  36   26 Apr 2019, 12:28 Adriano ViolanteGeneralInformationReport after dispatch meeting 09.00SPB/SFX


IRD commissioning ongoing.
CRL
motors being tested. --> Mechanical issue
  
  37   29 Apr 2019, 10:04 Adriano ViolanteGeneralInformationStatus report after dispatch meeting 09.30SPB/SFX


IRDa commissioning
ongoing. Focus (<5um) in the second interaction
  
  38   03 May 2019, 14:07 Adriano ViolanteGeneralInformationReport after dispatch meeting 9:00SPB/SFX


IRDa commissioning
ongoing. First images have been taken with
  
  39   06 May 2019, 10:20 Adriano ViolanteGeneralInformationStatus report after dispatch meeting 09.30SPB/SFX


IRDa commissioning
ongoing. 
For this week AGIPD
  
  40   08 May 2019, 10:10 Adriano ViolanteGeneralInformationMinutes of the Technical integration meeting 08.05.19 SPB/SFX


IRDa commissioning
ongoing. 
CSS. Limit switches
 Technical_Integration_Meeting_07.05.2019_-_Copy.pptx 
  41   10 May 2019, 10:52 Adriano ViolanteGeneralInformationReport after dispatch meeting 09.00SPB/SFX


IRDa commissioning
successful. A. Mancuso thanked all the people
  
  42   13 May 2019, 11:24 Adriano ViolanteGeneralInformationReport after dispatch meeting 09.30SPB/SFX


The gear ratio of the CSS
is unclear but this was already known and
  
  43   15 May 2019, 12:53 Adriano ViolanteGeneralInformationMinutes of the Technical integration meeting 15.05.19 SPB/SFX


Nano KB mirrors and CSS
controls are OK
Digitizers have
  
  44   17 May 2019, 10:47 Adriano ViolanteGeneralInformationStatus report after dispatch meeting 09.00SPB/SFX


ADC have been requested.
HW should be already installed (SPB to check).
  
  50   03 Jun 2019, 12:57 Adriano ViolanteGeneralInformationStatus report after dispatch meeting 09.30SPB/SFX


No major issues.


FXE


Tool to save motor positions
  
  52   07 Jun 2019, 11:53 Adriano ViolanteGeneralInformationReport after dispatch meeting 09.00FXE

SPB/SFX


few days of beamtime remaining,
  
  53   12 Jun 2019, 12:40 Adriano ViolanteGeneralInformationMinutes of the Technical integration meeting 12.06.19 FXE

SPB/SFX

SCS
  
  54   14 Jun 2019, 10:47 Adriano ViolanteGeneralInformationStatus report after dispatch meeting 09.00FXE

SPB/SFX


Getting ready for the shutdown.
  
  55   17 Jun 2019, 10:43 Adriano ViolanteGeneralInformationReport after dispatch meeting 09.30FXE


Floor is being re-worked.
Experiment hutch is not accessible until
  
  56   19 Jun 2019, 10:55 Adriano ViolanteGeneralInformationMinutes of the Technical integration meeting 19.06.19 FXE

SPB/SFX


No major issues
Starting
  
  58   21 Jun 2019, 10:13 Adriano ViolanteGeneralInformationStatus report after dispatch meeting 09.00FXE

​SPB/SFX


An AC device in the control
  
  59   24 Jun 2019, 09:53 Adriano ViolanteGeneralInformationStatus report after dispatch meeting 09.30FXE


CRLs mainteinance has been
completed.


​SPB/SFX
  
  60   26 Jun 2019, 10:22 Adriano ViolanteGeneralInformationMinutes of the Technical integration meeting 26.06.19 XO

From now on A. Galler will join
the technical integration meeting. Therefore
  
  61   28 Jun 2019, 11:25 Adriano ViolanteGeneralInformationStatus report after dispatch meeting 09.00XO

FXE

SPB/SFX
  
  62   01 Jul 2019, 10:07 Adriano ViolanteGeneralInformationStatus report after dispatch meeting 09.30XO

FXE

SPB/SFX
  