General Announcement:
- Test of automatic switch of power bridge is shifted to Feb.2: this affects all devices connected to orange or green power sockets (no power for few seconds/minute). General e-mail will be sent. Instruments will need to care for equipment which is connected to these sockets. This also affects the E0 level as well as office space in XHQ. Pease plug devices out or re-plug in other sockets.
- The Covid-19 regulations continue valid. Only critical work in the XHEXP1 or tunnel activities shall take place.
- Work on the Soft Mono in XTD10 (SA3) takes place this week. XRO and ME asks everybody to do not move any motors in this device during the whole week.
CTRL:
- New Script to fix label issues in Karabo is ready and will be run today. An e-mail will be sent.
- ITDM and CTRL managed to get updated the “Read the docs”. It runs properly.
DA:
- Not present due to Satellite Workshop.
EEE:
- nothing to report
VAC:
- continuing with tunnel works
XPD:
- Ongoning with few tasks in the tunnel
DET:
- Not present
ITDM:
- nothing to report. Offline GPFS under work today: no Maxwell access during this time.
XRO:
- Not present. Please see general announcements on the Soft Mono.
LAS:
- Error with remote operation on mirrors for SA3/SQS PP-laser is found. A discussion after the meeting will take place between LAS and XO.
UNSYS:
- Nothing to report
SPB:
- Nothing to report
FXE:
- Nothing to add
MID:
- all fine
HED:
- Nothing to report
SCS:
- Nothing to report
SQS:
- Nothing to report |