31 Adriano ViolanteGeneralInformationMinutes of the Technical integration meeting 06.03.19 SPB/SFX


CSS component commissioning.
Concept and implementation finalized. EPLAN
  
  17   08 Mar 2019, 13:01 Adriano ViolanteGeneralInformationMinutes of the dispatch meeting 09.00SPB/SFX


Only minor issues being
addressed with the support groups.


FXE
  
  18   11 Mar 2019, 11:58 Adriano ViolanteGeneralInformationStatus report after dispatch meeting 09.30SPB/SFX


Experiments were succesfull
Calibration
pipeline has issues - being fixed
Detailed
  
  19   13 Mar 2019, 11:11 Adriano ViolanteGeneralInformationMinutes of the Technical integration meeting 13.03.19 SPB/SFX


CRL implementation in the
hutch will happen in April. AE and EET involved.
 ElectricalSafety.pdf 
  20   15 Mar 2019, 11:27 Adriano ViolanteGeneralInformationMinutes after dispatch meeting 09.00SPB/SFX


No major issues reported
Motors
in Loop 14 have been tested and problems
  
  21   18 Mar 2019, 10:04 Adriano ViolanteGeneralInformationStatus report after dispatch meeting 09.30SPB/SFX


No major issues reported
Crates
for the CRL will be installed today. Test
  
  22   20 Mar 2019, 14:07 Adriano ViolanteGeneralInformationMinutes of the Technical integration meeting 20.03.19 SPB/SFX


CRL implementation in the
hutch will happen in April. AE and EET involved.
  
  23   25 Mar 2019, 11:38 Adriano ViolanteGeneralInformationStatus report after dispatch meeting 09.30SPB/SFX


The Julabo chiller for
the AGIPD detector broke. After intervention
  
  24   27 Mar 2019, 10:48 Adriano ViolanteGeneralInformationMinutes of the Technical integration meeting 27.03.19 SPB/SFX


CRL implementation in the
hutch will happen in April. AE and EET involved.
  
  25   29 Mar 2019, 11:02 Adriano ViolanteGeneralInformationReport after dispatch meeting 09.30SPB/SFX

FXE

​SQS
  
  26   01 Apr 2019, 10:21 Adriano ViolanteGeneralInformationReport after dispatch meeting 09.30SPB/SFX


The quadrant motion system
test for the AGIPD presented some issues
  
  28   03 Apr 2019, 10:44 Adriano ViolanteGeneralInformationMinutes of the Technical integration meeting 03.04.19 SPB/SFX


CRL implementation in the
hutch. Cables at the back of the crate have
  
  29   05 Apr 2019, 10:07 Adriano ViolanteGeneralInformationReport after dispatch meeting 09.00SPB/SFX


5Hz mode tests started
(SPB/SQS) and partially successful. A detailed
  
  30   08 Apr 2019, 10:48 Adriano ViolanteGeneralInformationReport after dispatch meeting 09.30SPB/SFX


5Hz mode tests started
(SPB/SQS) and partially successful. A detailed
  
  31   10 Apr 2019, 10:54 Adriano ViolanteGeneralInformationMinutes of the Technical integration meeting 10.04.19 SPB/SFX


CRL implementation in the
hutch. Tests can start today.
CSS
  
  32   12 Apr 2019, 10:41 Adriano ViolanteGeneralInformationStatus report after dispatch meeting 09.30SPB/SFX


Hercules students period.
During the night a pump failed and recovered
  
  33   15 Apr 2019, 09:55 Adriano ViolanteGeneralInformationStatus report after dispatch meeting 09.30SPB/SFX


Tomorrow set up of the
donwstream interaction region will start.
Jungfrau
  
  34   17 Apr 2019, 11:34 Adriano ViolanteGeneralInformationMinutes of the Technical integration meeting 17.04.19 SPB/SFX


CRL motors being tested.
Today BB (AE) will check the status.
CSS
  