Technical integration and coordination SASE1 Status and SASE3 Readiness
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther, Page 24 of 29  Not logged in ELOG logo
ID Date Author Location Severity Subject Text Attachments
  114   28 Apr 2020, 16:19 Frederik Wolff-FabrisGeneralInformationNotes XO Integration meeting 27.04.2020General Announcement:
- The CTRL group has received 3 Control Network
tasks that can be carried out this week;
  
  113   24 Apr 2020, 13:48 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 24.04.2020Relaxation control network: 
- CTRL and XO remind the groups to submit
the planned activities on e.g. scenes, projects,
  
  112   23 Apr 2020, 10:04 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 22.04.2020General Announcement:
- An e-mail was sent yesterday about the
relaxation of restrictions on the control
  
  111   20 Apr 2020, 10:59 Frederik Wolff-FabrisGeneralInformationNotes Dispatch Meeting 20.04.2020General:
- Desy informed a power glitch occurred on
Thursday 16th at 04:55AM. TS has not seen
  
  110   15 Apr 2020, 09:03 Andreas GallerGeneralInformationTechnical Integration Meeting 15.04.2020

CTRL:


notificagion service device
  
  109   08 Apr 2020, 08:45 Andreas GallerGeneralInformationTechnical Integration Meeting 08.04.2020

CTRL:


no bigger issues
announcement:
  
  108   06 Apr 2020, 09:50 Frederik Wolff-FabrisGeneralInformationnotes Dipatch Meeting April 6th, 2020CTRL:
- It was remotely observed that some cameras
were consuming too much memory. By remotely
  
  107   01 Apr 2020, 09:19 Andreas GallerGeneralInformationTechnical Integration Meeting 01.04.2020

CTRL:


productive meeting with
  
  Draft   30 Mar 2020, 08:57 Andreas Galler   CTRL:


Broker Pile Up in 4 topics
over the weekend

LAS affected
  
  105   25 Mar 2020, 09:32 Andreas GallerGeneralInformationTechnical Integration Meeting 25.03.2020Currently EuXFEL
enforces a hand-off policy for instrument/tunnel
hardware. That includes remote control of
  
  104   23 Mar 2020, 08:57 Andreas GallerGeneralInformationnotes Dispatch meeting Mar 23 2020Currently EuXFEL
enforces a hand-off policy for instrument/tunnel
hardware. That includes remote control of
  
  103   18 Mar 2020, 09:26 Andreas GallerGeneralInformationTechnical Integration Meeting 18.03.2020

SPB:


interument parked
power
  
  102   16 Mar 2020, 09:36 Frederik Wolff-FabrisGeneralInformationNotes Dipatch Meeting March 16th, 2020 FXE:
- Beamline is in safe state;
- Minor Jungfrau calibration issues over
  
  101   10 Mar 2020, 12:44 Frederik Wolff-FabrisGeneralInformationnotes Dipatch Meeting March 9th, 2020* Users are scheduled to be here this week
(4 beamlines in user runs). SPB, HED, MID
report several users have cancelled the travel.
  
  100   04 Mar 2020, 08:49 Andreas GallerGeneralInformationnotes Dispatch meeting Mar 2 2020SPB:


AGIPD improvement campaign
great success
EEE --> 2nd C&C
  
  99   26 Feb 2020, 09:06 Andreas GallerGeneralInformationnotes Dispatch meeting Feb 24 2020SPB:


nothing to report


FXE:


not present due to group
  
  98   17 Feb 2020, 12:02 Frederik Wolff-FabrisGeneralInformationnotes Dipatch Meeting Feb. 17th, 2020FXE:
Nothing to report: no issues;
  
  97   10 Feb 2020, 10:12 Frederik Wolff-FabrisGeneralInformationNotes Dispatch meeting Feb 10th, 2020SPB: Nothing to report;

FXE:  Everything ongoing; nothing special
  
  96   22 Jan 2020, 09:16 Andreas GallerGeneralInformationnotes Dispatch meeting Jan 20 2020

SPB:


nothing to report


FXE:
  
  95   15 Jan 2020, 09:09 Andreas GallerGeneralInformationnotes Dispatch meeting Jan 13 2020

SPB:


Testing coordinated movement
  