SASE1 Status and SASE3 Readiness
|
Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther |
Not logged in |
|
|
Message ID: 180
Entry time: 23 Nov 2020, 11:33
|
Author: |
Frederik Wolff-Fabris |
Location: |
General |
Severity: |
Information |
Subject: |
Notes XO Integration Meeting 23.11.2020 |
|
|
General Announcement:
- An e-mail to the readiness and stgl mailing lists was sent regarding the calendar share and updated task list. Please contact xo-planning@xfel.eu in case of any issue.
- Desy has made mandatory for the tunnel works the use a community mask all the time and a FFP2 mask if distance between two persons is less than 1.5m.
CTRL:
- CTRL sent requests to the DA colleagues. S. Hauf asks the colleagues to take a look and have a discussion afterwards.
- Karabo deployment on FXE will take place on Wednesday.
M. Turcato says one DET person must be back to work on that day to switch Detector off and on by again: Wed afternoon or Thursday morning it shall be OK.
DA:
- Nothing to report.
EEE:
- PLCs will start shutdown with planned activities on today and tomorrow in SA3 instruments.
VAC:
- Not present.
XPD:
- Plan for XGM/SCS is to keep it running (under vacuum). XPD reminds SCS people to keep XGM on vacuum.
DET:
- AGIPD intervention: is progressing quite well and advancing.
A. Violante says it is progressing faster than expected and many small issues were solved during the weekend; first quadrant was already re-mounted and tested.
By the end of this week an update on time planning will be made.
ITDM:
- Today ITDM starts the update of offline storage system (unavailable all day).
- The update on the online cluster system will start today in SA1 and then SA2 and SA3. It will not be available until Wednesday.
XRO:
- Working on the winter shutdown.
LAS:
- Carrying on planned maintenance work.
UNSYS:
- Not present.
SPB:
- AGIPD intervention is going well and is under control.
FXE:
- Cabling works starting today in the hutch.
- A. Galler asks if calibration of LPD was done. D. Khakhulin mentions that the raw data was used and calibration constants were not used.
M. Turcato says one has to discuss together with calibration team.
MID:
- All fine.
HED:
- Nothing to report.
SCS:
- Nothing to report.
SQS:
- Nothing to report. |